PJMS 112674 SOW Construct Concrete Apron at Front of Maintenance Bay (1).doc
DOC document 697 KB Posted
- Attached to
- Motor Vehicle area Paving Federal contract opportunity
- Solicitation number
- W50S8222B0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Results.pdf | ||
| WF 113 - Installation Access Application.pdf | ||
| VM_Overhead_view.jpg | JPG image | |
| PJMS 112674 Construct 51FT Wide Apron at Maintenance (1).pdf | ||
| W50S8222B0003.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCT CONCRETE APRON AT FRONT OF MAINTENANCE BAY
FACILITY 2110
STATEMENT OF WORK
PROJECT NUMBER: PJMS 112674
Base Engineer:
175CES/CC
Using Agency:
175LRS/CC
Fire Chief:
175CES/CEF
Security Forces:
175SFS/CC
Communication:
175CS/CC
Environmental:
175WG/EMO
Safety:
175WG/SE
MARYLAND AIR NATIONAL GUARD BASE
MARTIN STATE AIRPORT
BALTIMORE, MARYLAND 21220
26 Aug 2022
1. General Project Information:
1.1.
Project Location and Background: This Statement of Work is to take place at Facility 2110, Vehicle Maintenance at the Maryland Air National Guard (MDANG) of Martin State Airport, Maryland Air National Guard, 2701 Eastern Boulevard, Baltimore, MD 21220. For several years the weight of vehicles going in and out of the maintenance bays has caused the asphalt to sink where it meets the concrete at the maintenance bays. This repair will create a smooth transition for the vehicles entering into the bay and maintain the structural integrity of the pavement over time.
1.1.1.
Coordinate access to premises with Contracting Office Representative (COR) at (410) 918-6538 for execution of work. Emergency situations, military operations, or other contingencies, may cause suspension of work or restrictions on access to the construction site. If military emergency operations require escorts, the Government will provide them to the Contractor at no cost.
1.2. Use of Premises:
1.2.1. Contractor shall assume full responsibility for protection and security of materials and equipment stored on site.
1.2.2. Contractor shall move any stored products, under their control, which interfere with operations of the Government.
1.2.3. The Contracting Officer Representative (COR) will determine the storage or work areas available under this contract.
1.3. Government Equipment: Contractor use of Government owned or leased equipment such as: hoists, forklifts, compressors, welding machines, cutting rigs, etc. shall not be permitted on either a reimbursable or non-reimbursable basis. Cost for all equipment required to accomplish the work shall be included in the Contractors final bid price.
1.4. Permits and Inspections: Normally no permits or inspections by local building officials are required. All inspections will be performed by COR unless modified by the Statement of Work. All testing will be performed by the contractor unless modified within the construction documents. A submission of the installation test report shall be submitted to the Commander of the 175th Civil Engineering Squadron before final payment will be delivered.
1.5. Unless otherwise specified in other sections of this specification, the use of burning equipment or open flame welding and cutting shall be allowed only as authorized in writing by the local Fire Inspector (Facility 3150). Once approved by the Fire Inspector, a written AF Form 592 – USAF Welding, Cutting, and Brazing Permit will be issued. The permit will be issued by the fire department within one (1) hour of request, and must be renewed daily.
1.6. Digging permits are obtained from the Work Control Office (Facility 2100) at (410) 918-6300. The Contractor is responsible for contacting ‘Miss Utility’ to mark the gas and electrical lines. The Contractor is responsible for hiring a private underground utility locating company to mark the water, sanitary sewer, storm sewer, broadband cable, and communication lines.
1.7. Change Orders: Only the Base Civil Engineer (BCE) or the Contractor may initiate change order requests. Do not proceed with any work until a signed modification or other written authority is received from the Contracting Officer. Only the Contracting Officer may approve a change order.
1.8. Field Changes: No changes in the cost or the scope of the project may be made without processing a change order. Field changes not involving cost or scope may be initiated by the BCE, COR, Contracting Officer or the Contractor.
1.9. Contractor Passes: Contractor’s Passes are only issued to personnel who have properly submitted a locally generated Wing Form 113: 175th Wing Installation Access Application (available from the Contracting Office or from the COR) and have been cleared through an approved background check. The vetting procedures are by the 175th Security Forces Squadron using the standards set forth in WI 31-101v3: Installation Access Control, Chapter 6.1.2: Fitness Determination. The Installation Access Application contains required information necessary to conduct a National Criminal Information Center (NCIC).
