Plans and Specifications for Bldg 644 Telecom Rpr Phase 1.pdf

PDF 10 MB Posted

Attached to
Ft Devens, MA Telecom Repair and Modernization Federal contract opportunity
Solicitation number
W15QKN-20-Q-5398
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to Ft Devens, MA Telecom Repair and Modernization, newest first.
File Type Posted
MA20200001.docx DOCX document
W15QKN-20-Q-5398.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SPECIFICATIONS FOR

BUILDING 644 TELECOMMUNICATIONS

REPAIR AND MODERNIZATION, PHASE 1

12 Lexington Street Devens, MA 01434

June 2020 Project No. AR-83392-0P

UNITED STATES ARMY GARRISON

FORT DEVENS, MASSACHUSETTS

Project No. AR-83392-0P Building 644 Telecommunication System Repair and Modernization Phase 1, USAG Fort Devens, Fort Devens RFTA MA 01434

Section 01 10 00 – Page 1 of 17

SECTION 01 10 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 WORK COVERED BY THE CONTRACT DOCUMENTS

A. The general description below is given to indicate the approximate scope of the work necessary to complete the project. It does not limit the work required under the drawings and specifications.

B. Project Identification: Building 644 Telecommunication System Repair and Modernization Phase 1, USAG Fort Devens, Fort Devens RFTA MA 01434

C. Project Location: Building 644 Fort Devens RFTA

12 Lexington Street Devens, Massachusetts 01434

D. Repair and modernization work are on-going at this project site.

This contract is phase 1 of the Telecommunication System Repair and Modernization. A following contract or order will perform phase 2 of the Telecommunication System Repair and Modernization. Other renovation work is on going at the project site. The contractor must coordinate it’s work with the Contracting Officer’s Representative.

1.2 WORK COVERED BY THE CONTRACT DOCUMENTS

ITEM 0001 REPAIR TELECOMMUNICATIONS SYSTEM, PHASE 1

The Contractor shall furnish all plant, labor and material, equipment, supervision, incidentals, and services required to perform and complete the work necessary to repair and modernize the telecommunications system of Building No. 644 Fort Devens Building 695 as specified in the following task list, the construction specifications and drawings herein.

Task List

A. SELECT DEMOLITION AND REMOVALS. With the exception of the items listed below and any other cabling or systems identified by the government during the pre-work walkthrough, perform all work required to remove and dispose of all existing telecommunications infrastructure in building 644. This includes, but is not limited to, all horizontal and backbone cabling, racks, cable support, cable tray, patch panels, 110 blocks, outlets, and faceplates.

1) It is the contractor’s responsibility to protect and keep operational the telecommunications infrastructure (i.e. rack, patch panel, horizontal cabling, POTs cross-connects, switch patch cables) serving the IDS systems in the two arms vaults.

Section 01 10 00 – Page 2 of 17

2) It is the contractor’s responsibility to protect all existing surface mounted raceway in all offices.

3) It is the contractor’s responsibility to protect and keep operational the outside plant (OSP) backbone fiber and copper cabling and infrastructure in Telecommunications Room (TR) 141.

4) The contractor is responsible to move and reset furniture in the rooms to access the raceways and outlets.

5) The contractor is responsible to move and reset the suspended ceiling tiles and/or grid to remove cabling.

6) The existing outlet locations are shown on the attached existing conditions drawings.

7) The existing equipment within the telecommunications rooms are shown on the attached existing conditions photographs.

B. TELECOMMUNICATIONS ROOM WINDOWS. The windows in Telecommunications

Rooms (TR)(Rooms 141, 251, and 346) are to be blackened using opaque covers.

C. WALL RELOCATION IN TELECOMMUNICATIONS ROOM 251. Perform all work required to relocate the plan wall east of TR 251 4 feet into the adjacent room 250 to enlarge TR 251. Repair ceiling in room 250 as needed. Finish and paint the new wall and ceiling area impacted by this work. The wall is a one-hour fire rated metal stud frame with 5/8 gypsum wallboard. The wall is to be painted to match the existing walls. The paint color is Navajo White. Electrical raceways and outlets are to be disconnected and reinstalled in accordance with NFPA 70. See attached drawing.

