SOW_Rehabilitate_Camp_Host_Utility_Hook_ups_(2).docx
DOCX document 977 KB Posted
- Attached to
- REHABILITATE HOST SITE UTILITY HOOK-UPS. Federal contract opportunity
- Solicitation number
- P17PS01891
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WD.txt | TXT text file | |
| General_Reference_Form_(1).pdf | ||
| Sol_P17PS01891.pdf | ||
| Terms_and_Conditions.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Greenbelt Park Statement of Work Rehabilitate Utility Hook-Ups at Greenbelt Park Campground Host Sites Location of project:
Greenbelt Park, 6565 Greenbelt Road, Greenbelt, MD 20770; Campground, 4 Camp Host Sites, Campground Loops-A, B, C & D.
Target date for start of project: (9/21/2017)
PMIS # 226287
Proposal:
Existing concrete pads containing fresh water, waste water and electrical utility hook-ups will be removed and replaced with utility connections and fixtures that comply with the current health and safety standards. Electrical Wiring and conduit will be replaced to supply proper electrical service to the pedestal.
Electrical:
New electrical conduit, wiring and pedestals will be installed. RV electrical hook-up panel will include 50,30,20 amp RV Direct burial pedestal electrical box. (50 amp 125/250 V, 30 amp 125 V, 20 amp 125V)
Plumbing:
Remove existing fixtures and connect new fresh water hydrant hook-up ¾” threaded connection with freeze proof heated hydrant, new 4” waste water connection and cap will be installed according to appropriate codes and regulations.
4 Host sites will be refurbished;
1. A-Loop Host site, on left when entering A-Loop. Power from electric transformer enters buried conduit approximately 90’ to electric pedestal.
2. B-Loop Host Site, 1st site in B-Loop. Power supply provided from building utility panel through buried conduit 120’ from building to pedestal.
3. C-Loop Host site, located at entrance to D-Loop. Electrical power supplied from C-Loop Comfort Station in buried conduit 250’ from building to camp site electrical pedestal.
4. D-Loop Host site, last site on left before reaching D-Loop shower building. Electrical power supplied in buried conduit 110’ from Comfort Station electrical panel to camp site pedestal.
Each Host Site will have the following;
1. New RV electrical pedestal with 50, 30, 20 electrical connection and appropriate wiring installed.
2. In ground hydrant with freeze proof heated hydrant, appropriate plumbing connections included.
3. New 4” waste hook-up and appropriate plumbing connections.
4. New concrete pad to be poured to support utility hookups.
Special considerations;
1. Accommodations for resident host(s) must be incorporated into the project. Options are temporary hook-ups for hosts RV or phased construction so 2 host sites are continuously operational.
2. Contractor is responsible for locating and marking existing utilities to prevent damage or unscheduled outages. Mrs. Utility locating service is not available because the utilities are NPS property.
Typical Existing to be removed image1.jpeg