Sol_P17PS01896.pdf
PDF 300 KB Posted
- Attached to
- DEWA-REMOVE UNDERGROUND HEATING OIL TANK Federal contract opportunity
- Solicitation number
- P17PS01896
About this file
P17PS01896
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| UST_Removal-SOW-Rev4-2017.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040330169
NPS, NER SUPPLY MABO
210 New York Ave.
Contracting Office Staten Island NY 10305
PNP
Lori Achkar 718-354-4715
107/21/2017
P17PS01896
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Statement of Work
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 30 calendar days and complete it within ________________ ________________ calendar days after receiving
08/01/2017
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
NPS, NER SUPPLY MABO
210 New York Ave.
Contracting Office Staten Island NY 10305
PNP
S (Spencer) Hamilton
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 27
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
P17PS01896
Provide a firm fixed price quote to Remove
Underground Storage Tanks located at Delaware
Water Gap National Recreation Area, in the states of Pennsylvania and New Jersey in accordance with the attached Statement of Work and Price Schedule.
This is a small business set-aside, NAICS 238220, Plumbing, Heating, and Air-Conditioning
Contractors, with a small business size standard of $15.0 million. The period of performance shall commence within ten(10)calendar days of the
Notice to Proceed. The performance should be completed within thirty (30) calendar days after the Notice to Proceed is issued.
The estimated price range for this procurement is between $25,000.00 - $100,000.00.
Note: Certificate of Insurance and 100% Payment
Bond are required within ten (10) calendar days upon receipt of award.
Delivery: 30 Days After Notice to Proceed
Delivery Location Code: 0009060079
NPS, Delaware Water Gap
1978 River Road
Bushkill PA 18324 US
FOB: Destination
00010 Remove underground heating oil tanks in accordance with the attached Statement of Work and Price Schedule.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
P17PS01896 4
Section A-Solicitation/Contract Form
Standard Form 1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair).
Section B Supplies or Services and Prices/Costs
Statement of Work and Contract Price Schedule herein incorporated by attachment in Section J and made part of this solicitation.
Contractor shall complete item 30a, 30b and 30c of the Standard Form 1442.
WAGE DETERMINATION U.S. Department of Labor Davis Bacon General Decision Number: PA170127 , 07/14/2017 PA127 NJ170043 06/09/2017 NJ43 and NJ170045 06/09/2017 NJ45 applies to this procurement.
Section C – Description/Specifications
Remove Heating Oil Tanks. See Attached Statement of Work in Section J
C.1 Applicable Clauses 52.246-12 Inspection of Construction. (AUG 1996)
Section D – Packagin and marking
Not applicable
Section E - Inspection and Acceptance
E.1 Failure to Perform In the event work is performed unsatisfactorily, the contractor will be requested to correct the deficiencies. The COR will set the time frame for the deficiency to be corrected (for example 48 hours). If the work remains deficient, the COR may have the work accomplished by other means and deduct the cost thereof from the monthly payment. Note: This cost will include the administrative time used to get the work accomplished.
E.2 Applicable Clauses 52.246-11 Higher-Level Contract Quality Requirement.
Section F – Deliveries or Performance
F.1 Place of Performance The contractor will provide the services required to complete this requirement at the following location:
Deleware Watergap National Recreation Area, multiple locations within New Jersey Sussex and Warren Counties, and Pennsylvanian Pike County areas.
F.2 Terms of the Contract After the award, the contractor will be given a written notice to proceed. The offeror shall provide contractual services for a thirty (30) calendar day period, which will commence on the start date specified in the notice to proceed. Work under this contract is expected to commence on or about 9/1/2017.
F.3 Applicable Clauses 52.242-14 Suspension of Work. (APR 1984) 52.242-15 Stop Work Order 52.247-34 F.o.b. Destination.
P17PS01896 5
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) - Alternate I (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than thirty (30) calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause) lause)
Section G - Contract Administration Data
1452.201-70 Authorities and Delegations. (SEPT 2011))
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer’s Representative is Phillip Morgan and a formal designation will be forthcoming. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her
P17PS01896 6
appointment, shall be at the Contractor's risk.