D. TELECOMMUNICATIONS ROOM FLOORING. Perform all work required to remove existing flooring and then provide and install an electro-static dissipative (ESD) vinyl tile in the Main TR 141, TR 251 and TR 346. ESD tile shall meet or exceed the example product shown in the attachment “Armstrong ESD VCT Product Data Sheet.” Devens RFTA DPW must approve tile color and finish. The bonding strip of the ESD flooring shall be bonded to the PBB or SBB in each TR with approved methods. The flooring is to be installed in accordance with the Manufacturer’s instructions.

E. TELECOMMUNICATIONS ROOM HVAC. Perform all work required to provide and install an HVAC system in the TR 141, TR 251 and TR 346. System installed shall be capable of operating 24/7/365. System installed shall be capable of meeting the following performance requirements;

18-27 degrees Celsius (64-81 degrees F). Noncondensing, -9 degrees Celsius (16 degrees F) Dew Point (DP) to 15 Degrees Celsius (59 degrees F) DP and 60% Relative Humidity (RH). All products used and all work performed shall be IAW requirements of ANSI/TIA-569-E.

Section 01 10 00 – Page 3 of 17

F. TELECOMMUNICATIONS ROOM BONDING AND GROUNDING. Perform all work required to provide and install a Primary Bonding Bus-Bar (PBB) in TR 141 and Secondary Bonding Bus-Bar (SBB) in TR 251 and TR 346.

Perform all work required to provide and install a Bonding Conductor for Telecommunications (BCT) and Telecommunications Bonding Backbone (TBB) to the PBB and each SBB. All products used and all work performed shall be IAW requirements listed in ANSI/TIA-569-D, ARNEC CHG3, and specification 27 10 00.00 48.

1.3 REFERENCES

A. Where references (e.g. ASTM, ACI, etc.) are noted for compliance throughout this Statement of Work, Contractor shall use the most current and up to date copy at time of actual construction.

B. Contractor shall be responsible for providing their own copies of references.

C. The publications listed below form part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

National Fire Protection Association (NFPA) Publication #70 National Electric Code

Telecommunications Industry Association (TIA)Publication ANSI/TIA-569-D Commercial Building Standard for Telecommunications Pathways and Spaces

U.S. Army Reserve Network Center (ARNEC)Infrastructure Technical Criteria through Change 3 dated 1 February 2020. (ARNEC CHG3). A copy is attached.

U.S. Army Corps OF Engineers, Louisville District – Army Reserve Guide Specification 27 10 00.00 48 Building Telecommunication Cabling System.

A copy is attached.

1.3 DEFINITIONS

A. Drawings – That part of the Contract Documents which graphically shows the scope, extent, and character of the Work to be performed by the Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined.

B. Existing Conditions - Including but not limited to, all existing buildings and interior utilities (HVAC, electricity, plumbing, etc.), structures, fences, roads, sidewalks, pavement, curbs, above and underground utilities and equipment, existing improvements, vegetation (trees, shrubs, grass, etc.), and underground facilities.

C. Furnish – When used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified

Section 01 10 00 – Page 4 of 17 location) ready for use or installation and in usable or operable condition.

D. Install, Perform or Provide – When used in conjunction with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.

E. Shop Drawings – All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for the Contractor and submitted by Contractor to illustrate some portion of the Work.

F. Site – Including but not limited to land, buildings, structures and or areas indicated in the Contract Documents as being furnished by the Government upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by the Government which are designated for use by the Contractor.

G. Underground Facilities – All underground pipelines, conduits, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

H. Work – The entire construction, on- and off-site, or the various separate identifiable parts thereof required to be provided under this Contract. Work includes and is the result of performing or providing all labor, services, submittals, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by this Contract.

I. Unless stated otherwise in the Contract, words or phrases which have a well-known technical or construction industry or trade meaning shall be used in the Contract in accordance with such recognized meaning.

1.4 PRICING

The Contractor shall submit a detailed cost breakdown for each item.

Each item shall be broken down to include labor, materials, equipment, and overhead.