1.9.1. Contractors who require access onto the installation for 30 days or more may be issued a Contractors pass. For Contractors requiring less than 30 days access onto the installation may be issued a Defense Biometric Identification System (DBIDS) generated AF Form 75, Visitors Pass. The Defense Forces Commander (DFC) maintains the right to deny contractors access to the installation based on unfavorable information obtained through NCIC or DBIDS.
1.9.2. Contractors working on the installation need to complete an Antiterrorism Level I training. The training can be found at http://jko.jten.mil/courses/atl1/launch.html. Please ensure contractors are attaching their certificates along with their applications. Contractors who have not completed an Antiterrorism Level I training will not be allowed on the installation.
1.10. Daily Report and Sign-In Register: Each day the Contractor is on site to perform any work, the Superintendent/Foreman shall sign in at the Base Engineering Building (BLD 2100), indicating specific Building/Location and the number of person who shall be performing work that day.
1.11. Hours of Operations: The hours of operations at Martin State Airport for the Air National Guard are 10 hours per day (0630 – 1700) Tuesday – Friday and two weekends per month (0730 – 1700). Coordinate access to premises with COR, for execution of work. Emergency situations, military operations, or other contingencies, may cause suspension of work or restrictions on access to the construction site.
1.12. Off-Hours Work: Except as otherwise specified, all work shall be performed during regular work hours (indicated above). If the Contractor desires or is required to work on Saturdays, Sundays, Holidays or other hours outside normal work schedule, the Contractor shall be required to seek written approval from the BCE. The Contractor is not entitled to premium time if the request is approved.
1.13. Clean up: The work site is an active civilian and military airport. Site cleanliness, Foreign Object Debris (FOD) control is absolute. The Contractor will clean up all construction debris and refuse and will remove it from the work site and the Base daily at their own expense.
1.14. Safety: The Contractor is responsible for performing all work In Accordance With (IAW) State and Federal OSHA requirements as well as compliance with the most current USACE EM 385-1. This is available at http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/toc.html.
1.15. Environmental Protection and Waste Disposal: The Contractor shall, at their own expense, remove all sludge, dusts and debris from the property of the Martin State Airport Air National Guard Base which have resulted from specific work described in Paragraph 2 of these specifications. Disposal of all such materials, which may include hazardous or toxic liquids that are used to perform the work, shall conform to all Federal, State, and Local environmental regulations with regards to both transportation and ultimate disposal. This project must comply with all Federal, State, and Local environmental regulations. All dumpster service and waste management shall be provided at no additional cost to the Government. All recyclable metal shall be placed into Martin State Airport scrap metal recycling containers. Please contact the Base Environmental Scientist, DeJaun Saunders at (410) 918-6486 for detailed information. Also for more information, review “Environmental Protection Plan for Contractors”, which will be provided during the solicitation phase.
1.16. Hazardous Materials: If suspected hazardous materials are discovered, do not disturb, and contact the COR.
1.17. Drawings: Drawings furnished by the government to the Contractor may be used for general information only and shall not be relied upon or used as the basis for preparation of contract drawings required by this contract without complete on-site verification by the Contractor.
1.18. Military Real Property Data – DD Form 1354: The Contractor shall furnish real property data to the Government via the DD Form 1354, Building Information Checklist for the Transfer and Acceptance of Military Real Property, for each new construction and/or renovation project awarded, unless otherwise notified. The cost and unit of measure of each individual asset must be identified separately. If demolition work is within the scope of the project, demolished assets and demolition costs must also be identified. The Contractor is responsible for accuracy of data, current up to the time of completion. The Contractor should contact the Real Property Office at 410-918-6222 with questions pertaining to the DD Form 1354. For construction data assistance, Contractor may contact the 175th Base Civil Engineer’s Office to speak with the COR, or Project Manager assigned to the project.
2.0. Specific Project Background:
2.1. Supply all equipment, material, and labor required to remove approximately 2,665 sf of existing pavement and replace with 6 inch thick reinforced concrete slab apron. This project is for the Maryland Air National Guard, Martin State Airport, and Baltimore, MD 21220.