(End of clause)
Contract Administration
Contracting personnel responsible for administering this contract:
Contracting Officer Spencer Hamilton NPS Northeast Region NY MABO 210 New York Avenue Staten Island, NY 10305 Phone: 718-354-4610 Spencer_hamilton@nps.gov
Contract Administrator (CA) responsible for administering this order:
Contracting Specialist responsible for this order:
Lori Achkar Contract Specialist NPS Northeast Region NY MABO 210 New York Avenue Staten Island, NY 10305 Phone: (718) 354-4715 Email: lori_achkar@nps.gov
Contracting Officer’s Representative (COR) for this order:
Phillip Morgan Deleware Watergap National Recreation Area 1978 River RoadBushkill, PA 18324 Email: phillip_morgan @nps.gov
Section H - Special Contract Requirements H.1 DOI ELECTRONIC - INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (September 2011)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
Release of Claims, Certified Payroll,Payment Bonds
Please submit a courtesy copy to Lori Achkar at lori_achkar@nps.gov for review and approval before uploading the invoice to IPP.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in CCR) will receive enrollment instructions via
P17PS01896 7
email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation. (End of Template)
H.2 Special Terms and Conditions In accordance with FAR 52.236-14, Availability and Use of Utility Services, the following utility services will be made available under this contract: N/A
H.3 Generic - Gender Terminology Except where stipulated by the Federal Acquisition Regulations, the use of terms such as he, she, his, and her are not to be interpreted as implying other than neutral gender terms such as "it" or "their".
H.4 Safety The Contractor is responsible for establishing and maintaining compliance with all applicable laws, regulations, rules, and standards, including without limitation, those regulations, rules, and standards, promulgated for the administration and enforcement of the following laws: the Occupational Safety and Health Act (OSHA) or Federally approved State equivalent(s) thereof; the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) as amended by Superfund Amendments and Reauthorization Act (SARA); Emergency Planning and Community Right-to-Know Act (EPCRA); Clean Air Act (CAA); Clean Water Act (CWA) and Toxic Substances Control Act (TSCA); and Solid Waste Disposal Act (SWDA), as amended by Resource Conservation and Recovery Act (RCRA).
H.5 Progress Meetings
(a) The Contractor shall be available to meet with the COR or his/her representative at the job site during construction to discuss work progress.
(b) Meetings will be scheduled by the COR with timely notification to the Contractor.
(c) At the progress meetings, the Contractor shall give oral reports of the progress on the project to the COR. If the work is behind schedule, the Contractor shall be prepared to (i) discuss the work and any causes of work delay(s); (ii) present a plan to bring the work back into conformance with the schedule; or, if necessary (iii) to propose a revised work schedule.
H.6 Payrolls The Contractor must furnish copies of his weekly payrolls to the CO. Payroll submission is required weekly, seven (7) days after close of payroll period.
H.7 Operation of Facility During Construction Construction activities must not interrupt the function and day-to-day operations of the facility during construction. The contractor must coordinate with the COR for any temporary measures. All temporary measures employed shall be at the Contractor's expense and shall be removed upon completion of the contract.
H.8 Work Hours Normal work hours are from 8:00 a.m. through 4:30 p.m., Monday through Friday, unless otherwise authorized.
Contractor will not be permitted to work at the job site on Saturday, Sunday or legal holidays unless otherwise authorized by the CO.
P17PS01896 8
H.9 Use of Premises
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on Government land or lands administered by the Government, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor. Such permission, if granted, will be without charge to the Contractor.
(b) Unless provided otherwise, the Contractor shall provide and maintain sanitation facilities for the workforce at the site. Solid waste shall be disposed of in accordance with applicable Federal, State, and local regulations.
H.10 Maximum Work Week The maximum workweek that will be approved is 40 hours. The Contractor's proposed hours of work are to include daily starting and stopping times.
H.11 Samples and Certificates When required by the specifications or the Contracting Officer, samples, certificates, and test data shall be submitted after award of the contract, prepaid, in time for proper action by the Contracting Officer or his/her designated representative. Certificates and test data shall be submitted in triplicate to show compliance of materials and construction specified in the contract performance requirements. Samples shall be submitted in duplicate by the contractor, except as otherwise specified, to show compliance with the contract requirements.
Materials or equipment for which samples, certifications or test data are required shall both be used in the work until approved in writing by the Contracting Officer.