1.5 CONTRACT DRAWINGS AND SPECIFICATIONS

A. The Government will furnish the Contractor paper copies of all technical contract documents. The complete set of drawing files and technical specification files which have all amendments incorporated;

B. The Contractor shall:

Section 01 10 00 – Page 5 of 17

1. Check all drawings furnished immediately upon receipt;

2. Compare all drawings and verify the figures before laying out the work;

3. Promptly notify the Contracting Officer of any discrepancies;

4. Be responsible for any errors which might have been avoided by complying with paragraph (b); and

5. Reproduce and print contract drawings and specifications as needed.

C. Omissions from the drawings or specifications or the incorrect showing of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or inaccurate details of the Work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

D. The Work shall conform to the contract specifications, attachments, and any contract drawings referenced.

E. Drawings and or sketches prepared by the Government shall not be used for shop drawings.

F. The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

1.6 SUBMITTALS REQUIRED FOR THIS CONTRACT

A. The Contractor shall submit the following preconstruction documents for approval:

- Project Work Plan to include schedule

- Safety Plan to include Activities Hazardous Analysis

- Payment Schedule of Values

- Product Data for Electro-static dissipative (ESD) vinyl tile

- Product Data for Air Conditioning Units

- Product Data for Primary Bonding Bus-Bar (PBB) and Secondary

Bonding Bus-Bar (SBB)

- Grounding Test Reports

B. Additional required submittals are listed in each specification section.

1.7 EXISTING CONDITIONS

Section 01 10 00 – Page 6 of 17

A. Photographs and drawings are provided as an attachment to show the existing conditions. See the Drawing Index.

B. Record drawings are provided as part of this Contract are the best available drawings and information depicting existing conditions. The Government does not guarantee the drawings show all conditions that may exist at the site of the work. See the Drawing Index.

1.8 EXAMINATION OF SITE

A. This building is undergoing an active renovation project. Systems Furniture is currently being installed throughout the building. It is HIGHLY recommended that the Contractor visit the Site and become familiar with general, local, and Site conditions which may affect cost, progress, or performance of the Work. A site visit shall be scheduled through the Army Reserve Contracting Center.

1.9 QUALITY ASSURANCE

A. Contractor will be responsible for appointing, employing, and paying for specified testing by an acceptable certified independent testing agency to perform the testing;

B. Tests on components materials and for compressive strength and shrinkage of concrete will be performed as specified herein. Test for determining slump will be in accordance with the requirements of

ASTM C 143;

C. Concrete for testing shall be supplied by the Contractor at no extra cost to the government.

D. Contractor shall provide assistance and facilities to the testing agency in obtaining samples, and disposal and cleanup of excess material.

1.10 RELATED DOCUMENTS

A. Drawings and provisions of the Contract, including all conditions, clauses and specification sections, apply to this Section.

1.11 CONTRACTOR QUALITY CONTROL

A. Contractor shall comply with Contract requirements for implementing a quality control program.

1.12 SUBMITTAL PROCEDURES

A. General

1. Units of weights and measures used on all submittals are to be the same as those used in the Contract Documents.

2. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.

Section 01 10 00 – Page 7 of 17

3. Prior to submission to Contracting Officer, all submittals shall be checked and approved by the Contractor as stated in the Contract. Each item shall be stamped, signed, and dated by the Contractor indicating action taken.

4. Proposed deviations from the Contract requirements are to be clearly identified. Include within submittal items such as:

Contractor's, manufacturer's, or fabricator's drawings;

descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list);

certifications; warranties; and other such required submittals.

5. Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.

6. Samples remaining upon completion of the Work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

7. The Contractor shall also comply with Special Contract

Requirements as required based on procurement type and total cost of this Contract.

B. Submittal Classification

1. Government Approved

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."

2. Information Only

Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

C. Transmittal Form

1. Transmittal Form (ENG Form 4025) shall be used for submitting both Government Approved and Information Only submittals in accordance with the instructions on the reverse side of the form.

These forms will be furnished to the Contractor during the pre-

Section 01 10 00 – Page 8 of 17 construction meeting. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted.

Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

2. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the Work covered in this Contract.

D. Submittal Procedure

1. Quantity of Submittals

a. The Contractor shall submit four (4) copies for each submittal specified in the Contract.