2.2. Cost Proposal:
Provide a detailed cost proposal indicating costs and breakdown for: Saw-cut existing asphalt pavement to depth of 9 inches as defined on the site plan and removing pavement in proposed work area. Compaction of base to receive new concrete. Concrete type to be MDSHA Mix #6, reinforced with 6 x 6 – W1.4 x W1.4 (10X10) 21lb C.S.F. welded wire fabric as defined in Typical Slab Downturn detail on Site Plan. Expansion joints must be formed for every 15ft length of concrete apron and surface application of silcure (a clear water soluble, sprayable, and inorganic, sodium silicate based compound) by soft-bristled brush or broom to achieve curing.
New apron grades must match existing pavement to achieve positive drainage away from entrance areas.
2.3. Description of Work:
Saw-cutting existing asphalt pavement to depth of 9 inch as defined on the site plan and remove pavement in proposed work area. Compact base to receive new concrete. Provide a 3 inch compacted layer of #57 stones for sub-base. Contractor is required to submit no less than two test cylinders of concrete mix for laboratory testing. Acceptable compressive strength for concrete is 4500 psi at 28 days in accordance with ASTM C78 and ASTM C 192. This testing will be conducted by an independent accredited agency. The concrete pad is to be brushed/broom finished. The contractor shall develop and institute approved measures to prevent plastic shrinkage cracks from developing by adherence to proper curing process. Reinforcement will be as shown to include 6 x 6 – W1.4 x W1.4 (10X10) 21lb C.S.F. with 2 inches cover. See Typical Slab Downturn detail on Site Plan. Expansion joints must be formed for every 15ft length of concrete apron and surface application of silicure (a clear water soluble, sprayable, and inorganic, sodium silicate based compound) by soft-bristled brush or broom finish to achieve curing. Expansion joints to be rubberized asphalt fuel resistant, hot applied, except at location where perimeter wall is adjacent to pour use asphalt impregnated fiberboard. The isolation joint at the perimeter walls must go all the way through the slab starting at the subbase. The top part of the preformed filler will be cut off and the space filled with elastomeric sealant.
New apron grades must match existing pavement to achieve positive drainage away from entrance areas. All disturbed areas must be graded to provide positive drainage to the catch basins.
Contractor will maintain the integrity of all existing bollards within the excavated areas and provide thirteen (13) new bollard sleeves (safety yellow) 8.75inch dia. installed after the concrete apron completion. Sleeves covers (4’-6” approx. height) to be Impact-resistant HDPE firmly installed. All touch-up, repair or replacement of damaged products to be achieved before substantial completion.
2.4. Construction Performance Period: The performance period will be 45 days after notice to proceed.
Meetings: A Preconstruction Meeting will be required post award and prior to construction.
Sundry Elements: Any material, devices or services not specifically mentioned or indicated in this specification that are reasonably required for a complete, finished and first class operating installation, shall be provided by the Contractor at no additional cost to the owner. The work shall be installed in accordance with this specification and best industry practices.
2.5. Cutting and Patching Proposal: Submit a proposal describing procedures at least 7 days before the time cutting and patching will be performed, requesting approval to proceed.
2.5.1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
2.5.2. Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.
2.6. Quality Control: The Contractor shall establish and maintain quality control to assure compliance with contract requirements and shall maintain records of his quality control for all construction operations required under this section. A copy of these records, as well as the records of corrective action taken, shall be furnished to the Government.
2.7. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions:
2.7.1. Notify the COR prior to arranging with Baltimore Gas and Electric to shut off electrical or natural gas utilities. Notify the COR not less than 7 days in advance of proposed utility interruptions.
2.7.2. Do not proceed with utility interruptions without the COR’s written permission.
3. Submittals:
a. Concrete:
i. Mixture prior to pour
ii. PSI test results End Statement of Work
CONCRETE APRON REQUIRED AT MAINTENANCE BAY
REPLACE BITUMIMOUS PAVEMENT WITH 6” R.C. SLAB
EXTENT OF 6” R.C. SLAB AT REFUELER BAY ENTRANCE
WO #201100674 Construct Concrete Apron at Front of Maintenance Bay 1 of 5= -1 Pages 8/26/2022