H.12 Excavation and Utility Clearances The Chief of Maintenance or Facility Manager, for each park, shall ensure that the Contractor is provided with necessary excavation and utility clearances. The Contractor shall request such clearances and staking in writing to the Contracting Officer no less than ten (10) calendar days prior to the date which he/she anticipates commencement of work. The Contractor will not proceed with excavation of any kind until such clearances have been issued. Clearances will be valid from the date of issue or completion of, or otherwise directed by the issuing authority.
H.13 Disposal Debris, rubbish, and non-usable material resulting from work under this contract shall be disposed in a manner that meets federal, state and local laws.
H.14 Contractor Employees
(a) The Contractor shall provide the Contracting Officer with the name(s) of the responsible Site Superintendent authorized to act for the Contractor.
H.15 Permits The contractor shall, without additional expense to the government, obtain all appointments, licenses, and permits required to perform work under this contract. The Contractor shall comply with federal, state and local laws.
Evidence of such permits and licenses shall be provided to the Contracting Officer before work commences, or as requested.
H.16 Quality of Work Workmanship shall be of the highest quality and best practices of the trade. Contractor shall conform to all requirements of applicable state and county codes, as well as applicable codes of the National Fire Protection Association. All replacement materials shall conform to the manufacturer specifications and standards.
Substitute items shall be equal to or better that the original material and must be approved by the Government.
H.17 Completion of Work The time stated for completion of the project includes all materiel procurement, payroll records, corrections of all
P17PS01896 9
discrepancies (Punch List Items), and final clean up on premises as stated in the clause "Commencement, Prosecution and Completion of Work", FAR 52.211-10 (APR 1984) Section F.
H.18 Material Approval Submittals The submittals contemplated by the clause herein entitles "Materials and Workmanship", FAR 52.236-5 (APR 1984), Section I, shall be submitted to the Contracting Officer through the COR in five (5) copies. Document number 006211 entitled "Submittal Transmittal Form" shall be used. Contractor shall re-submit any disapproved submittals within seven (7) calendar days of disapproval.
H.19 Archeological Findings Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of, and will be removed only by, the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings; and continue operation in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for the contractor, he will be compensated by an equitable adjustment under the General Provision of the Contract.
Part II- Section I - Contract Clauses
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far
(End of clause)
52.204-1 Approval of Contract.
As prescribed in 4.103, insert the following clause:
Approval of Contract (Dec 1989)
This contract is subject to the written approval of Contracting Officer and shall not be binding until so approved.
(End of clause)
52.204-2 Security Requirements - Alternate II.
52.204-9 Personal Identity Verification of Contractor Personnel.
52.204-10 Reporting Executive Compensation and First Tier Subcontract Awards. (OCT 2015) 52.204-13 System for Award Management Maintenance. (July 2013)
52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (AUG 2013)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. (DEC 2014)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011) http://www.acquisition.gov/far
P17PS01896
52.219-28 Post Award Small Business Program Representations. (JUL 2013)
52.222-3 Convict Labor. (JUN 2003)
52.222-6 Davis-Bacon Act. (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY 2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of Segregated Facilities. (FEB 1999)
52.222-26 Equal Opportunity. (MAR 2007)
52.222-27 Affirmative Action Compliance Requirements for Construction. (FEB 1999)
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)
52.222-50 Combating Trafficking in Persons. (FEB 2009)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013)
52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997) - Alternate I. (JUL 1995)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-10 Waste Reduction Program
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts.
(MAY 2008)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.227-4 Patent Indemnity-Construction Contracts. (DEC 2007)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-11 Pledges of Assets.
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014)
52.232-16 Progress Payments. (APR 2012) Alternate I (MAR 2000)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-27 Prompt Payment For Construction Contracts. (MAY 2014)
52.232-33 Payment by Electronic Funds Transfer – System for Award Management. (JUL 2013)
52.232-39 Unenforceability of Unauthorized Obligations. (JUNE 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)
52.233-1 Disputes. (JUL 2002) Alternate I (DEC 1991)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.242-14 Suspension of Work. (APR 1984)
52.243-1 Changes—Fixed Price - Alternate II. Not sure if this applies
52.243-5 Changes and Changed Conditions. (APR 1984)
52.243-7 Notification of Changes.
52.244-6 Subcontracts for Commercial Items. (OCT 2014)
52.246-12 Inspection of Construction. (AUG 1996)
52.246-21 Warranty of Construction.(MAR 1994) Alternate I (APR 1984)
52.247-5 Familiarization with Conditions.