2. Variations from contract requirements require government approval pursuant to Contract Clause FAR 52.236-21 and will be considered where advantageous to the government.

a. Considering Variations

Discussions with the Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP). Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the government requiring rejection and removal of such work at no additional cost to the government.

b. Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

c. Warranting That Variations Are Compatible

When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

3. All submittals shall be forwarded to, Directorate of Contracting

Officer, Box 34, 30 Quebec Street, Building 666, Fort Devens, MA

Section 01 10 00 – Page 9 of 17

01434-4429. Four copies each shall be submitted for all submittals.

4. Government Approved Submittals

a. Upon completion of review of submittals requiring government approval, the submittals will be identified as having received approval by being so stamped and dated. Two (2) copies of the submittal will be retained by the Contracting Officer and two

(2) copies of the submittal will be returned to the

5. Information Only Submittals

a. Normally submittals for information only will not be returned.

Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the drawings and specifications; it will not prevent the Contracting Officer from requiring removal and replacement of non-conforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

E. Scheduling

1. Submittals covering component items forming a system or items that are interrelated shall be submitted concurrently and scheduled to be coordinated. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 14 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals. Failure to complete the project on time will be cause for liquidated damages per customer/government denied usage of the facility at an approved direct cost to Contractor.

F. Approved/Accepted Submittals

1. The Contracting Officer's approval or acceptance of submittals is not be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.

2. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist. The Contractor under the Contractor’s quality control program requirements of this Contract is responsible for dimensions, details, and the satisfactory construction of all work, etc.

Section 01 10 00 – Page 10 of 17

3. After submittals have been approved or accepted by the Contracting Officer, no re-submittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

G. Disapproved/Rejected Submittals

1. Contractor shall make corrections required by the Contracting

Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes" is to be given to the Contracting Officer.

2. Contractor is responsible for the dimensions, details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

3. If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

H. Withholding of Payment

1. Payment for materials incorporated in the Work will not be made if required approvals have not been obtained.

2. No payment will be made for any materials incorporated into the

Work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.

I. Stamps

Stamps used by the Contractor on all Submittals, to certify that the submittal meets contract requirements, shall be similar to the following:

CONTRACTOR

(Firm Name)

_____ Approved

_____ Approved with corrections as noted on submittal data and/or attached sheets(s).

SIGNATURE: ________________________________________________________

TITLE: ______________________________________________________________

DATE: _______________________________________________________________

Section 01 10 00 – Page 11 of 17

1.13 PERMITS, FEES, AND CERTIFICATES

A. Unless otherwise stated, the Contractor shall obtain and pay for, but not limited to, all fees, licenses, permits, certificates, etc.

as required by Local, State, and or Federal Laws and Regulations and Laws necessary for the prosecution of the Work.

1.14 ACCIDENT PREVENTION AND SAFETY PLANNING

A. As prescribed by Contract Clause 52.236-13 Accident Prevention, the Contractor shall provide and maintain work environments and procedures which will-

(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;

(2) Avoid interruptions of Government operations and delays in project completion dates; and

(3) Control costs in the performance of this contract.

B. For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall-

(1) Provide appropriate safety barricades, signs, and signal lights;

(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and

(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.

C. If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.

D. The Contractor shall also comply with the Fort Devens RFTA Regulation No. 385-10 Fort Devens RFTA Safety Program dated 11 September 2017. The Contractor shall prepare and submit for acceptance a Site and Activity Specific Safety Plan consisting of the following as a minimum:

(1) The Company Safety and Health Policy

(2) Job Inspection Plan

(3) Personal Protective Equipment (PPE) requirements

Section 01 10 00 – Page 12 of 17

(4) Unsafe working conditions and hazard reporting procedures with special emphasis on how the Fort Devens RFTA Safety Office will be informed.

(5) Primary point of contact for safety matters

(6) A hazard analysis / risk assessment will be performed by the contractor for all major phases of work. The standard Army Risk Assessment Form (DD Form 2297) or the Activity Hazard Analysis Form from EM 385-1 may be used. A copy of this assessment will be provided to the Fort Devens RFTA Safety Officer prior to the start of physical work with a residual risk level signed by the contractor representative.

