PERFORMANCE WORK STATEMENT (PWS)

Delivery and Installation of Vault Restrooms New Melones Lake, Sonora, CA.

Dated February 9, 2023

1.0 INTRODUCTION: New Melones Lake: Reclamation manages projects and lands throughout the United States. In California, these projects consist of water storage and conveyance systems such as dams, wells, canals, and pumping stations; hydroelectric power plants; a regional power and water control center; developed recreation sites; and administrative and maintenance offices. New Melones Lake is one of these Reclamation projects and is managed by New Melones Lake staff for substantial recreation opportunities.

2.0 SCOPE: The purpose of this contract is to provide and install two (2) single vault restrooms at two (2) separate locations. One vault restroom will be installed at the Mark Twain Recreation Area and at the Equestrian Staging Area in the Peoria Wildlife Area.

The vault restrooms must be:

1. The vault toilets must be fully ADA compliant facilities;

2. The vault toilets shall be earth-tone colors (brown, tan, etc);

3. Constructed of concrete;

4. Engineered to withstand extreme heat, zone-4 seismic loads, and large rain events;

5. Provide waste storage in a sealed vault of at least 1000 gallons;

6. Provide proper venting to minimize odors;

7. Roof vents shall be designed to prevent rocks, sticks or wildlife from entering the vents;

8. Provide interior LED lighting at night that is recharged by solar cells;

9. The vault restroom must provide an interior wastebasket;

10. Solar panels must be tamper resistant and protected from vandalism;

11. Interior and exterior surfaces must be readily cleanable of graffiti and vandalism;

12. Waste vault must be in-ground;

13. Vault restroom must be installed at ground level

14. Access for waste vault pumping must be on the exterior and lockable.

The contractor shall be responsible for delivery and complete installation of the vault toilet restroom, including any earth and crane work at each installation location. Installation work must comply with limitations set forth in the NEPA documents for this project. After each installation, the contractor shall be responsible for removing the extra soil.

The handiness of each vault restroom will be selected in consultation with the COR prior to shipment of the vault restroom.