52.247-12 Supervision, Labor, or Materials.
52.247-17 Charges.
52.247-21 Contractor Liability for Personal Injury and/or Property Damage.
52.249-1 Termination for the Convenience of the Government. (Fixed-Price). (APR 1984)
52.249-10 Default. (Fixed-Price Construction) (APR 1984) Alternate II (APR 1984)
52.253-1 Computer Generated Forms. (JAN 1991)
52.203-99 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements. (DEVIATION 2015-02)
(a) The Contractor shall not require employees or subcontractors seeking to report fraud, waste, or abuse to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(b) The contractor shall notify employees that the prohibitions and restrictions of any internal confidentiality agreements covered by this clause are no longer in effect.
(c) The prohibition in paragraph (a) of this clause does not contravene requirements applicable to Standard Form 312, Form 4414, or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(d) (1) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Resolution Appropriations Act, 2015 (Pub. L. 113-235), use of funds appropriated (or otherwise made available) under that or any other Act may be prohibited, if the Government determines that the Contractor is not in compliance with the provisions of this clause. (2) The Government may seek any available remedies in the event the Contractor fails to comply with the provisions of this clause.
(End of clause)
52.215-8 Order of Precedence – Uniform Contract Format. (OCT 1997) Any inconsistency in this solicitation shall be resolved by giving precedence in the following order:
(a) The Schedule (excluding the specifications).
(b) Representations and other instructions.
(c) Contract clauses.
(d) Other documents, exhibits, and attachments.
(e) The specifications.
(End of clause)
52.217-8 – Option to Extend Services (Nov 1999) The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days.
(End of Clause) 52.217-9 Option to Extend the Term of the Contract. (MAR 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within _15__ days provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed [30]days).
(End of Clause)
52.252-4 Alterations in Contract.
As prescribed in 52.107(d), insert the following clause in solicitations and contracts in order to revise or supplement, as necessary, other parts of the contract, or parts of the solicitation that apply after contract award, except for any clause authorized for use with a deviation. Include clear identification of what is being altered.
Alterations in Contract (Apr 1984)
Portions of this contract are altered as follows:
(End of clause)
52.252-6 Authorized Deviations in Clauses.
As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized deviation. Whenever any FAR or supplemental clause is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the clause when it is used without deviation, include regulation name for any supplemental clause, except that the contracting officer shall insert “(DEVIATION)” after the date of the clause.
Authorized Deviations in Clauses (Apr 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.
(b) The use in this solicitation or contract of any _____. [insert regulation name] (48 CFR _____) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.
(End of clause)
52.222-55 Minimum Wages under executive Order 13658 (JAN. 2015)
(a) Definitions. As used in this clause— “United States” means the 50 states and the District of Columbia.
“Worker”—
(1) Means any person engaged in performing work on, or in connection with, a contract covered by Executive Order 13658, and
(i) Whose wages under such contract are governed by the Fair Labor Standards Act (29 U.S.C. chapter 8), the Service Contract Labor Standards statute (41 U.S.C. chapter 67), or the Wage Rate Requirements (Construction) statute (40 U.S.C. chapter 31, subchapter IV),
(ii) Other than individuals employed in a bona fide executive, administrative, or professional capacity, as those terms are defined in 29 CFR part 541,
(iii) Regardless of the contractual relationship alleged to exist between the individual and the employer.
(2) Includes workers performing on, or in connection with, the contract whose wages are calculated pursuant to special certificates issued under 29 U.S.C. 214(c).
(3) Also includes any person working on, or in connection with, the contract and individually registered in a bona fide apprenticeship or training program registered with the Department of Labor's Employment and Training Administration, Office of Apprenticeship, or with a State Apprenticeship Agency recognized by the Office of Apprenticeship.
(b) Executive Order Minimum Wage rate. (1) The Contractor shall pay to workers, while performing in the United States, and performing on, or in connection with, this contract, a minimum hourly wage rate of $10.10 per hour beginning January 1, 2015.