1.15 JOINT SITE SURVEYS

A. Pre-Construction

1. Prior to the start of any Work, the Contractor shall:

a. Conduct with the Contracting Officer a thorough pre-construction survey of the Site.

b. Submit a pre-construction report detailing the findings of the pre-construction survey. The report shall be validated by the Contracting Officer and signed by both parties. Failure to submit the report shall deem the Contractor responsible for any damages to the pre-construction conditions of Government property.

2. At a minimum, the pre-construction report shall contain the following:

a. Pre-construction conditions of the Site, access routes, storage areas, and any other areas where the Contractor may utilize for the Work. All pre-construction damages and other surface defects not annotated on the report shall be deemed the responsibility of the Contractor to fully correct and or restore.

b. The report shall list and designate areas for working, storage of materials and construction equipment, and routes of access to Site where Work is to occur. The designated areas shall be agreed upon by the Contractor and Contracting Officer.

B. Construction Progress

1. During construction, the Site and designated areas shall be routinely surveyed for post-construction damages which may result from the Work. Contractor shall repair all damages at no additional cost to the Government.

C. Pre-Final Inspection

Section 01 10 00 – Page 13 of 17

1. Ten days prior to the expected partial or final inspection date, the Contractor and Contracting Officer together shall conduct a thorough re-survey of the Site and areas involved in the Work.

The Contractor shall furnish a re-survey report of present conditions; the re-survey report shall include and follow the criteria as shown herein under Pre-Construction in section JOINT

SITE SURVEYS.

a. The report shall also list, despite protection measures, any damage caused by the Contractor as a result of executing the Work.

b. The report will also be the basis for determining the

Contractor’s scope of responsibility for repairs to damage caused by the Contractor.

1.16 PROTECTION

A. Provide and maintain protection for all existing conditions on or adjacent to the Site, as well as nearby third party property which is not part of the Work; this also includes parts of the Contract which do not unreasonably interfere with the Work. It is recommended that the Contractor become very familiar with the Site and any adjacent property.

B. Upon discovery of unknown utility or concealed conditions, notify the Contracting Officer immediately and re-direct work to avoid delay.

C. Avoid damage to existing vegetation to remain in place and only remove vegetation when specifically authorized to do so.

D. Any damage to existing conditions, including third party property, as a result of failure to comply with the requirements of the Contract or failure to exercise reasonable care in conducting the Work shall be immediately repaired. If Contractor fails or refuses to promptly repair the damage, the Contracting Officer shall exercise its rights to repair the damage at the expense of the

E. During the Work, the Contractor shall provide temporary protection at all times for:

1. Damaged portions of existing structures and land where materials are handled and equipment is moved and or relocated.

2. The interior of existing structures for the prevention of damage and the intrusion of dust and inclement weather. Prior to the starting any phases or work, all surfaces that are to remain in place and intact shall be adequately protected; this protection shall be maintained until all associated work in the area is completed and accepted by Government.

1.17 RESTORATION

Section 01 10 00 – Page 14 of 17

A. All existing conditions which are disturbed, damaged and or removed as a result of the Work, shall be fully restored (restored shall mean, but not be limited to, repaired, put back into service, replaced, etc). Restorations shall match elevations, conditions prior to the start of the Work. Except as otherwise noted, materials and workmanship used in restoring the damaged work shall conform in type and quality to that of original existing conditions.

All restorations shall be at the expense of the Contractor.

B. Remove, cut, alter, replace, patch, and or repair existing conditions as necessary to complete Work as described in the Contract. Except as otherwise noted, the Contractor shall not cut, alter or remove any structural components, nor disturb any plumbing, steam, gas, or electric utilities without prior approval from the Contracting Officer.

C. Prior to any disturbance to existing conditions, the Contracting

Officer shall be notified immediately when conditions which are to be altered and or extended are found to be defective in any way.

D. Damage to any vegetation, which is to remain in place, shall be trimmed with a clean cut and the cut painted with a pruning compound that is compatible with the vegetation and as directed by the

E. The lawn in the work area shall be cut during the contract work. At the completion of work, it shall be cleaned, graded, raked, and reseeded.

F. Changes in contract price and or time as a result of restoration to damaged existing conditions which were not shown in the Contract Documents or were unknown to the Government will be covered by the clauses entitled “CHANGES” (FAR 52.243-5) and “DIFFERING SITE

CONDITIONS” (FAR 52.236-2).

1.18 PHYSICAL DATA

A. Data and information furnished or referred to below is for the Contractor’s information only. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

B. The indications of physical conditions on the drawings are the result of AS-Built Drawings. The Contractor by his own site investigations shall determine actual field conditions and measurements.

C. The government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by the drawings.

Bidders are expected to examine site of work and, after investigation, decide for themselves character of materials and make their bids accordingly.

1.19 AVAILABILITY AND USE OF UTILITY SERVICES

Section 01 10 00 – Page 15 of 17

A. The Government shall reasonably make existing utilities available to the Contractor. The Contractor shall carefully conserve any utilities which are furnished without charge.

B. At the expense of the Contractor and the satisfaction of the

Contracting Officer, all necessary temporary facilities (electricity, heating, cooling, telephone, controls, distribution lines, etc.), shall be installed and maintained.

C. Prior to final acceptance of the Work, the Contractor shall remove all temporary facilities and any associated appurtenances, and clean and repair damage caused by installation or use of temporary facilities.

1.20 RECORD (“AS-BUILT”) DRAWINGS

A. Contractor shall maintain in a safe place and separate from documents used for construction at least one working copy of record drawings which are neatly and clearly annotated in red to show all Work as actually constructed. Annotations shall be completed in similar drafting practices as that of the original design drawings and include such supplementary notes, legends, and details as required.

B. The record drawings shall be kept current on a weekly basis and made available at all times to the Government. They shall incorporate all contract drawings such as, but not limited to, Architectural, Electrical, Civil, Structural, Mechanical and Fire Protection. If applicable, they shall show, but not limited to, the following information:

1. The actual location, type and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point.

Also record the average depth below the surface of each run.

2. The location and dimensions of any changes within and or to a building structure.

3. Systems designed, or enhanced by the Contractor and or the government, such as but not limited to, mechanical and electrical, domestic water, drainage, sanitary, gas, fire alarm, fire sprinkler, irrigation systems, etc.

4. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities.

5. Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the Contractor; including but not limited to fabrication, Section 01 10 00 – Page 16 of 17 erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.

6. The size and type, topography, invert elevations and grades of drainage installed or affected as part of the Work.

7. Changes or modifications which result from the final inspection.

8. Where contract drawings or specifications present options, show only the option selected for the Work on the record drawings.

9. If borrow material for this Work is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.

C. The record drawings will be periodically reviewed for accuracy and completeness by the Government. Monthly progress payments will be based on the ongoing maintenance of these drawings.

D. The Contractor’s progress schedule shall have a separate line item specifically for record drawings with an assigned amount of one percent (1%) of the Contract Price.

E. If the Contractor fails to maintain the record drawings as specified herein, the Contracting Officer will deduct from the monthly progress payment an amount representing the estimated cost of maintaining the record drawings. This monthly deduction will continue until an agreement can be reached between the Contracting Officer and the Contractor regarding the accuracy and completeness of updated drawings.

F. A final inspection will be scheduled upon receipt of the final record drawings to the reviewed by the Government. If the punch list causes any changes in the record drawings, the Contractor shall be responsible for those changes at no additional cost to the Government.

G. When the final record drawings have been approved by the Government, the wording "RECORD DRAWINGS/AS-BUILT CONDITIONS" shall be shown on each drawing. Mark all other contract drawings either "Record" drawing denoting no revisions on the sheet or "Revised Record" denoting one or more revisions. Date original contract drawings in the revision block.

1.21 CLEANUP

A. On a daily basis, Contractor shall remove and properly dispose of all waste material and other debris generated by the Work. It shall be removed off the Site in a manner as to prevent spillage on streets and adjacent roads. Do not allow the materials to accumulate on the Site.

B. Removal, as indicated above, shall be in accordance with all

Federal, State, and Local Regulations and Laws.