(2) The Contractor shall adjust the minimum wage paid, if necessary, beginning January 1, 2016 and annually thereafter, to meet the Secretary of Labor's annual E.O. minimum wage. The Administrator of the Department of Labor's Wage and Hour Division (the Administrator) will publish annual determinations in the Federal Register no later than 90 days before the effective date of the new E.O. minimum wage rate. The Administrator will also publish the applicable E.O. minimum wage on www.wdol.gov (or any successor Web site) and on all wage determinations issued under the Service Contract Labor Standards statute or the Wage Rate Requirements (Construction) statute. The applicable published E.O. minimum wage is incorporated by reference into this contract.
(3)(i) The Contractor may request a price adjustment only after the effective date of the new annual E.O.
minimum wage determination. Prices will be adjusted only if labor costs increase as a result of an increase in the annual E.O. minimum wage, and for associated labor costs and relevant subcontract costs. Associated labor costs shall include increases or decreases that result from changes in social security and unemployment taxes and workers' compensation insurance, but will not otherwise include any amount for general and administrative costs, overhead, or profit.
(ii) Subcontractors may be entitled to adjustments due to the new minimum wage, pursuant to paragraph (b)(2).
Contractors shall consider any subcontractor requests for such price adjustment.
https://www.federalregister.gov/executive-order/13658 https://www.federalregister.gov/executive-order/13658 https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-541 http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=214&type=usc&link-type=html http://www.wdol.gov/
(iii) The Contracting Officer will not adjust the contract price under this clause for any costs other than those identified in paragraph (b)(3)(i) of this clause, and will not provideduplicate price adjustments with any price adjustment under clauses implementing the Service Contract Labor Standards statute or the Wage Rate Requirements (Construction) statute.
(4) The Contractor warrants that the prices in this contract do not include allowance for any contingency to cover increased costs for which adjustment is provided under this clause.
(5) A pay period under this clause may not be longer than semi-monthly, but may be shorter to comply with any applicable law or other requirement under this contract establishing a shorter pay period. Workers shall be paid no later than one pay period following the end of the regular pay period in which such wages were earned or accrued.
(6) The Contractor shall pay, unconditionally to each worker, all wages due free and clear without subsequent rebate or kickback. The Contractor may make deductions that reduce a worker's wages below the E.O. minimum wage rate only if done in accordance with 29 CFR 10.23, Deductions.
(7) The Contractor shall not discharge any part of its minimum wage obligation under this clause by furnishing fringe benefits or, with respect to workers whose wages are governed by the Service Contract Labor Standards statute, the cash equivalent thereof.
(8) Nothing in this clause shall excuse the Contractor from compliance with any applicable Federal or State prevailing wage law or any applicable law or municipal ordinance establishing a minimum wage higher than the E.O. minimum wage. However, wage increases under such other laws or municipal ordinances are not subject to price adjustment under this subpart.
(9) The Contractor shall pay the E.O. minimum wage rate whenever it is higher than any applicable collective bargaining agreement(s) wage rate.
(10) The Contractor shall follow the policies and procedures in 29 CFR 10.24(b) and 10.28 for treatment of workers engaged in an occupation in which they customarily and regularly receive more than $30 a month in tips.
(c)(1) This clause applies to workers as defined in paragraph (a). As provided in that definition—
(i) Workers are covered regardless of the contractual relationship alleged to exist between the contractor or subcontractor and the worker;
(ii) Workers with disabilities whose wages are calculated pursuant to special certificates issued under 29 U.S.C.
214(c) are covered; and
(iii) Workers who are registered in a bona fide apprenticeship program or training program registered with the Department of Labor's Employment and Training Administration, Office of Apprenticeship, or with a State Apprenticeship Agency recognized by the Office of Apprenticeship, are covered.
(2) This clause does not apply to—
(i) Fair Labor Standards Act (FLSA)-covered individuals performing in connection with contracts covered by the E.O., i.e. those individuals who perform duties necessary to the performance of the contract, but who are not directly engaged in performing the specific work called for by the contract, and who spend less than 20 percent of their hours worked in a particular workweek performing in connection with such contracts;
(ii) Individuals exempted from the minimum wage requirements of the FLSA under 29 U.S.C. 213(a) and 214(a) and (b), unless otherwise covered by the Service Contract Labor Standards statute, or the Wage Rate Requirements (Construction) statute. These individuals include but are not limited to—
(A) Learners, apprentices, or messengers whose wages are calculated pursuant to special certificates issued under 29 U.S.C. 214(a).
(B) Students whose wages are calculated pursuant to special certificates issued under 29 U.S.C. 214(b).