Section 01 10 00 – Page 17 of 17

C. Do not burn or bury materials and or debris on site. Leave site in clean condition.

PART 2 NOT USED

PART 3 NOT USED

ATTACHMENTS:

Drawing File No. 655-7400 Sheet 1 E101 Building 644 First Floor Voice/Data

Plan Drawing File No. 655-7400 Sheet 2 E102 Building 644 Second Floor Voice/Data

Plan Drawing File No. 655-7400 Sheet 3 E103 Building 644 Second Floor Voice/Data

Plan

Drawing File No. 610-50-03 Sheet 128 E24 Building 644 Communications Fire

Alarm Riser Diagram

Existing Conditions Photographs as of 6/27/2020 of Building 644

Submittal Register

ENG Form 4025-R Transmittal of Shop Drawings, Equipment Data, Material

Samples, or Manufacturer’s Certificates of Compliance

U.S. Army Reserve Network Center (ARNEC)Infrastructure Technical Criteria through Change 3 dated 1 February 2020 (ARNEC CHG3).

U.S. Army Corps OF Engineers, Louisville District – Army Reserve Guide Specification 27 10 00.00 48 Building Telecommunication Cabling System.

Manufacturer’s Product Data - Armstrong Excelon SDT ESD Vinyl Composition Tile

END OF SECTION 01 10 00

Section 01 57 20 – Environmental Protection (Fort Devens)

SECTION 01 57 20

ENVIRONMENTAL PROTECTION (FORT DEVENS)

PART 1 GENERAL

1.1 REFERENCES (NOT USED)

1.2 DEFINITIONS

A. Contractor Generated Hazardous Waste - Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene etc.), waste thinners, excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.

B. Environmental Pollution and Damage - Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare;

unfavorably alter ecological balances of importance to human life;

affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.

C. Environmental Protection - Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.

D. Hazardous Materials - As defined by the Environmental Protection

Agency (EPA) or State Hazardous Control Authority. Hazardous material is any material that is regulated as a hazardous material by the EPA or requires a Material Safety Data Sheet (MSDS), or during end use, treatment, handling, packaging, storage, transpiration, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste. Such material include ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs). Nonetheless, the exposure may occur incident to manufacture, storage, use and demilitarization of these items.

E. Hazardous Waste - Any discarded material, liquid, solid, or gas, which meets the definition of hazardous material or is designated hazardous waste by the Environmental Protection Agency or State Hazardous Control Authority.

F. Land Application for Discharge Water - The term "Land Application" for discharge water implies that the Contractor must discharge water at a rate which allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "Waters of the United States" must occur. Land Application must be in compliance with all applicable Federal, State, and local laws and

G. Oily Waste - Those materials which are, or were, mixed with used oil and have become separated from that used oil. Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, used oil and may be appropriately tested and discarded in a manner which is in compliance with Federal, State and local requirements.

H. Pesticide - Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.

I. Solid Waste - Garbage, refuse, debris, sludge, or other discharged material, including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.

J. Surface Discharge - The term implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur.

Waters that are surface discharged may terminate in drainage ditches, storm sewers, c reeks, and/or "Waters of the United States" and would require a permit to discharge water from the governing agency.

K. Waste Hazardous Material (WHM) - Any waste material which because of its quantity, concentration, or physical, chemical, or infectious characteristics may pose a substantial hazard to human health or the environment and which has been so designated. Used oil not containing any hazardous waste, as defined above, falls under this definition.

L. Waters of the United States - All waters which are under the jurisdiction of the Clean Water Act, as defined in 33 CFR 328.

M. Wetlands - Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions.

Wetlands generally include swamps, marshes, and bogs.

1.3 NOTIFICATION

The Contracting Officer will notify the Contractor in writing of any observed noncompliance with Federal, State or local environmental laws or regulations, and permits. After receipt of such notice, the Contractor will inform the Contracting Officer of the proposed corrective action and take such action when approved by the Contracting Officer. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken.

No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 PROTECTION OF NATURAL RESOURCES

A. Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified.

If the work is near streams, lakes, or other waterways, conform to the national permitting requirements of the Clean Water Act.