(C) Those employed in a bona fide executive, administrative, or professional capacity (29 U.S.C. 213(a)(1) and 29 CFR part 541).
(d) Notice. The Contractor shall notify all workers performing work on, or in connection with, this contract of the applicable E.O. minimum wage rate under this clause. With respect to workers covered by the Service Contract Labor Standards statute or the Wage Rate Requirements (Construction) statute, the Contractor may meet this requirement by posting, in a prominent and accessible place at the worksite, the applicable wage determination under those statutes. With respect to workers whose wages are governed by the FLSA, the Contractor shall post notice, utilizing the poster provided by the Administrator, which can be obtained at www.dol.gov/whd/govcontracts, in a prominent and accessible place at the worksite. Contractors that customarily https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-10.23 https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-10.24 http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=214&type=usc&link-type=html http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=214&type=usc&link-type=html http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=213&type=usc&link-type=html http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=214&type=usc&link-type=html http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=214&type=usc&link-type=html http://api.fdsys.gov/link?collection=uscode&title=29&year=mostrecent§ion=213&type=usc&link-type=html https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-541 https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-541 http://www.dol.gov/whd/govcontracts post notices to workers electronically may post the notice electronically provided the electronic posting is displayed prominently on any Web site that is maintained by the contractor, whether external or internal, and customarily used for notices to workers about terms and conditions of employment.
(e) Payroll Records. (1) The Contractor shall make and maintain records, for three years after completion of the work, containing the following information for each worker:
(i) Name, address, and social security number;
(ii) The worker's occupation(s) or classification(s);
(iii) The rate or rates of wages paid;
(iv) The number of daily and weekly hours worked by each worker;
(v) Any deductions made; and
(vi) Total wages paid.
(2) The Contractor shall make records pursuant to paragraph (e)(1) of this clause available for inspection and transcription by authorized representatives of the Administrator. The Contractor shall also make such records available upon request of the Contracting Officer.
(3) The Contractor shall make a copy of the contract available, as applicable, for inspection or transcription by authorized representatives of the Administrator.
(4) Failure to comply with this paragraph (e) shall be a violation of 29 CFR 10.26 and this contract. Upon direction of the Administrator or upon the Contracting Officer's own action, payment shall be withheld until such time as the noncompliance is corrected.
(5) Nothing in this clause limits or otherwise modifies the Contractor's payroll and recordkeeping obligations, if any, under the Service Contract Labor Standards statute, the Wage Rate Requirements (Construction) statute, the Fair Labor Standards Act, or any other applicable law.
(f) Access. The Contractor shall permit authorized representatives of the Administrator to conduct investigations, including interviewing workers at the worksite during normal working hours.
(g) Withholding. The Contracting Officer, upon his or her own action or upon written request of the Administrator, will withhold funds or cause funds to be withheld, from the Contractor under this or any other Federal contract with the same Contractor, sufficient to pay workers the full amount of wages required by this clause.
(h) Disputes. Department of Labor has set forth in 29 CFR 10.51, Disputes concerning contractor compliance, the procedures for resolving disputes concerning a contractor's compliance with Department of Labor regulations at 29 CFR part 10. Such disputes shall be resolved in accordance with those procedures and not the Disputes clause of this contract. These disputes include disputes between the Contractor (or any of its subcontractors) and the contracting agency, the Department of Labor, or the workers or their representatives.
(i) Antiretaliation. The Contractor shall not discharge or in any other manner discriminate against any worker because such worker has filed any complaint or instituted or caused to be instituted any proceeding under or related to compliance with the E.O. or this clause, or has testified or is about to testify in any such proceeding.
(j) Subcontractor compliance. The Contractor is responsible for subcontractor compliance with the requirements of this clause and may be held liable for unpaid wages due subcontractor workers.
(k) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (k) in all subcontracts, regardless of dollar value, that are subject to the Service Contract Labor Standards statute or the Wage Rate Requirements (Construction) statute, and are to be performed in whole or in part in the United States.
(End of clause)
52.225-9 Buy American–Construction Materials. (MAY 2014)
(a) Definitions. As used in this clause--https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-10.26 https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-10.51 https://www.federalregister.gov/select-citation/2014/12/15/29-CFR-10
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the…
This is the start of the file's text. The full file is on GovTribe.