B. Do not disturb fish and wildlife. Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as indicated or specified.

C. Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer. Where such use of attached ropes, cables, or guys is authorized, the Contractor will be responsible for any resultant damage.

D. Protect existing trees which are to remain and which may be injured, bruised, defaced, or otherwise damaged by construction operations.

Remove displaced rocks from uncleared areas. By approved excavation, remove trees with 30 percent or more of their root systems destroyed. Remove trees and other landscape features scarred or damaged by equipment operations, and replace with equivalent, undamaged trees and landscape features. Obtain Contracting Officer's approval before replacement.

E. The Contracting Officer's approval is required before any equipment will be permitted to ford live streams. In areas where frequent crossings are required, install temporary culverts or bridges.

Obtain Contracting Officer's approval prior to installation. Remove temporary culverts or bridges upon completion of work, and repair the area to its original condition unless otherwise required by the

3.2 WORK AREA LIMITS

Mark the areas that need not be disturbed under this Contract prior to commencing construction activities. Mark or fence isolated areas within the general work area which are not to be disturbed. Protect monuments and markers before construction operations commence. Where construction operations are to be conducted during darkness, any markers must be visible in the dark. The Contractor's personnel must be knowledgeable of the purpose for marking and/or protecting particular objects.

3.3 LANDSCAPE

Trees, shrubs, vines, grasses, land forms and other landscape features to be preserved as indicated and or defined in the Contract must be clearly identified by marking, fencing, or wrapping with boards, or any other approved techniques. Restore landscape features damaged or destroyed during construction operations outside the limits of the approved work area.

3.4 EROSION AND SEDIMENT CONTROLS

A. If required by the Contract, the Contractor shall responsible for providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations.

B. The erosion and sediment controls selected and maintained by the

Contractor shall be such that water quality standards are not violated as a result of construction activities.

C. The area of bare soil exposed at any one time by construction operations should be kept to a minimum. Construct or install temporary and permanent erosion and sediment control best management practices (BMPs) as may be indicated in the Contract.

D. Erosion and sediment controls must be provided for onsite borrow and spoil areas to prevent sediment from entering any nearby waters.

E. Temporary excavation and embankments for work areas must be controlled to protect adjacent areas.

F. Remove all temporary measures after the area has been fully stabilized.

3.5 WATER RESOURCES

Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated. For construction activities immediately adjacent to impaired surface waters, the Contractor must be capable of quantifying sediment or pollutant loading to that surface water when required by Federal or State issued Clean Water Act permits.

3.6 WETLANDS

Do not enter, disturb, destroy, or allow discharge of contaminants into any wetlands. The protection of wetlands is the Contractor's responsibility. Authorization to enter specific wetlands identified will not relieve the Contractor from any obligation to protect other wetlands within, adjacent to, or in the vicinity of the construction site and associated boundaries.

3.7 AIR RESOURCES

Equipment operation, activities, or processes will be in accordance with all Federal and State air emission and performance laws and standards.

3.8 DUST CONTROL

A. Keep dust down at all times, including during nonworking periods.

Sprinkle or treat, with dust suppressants, the soil at the site, haul roads, and other areas disturbed by operations.

B. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming.

C. Air blowing will be permitted only for cleaning nonparticulate debris such as steel reinforcing bars.

D. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete. Do not unnecessarily shake bags of cement, concrete mortar, or plaster.

3.9 BURNING

Burning is prohibited and will not be allowed on government property.

3.10 SOLID WASTES

A. Place solid wastes (excluding clearing debris) in containers which are emptied on a regular schedule. Handling, storage, and disposal must be conducted to prevent contamination. Employ segregation measures so that no hazardous or toxic waste will become co-mingled with solid waste.

B. Transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal.

C. Verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate.

3.11 CHEMICALS AND CHEMICAL WASTES

Dispense chemicals ensuring no spillage to the ground or water. Perform and document periodic inspections of dispensing areas to identify leakage and initiate corrective action. This documentation will be periodically reviewed by the Government. Collect chemical waste in corrosion resistant, compatible containers. Collection drums must be monitored and removed to a staging or storage area when contents are within 6 inches of the top.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .