P17PS00898 SOLICITATION BODY
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| P17PS00898_GRSM_189645_AMENDMENT_0002.pdf | ||
| GRSM_189465_Cable_Mill_Solar_-_Final_Questions_and_Answers_Am_0002.pdf | ||
| Bote_Mtn_Tunnel_016P_Clearances.pdf | ||
| GRSM_189465_Cable_Mill_Solar_-_Final_Questions_and_Answers.pdf | ||
| P17PS00898_GRSM_189645_AMENDMENT_0001.pdf | ||
| Abrams_Creek_Bridge_031P_Load_Rating.pdf | ||
| ATT_1_GRSM_189465_CD_Specifications_FINAL.pdf | ||
| P17PS00898_GRSM_189465_SF1442.pdf | ||
| ATT_5_PAST_PERFORMANCE_QUESTIONNAIRE.docx | DOCX document | |
| ATT_2_GRSM_189465_Construction_Document_Drawings.pdf | ||
| ATT_4_-_WAGE_DETERMINATIONS_BLOUNT_COUNTY.pdf | ||
| ATT_3_BATTERY_ROOM_SKETCH_-_LAYOUT_WITH_BATTERIES.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Document No.
P17PS00898
Document Title
GRSM 189465 – Implement a Sustainable Energy System at Cable Mill, Great Smoky Mountains National Park
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION A -- SOLICITATION, OFFER, & AWARD
SECTION B – SUPPLIES OR SERVICES AND PRICES
SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK
SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
SECTION F – DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
52.242-14 SUSPENSION OF WORK (APR 1984)
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (JUL 1996)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PAYMENT PLATFORM
(APR 2013)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SPECIAL CLAUSE 1: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS .. 18
SPECIAL CLAUSE 2: KEY PERSONNEL
LIABILITY INSURANCE REQUIREMENTS
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
52.202-1 DEFINITIONS (NOV 2013)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBONTRACTOR SALES TO THE GOVERNMENT (SEPT 2006)
52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER
ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT
2010)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS
OR STATEMENTS (JAN 2017)
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER
(MAY 2011)
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
(OCT 2016)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2016)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2016)
52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (OCT 2015)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY
MATTERS (JUL 2013)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
52.215-2 AUDIT AND RECORDS—NEGOTIATION (OCT 2010)
1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR (APR 1984) .. 35
52.215-8 ORDER OF PRECEDENCE—UNIFORM CONTRACT FORMAT (OCT 1997)
52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS
CONCERNS (OCT 2014)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)
52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017)
52.219-27 NOTICE OF SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (NOV 2011)
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS—OVERTIME COMPENSATION
(MAY 2014)
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION—DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED
REGULATIONS (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APRIL 2015)
52.222-26 EQUAL OPPORTUNITY (SEPT 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APRIL
2015)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT
(DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (MARCH 2015)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)
52-222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2017)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION (SEP 2013)
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN 1997)—
ALTERNATE I (JULY 1995)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND
CONSTRUCTION CONTRACTS (MAY 2008)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
(AUG 2011)
52.224-1 PRIVACY ACT NOTIFICATION (APR 1984)
52.224-2 PRIVACY ACT (APR 1984)
52.224-3 PRIVACY TRAINING (JAN 2017)
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (DEC
2007)
52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA – SPECIAL WORKS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (JAN 2012)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION (OCT 2010)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT
(JUL 2013)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS
(DEC 2013)
52.233-1 DISPUTES (MAY 2014)—ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT (JUL 1996)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (JAN 2017)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994) – ALTERNATE I (APR 1984)
52.248-3 VALUE ENGINEERING—CONSTRUCTION (OCT 2015)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)—
ALTERNATE I (SEPT 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS .. 114
52.203-18 PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL
CONFIDENTIALITY AGREEMENTS OR STATEMENTS—REPRESENTATION (JAN 2017)
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)
52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (JUL 2016)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC
2014)
52.204-20 PREDECESSOR OF OFFEROR (JUL 2016)
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS—REPRESENTATION (NOV 2015)
52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A
FELONY CONVICTION UNDER ANY FEDERAL LAW (FEB 2016)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999)
52.223-22 PUBLIC DISCLOSURE OF GREENHOUSE GAS EMISSIONS AND REDUCTION GOALS-
REPRESENTATION (DEC 2016)
SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION
L.1 PROPOSAL SUBMISSION REQUIREMENTS
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016)
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)
52.204-22 ALTERNATE LINE ITEM PROPOSAL (JAN 2017)
52.211-6 BRAND NAME OR EQUAL (AUG 1999)
52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION (JAN 2017)
1452.215-71 USE AND DISCLOSURE OF PROPOSAL INFORMATION—DEPARTMENT OF THE
INTERIOR (APR 1984)
52.216-1 TYPE OF CONTRACT (APR 1984)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY
2014)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS (MAY 2014)
52.228-1 BID GUARANTEE (SEP 1996)
1452.233-2 SERVICE OF PROTEST DEPARTMENT OF THE INTERIOR (SEPT 2006) (DEVIATION)
(JUL 1996)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I
52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION (OCT 1997)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
SECTION M – EVALUATION FACTORS FOR AWARD
SPECIAL PROVISION 1: EVALUATION OF OPTIONS
Document Title
GRSM 189465 – Implement a Sustainable Energy System
PART I – THE SCHEDULE
SECTION A -- SOLICITATION, OFFER, & AWARD
Solicitation, Offer, and Award (SF-1442) - pages 1-3 of this package
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION B – SUPPLIES OR SERVICES AND PRICES
SOLICITATION NUMBER: P17PS00898
PARK - PMIS: GRSM 189465
DEVELOPED AREA: Cable Mill, Cades Cove, Great Smoky Mountains National Park (GRSM) PROJECT TITLE: Implement a Sustainable Energy System at Cable Mill
In addition to completing the SF 1442 and price schedule provided in Section B, offerors shall also submit a detailed cost breakdown of materials, direct labor, indirect expenses, equipment, general conditions and bond.
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI)
TITLE
QTY
UNIT OF
MEASURE
UNIT PRICE
TOTAL
PRICE
0001 Sitework 1 Lump Sum
0002 Photovoltaic System 1 Lump Sum
0003 Electrical Modifications 1 Lump Sum
TOTAL BASE PRICE (Contract Line Item Number 1 through 3) ------------------------------------ $
0004 OPTION A: Battery Bank Replacement – Gel-Type
1 Lump Sum
TOTAL PRICE FOR BID OPTION A (Contract Line Item Number 4) ------------------------------------------- $
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 4) ----------
All measurement and payment information is included in the project specifications, Section 012700.
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK
Place of Performance:
Cable Mill, Cades Cove, Great Smoky Mountains National Park (GRSM)
The work for this project includes the installation of a new 27 kW photovoltaic system, including solar panels, concrete footers, mounting structure, inverters, electrical infrastructure, chainlink fence, barb-less wire fence, and landscaping to support a natural screen. Add alternatives are included in this project for replacement of the site's existing storage batteries.
SPECIFICATIONS AND DRAWINGS ARE ATTACHED AND INCORPORATED HEREIN BY REFERENCE, SEE
SECTION J, AND ATTACHMENT(S)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION D – PACKAGING AND MARKING
No clauses included.
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION F – DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 76 calendar days after issuance of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1000 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the
Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PAYMENT PLATFORM
(APR 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
Document Title
GRSM 189465 – Implement a Sustainable Energy System
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
• 2-Page Pay Estimate
• Schedule of Values
• Annotated Project Schedule
• Subcontracting Worksheet
The Government will provide the contractor with templates for all above documents except the project schedule.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause) https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
Document Title
GRSM 189465 – Implement a Sustainable Energy System
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SPECIAL CLAUSE 1: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE
ITEMS
The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Contractor within 15 days after contract award. Performance of added line item tasks shall be at the price negotiated in the contract Schedule.
(End of clause)
SPECIAL CLAUSE 2: KEY PERSONNEL
(a) The Contractor shall assign to this contract the following key personnel:
Project Manager:
On-site Superintendent:
(b) During the first 30 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 30-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.
LIABILITY INSURANCE REQUIREMENTS
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
Employer's liability $100,000
General liability $500,000
Construction Per person $100,000 Per occurrence $500,000 Property damage $1,000,000
Document Title
GRSM 189465 – Implement a Sustainable Energy System
Architect-Engineer Per person $200,000 Per occurrence $500,000 Property damage $ 20,000
Automobile liability Per person $200,000 Per occurrence for bodily injury $500,000 (other than passenger liability) Per occurrence for property damage $20,000
Aircraft public and passenger liability, when aircraft used in connection with the performing this contract Per person $200,000 Per occurrence for bodily injury $500,000 Per occurrence for property damage $200,000 Passenger liability bodily injury $200,000 multiplied by number of seats or passengers, whichever is greater
If this is a construction contract, the Contractor shall maintain compensation insurance, for employees engaged in the work, complying with the workmen's compensation laws of the State in which the work is to be performed and shall maintain liability insurance protecting the Contractor from claims because of bodily injury (including death) and property damage arising under this Contract.
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The Contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
Document Title
GRSM 189465 – Implement a Sustainable Energy System
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
52.202-1 DEFINITIONS (NOV 2013)
When a solicitation provision or contract clause uses a word or term that is defined in the Federal Acquisition Regulation (FAR), the word or term has the same meaning as the definition in FAR 2.101 in effect at the time the solicitation was issued, unless—
(a) The solicitation, or amended solicitation, provides a different definition;
(b) The contracting parties agree to a different definition;
(c) The part, subpart, or section of the FAR where the provision or clause is prescribed provides a different meaning; or
(d) The word or term is defined in FAR Part 31, for use in the cost principles and procedures.
(End of clause)
52.203-3 GRATUITIES (APR 1984)
(a) The right of the Contractor to proceed may be terminated by written notice if, after notice and hearing, the agency head or a designee determines that the Contractor, its agent, or another representative—
(1) Offered or gave a gratuity (e.g., an entertainment or gift) to an officer, official, or employee of the Government;
and
(2) Intended, by the gratuity, to obtain a contract or favorable treatment under a contract.
(b) The facts supporting this determination may be reviewed by any court having lawful jurisdiction.
(c) If this contract is terminated under paragraph (a) of this clause, the Government is entitled—
(1) To pursue the same remedies as in a breach of the contract; and
(2) In addition to any other damages provided by law, to exemplary damages of not less than 3 nor more than 10 times the cost incurred by the Contractor in giving gratuities to the person concerned, as determined by the agency head or a designee. (This paragraph (c)(2) is applicable only if this contract uses money appropriated to the Department of Defense.)
(d) The rights and remedies of the Government provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under this contract.
(End of clause)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
(a) The Contractor warrants that no person or agency has been employed or retained to solicit or obtain this contract upon an agreement or understanding for a contingent fee, except a bona fide employee or agency. For breach or violation of this warranty, the Government shall have the right to annul this contract without liability or, to deduct from the contract price or consideration, or otherwise recover, the full amount of the contingent fee.
(b) “Bona fide agency,” as used in this clause, means an established commercial or selling agency, maintained by a contractor for the purpose of securing business, that neither exerts nor proposes to exert improper influence to solicit or obtain Government contracts nor holds itself out as being able to obtain any Government contract or contracts through improper influence.
https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 https://acquisition.gov/far/current/html/FARTOCP31.html#wp253693
Document Title
GRSM 189465 – Implement a Sustainable Energy System
“Bona fide employee,” as used in this clause, means a person, employed by a contractor and subject to the contractor’s supervision and control as to time, place, and manner of performance, who neither exerts nor proposes to exert improper influence to solicit or obtain Government contracts nor holds out as being able to obtain any Government contract or contracts through improper influence.
“Contingent fee,” as used in this clause, means any commission, percentage, brokerage, or other fee that is contingent upon the success that a person or concern has in securing a Government contract.
“Improper influence,” as used in this clause, means any influence that induces or tends to induce a Government employee or officer to give consideration or to act regarding a Government contract on any basis other than the merits of the matter.
(End of clause)
52.203-6 RESTRICTIONS ON SUBONTRACTOR SALES TO THE GOVERNMENT (SEPT 2006)
(a) Except as provided in (b) of this clause, the Contractor shall not enter into any agreement with an actual or prospective subcontractor, nor otherwise act in any manner, which has or may have the effect of restricting sales by such subcontractors directly to the Government of any item or process (including computer software) made or furnished by the subcontractor under this contract or under any follow-on production contract.
(b) The prohibition in (a) of this clause does not preclude the Contractor from asserting rights that are otherwise authorized by law or regulation.
(c) The Contractor agrees to incorporate the substance of this clause, including this paragraph (c), in all subcontracts under this contract which exceed the simplified acquisition threshold.
(End of clause)
52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)
(a) Definitions.
“Kickback,” as used in this clause, means any money, fee, commission, credit, gift, gratuity, thing of value, or compensation of any kind which is provided to any prime Contractor, prime Contractor employee, subcontractor, or subcontractor employee for the purpose of improperly obtaining or rewarding favorable treatment in connection with a prime contract or in connection with a subcontract relating to a prime contract.
“Person,” as used in this clause, means a corporation, partnership, business association of any kind, trust, joint-stock company, or individual.
“Prime contract,” as used in this clause, means a contract or contractual action entered into by the United States for the purpose of obtaining supplies, materials, equipment, or services of any kind.
“Prime Contractor” as used in this clause, means a person who has entered into a prime contract with the United States.
“Prime Contractor employee,” as used in this clause, means any officer, partner, employee, or agent of a prime Contractor.
“Subcontract,” as used in this clause, means a contract or contractual action entered into by a prime Contractor or subcontractor for the purpose of obtaining supplies, materials, equipment, or services of any kind under a prime contract.
“Subcontractor,” as used in this clause, (1) means any person, other than the prime Contractor, who offers to furnish or furnishes any supplies, materials, equipment, or services of any kind under a prime contract or a subcontract entered into in connection with such prime contract, and (2) includes any person who offers to furnish or furnishes general supplies to the prime Contractor or a higher tier subcontractor.
“Subcontractor employee,” as used in this clause, means any officer, partner, employee, or agent of a subcontractor.
(b) 41 U.S.C. chapter 87, Kickbacks, prohibits any person from— http://uscode.house.gov/
Document Title
GRSM 189465 – Implement a Sustainable Energy System
(1) Providing or attempting to provide or offering to provide any kickback;
(2) Soliciting, accepting, or attempting to accept any kickback; or
(3) Including, directly or indirectly, the amount of any kickback in the contract price charged by a prime Contractor to the United States or in the contract price charged by a subcontractor to a prime Contractor or higher tier subcontractor.
(c)(1) The Contractor shall have in place and follow reasonable procedures designed to prevent and detect possible violations described in paragraph (b) of this clause in its own operations and direct business relationships.
(2) When the Contractor has reasonable grounds to believe that a violation described in paragraph (b) of this clause may have occurred, the Contractor shall promptly report in writing the possible violation. Such reports shall be made to the inspector general of the contracting agency, the head of the contracting agency if the agency does not have an inspector general, or the Attorney General.
(3) The Contractor shall cooperate fully with any Federal agency investigating a possible violation described in paragraph (b) of this clause.
(4) The Contracting Officer may (i) offset the amount of the kickback against any monies owed by the United States under the prime contract and/or (ii) direct that the Prime Contractor withhold from sums owed a subcontractor under the prime contract the amount of the kickback. The Contracting Officer may order that monies withheld under subdivision (c)(4)(ii) of this clause be paid over to the Government unless the Government has already offset those monies under subdivision (c)(4)(i) of this clause. In either case, the Prime Contractor shall notify the Contracting Officer when the monies are withheld.
(5) The Contractor agrees to incorporate the substance of this clause, including paragraph (c)(5) but excepting paragraph (c)(1), in all subcontracts under this contract which exceed $150,000.
(End of clause)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR
IMPROPER ACTIVITY (MAY 2014)
(a) If the Government receives information that a contractor or a person has violated 41 U.S.C. 2102-2104, Restrictions on Obtaining and Disclosing Certain Information, the Government may—
(1) Cancel the solicitation, if the contract has not yet been awarded or issued; or
(2) Rescind the contract with respect to which—
(i) The Contractor or someone acting for the Contractor has been convicted for an offense where the conduct violates 41 U.S.C. 2102 for the purpose of either—
(A) Exchanging the information covered by such subsections for anything of value; or
(B) Obtaining or giving anyone a competitive advantage in the award of a Federal agency procurement contract; or
(ii) The head of the contracting activity has determined, based upon a preponderance of the evidence, that the
Contractor or someone acting for the Contractor has engaged in conduct punishable under 41 U.S.C. 2105(a).
(b) If the Government rescinds the contract under paragraph (a) of this clause, the Government is entitled to recover, in addition to any penalty prescribed by law, the amount expended under the contract.
(c) The rights and remedies of the Government specified herein are not exclusive, and are in addition to any other rights and remedies provided by law, regulation, or under this contract.
(End of clause)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
(a) The Government, at its election, may reduce the price of a fixed-price type contract and the total cost and fee under a cost-type contract by the amount of profit or fee determined as set forth in paragraph (b) of this clause if the head of the http://uscode.house.gov/
Document Title
GRSM 189465 – Implement a Sustainable Energy System contracting activity or designee determines that there was a violation of 41 U.S.C. 2102 or 2103, as implemented in section 3.104 of the Federal Acquisition Regulation.
(b) The price or fee reduction referred to in paragraph (a) of this clause shall be—
(1) For cost-plus-fixed-fee contracts, the amount of the fee specified in the contract at the time of award;
(2) For cost-plus-incentive-fee contracts, the target fee specified in the contract at the time of award, notwithstanding any minimum fee or “fee floor” specified in the contract;
(3) For cost-plus-award-fee contracts—
(i) The base fee established in the contract at the time of contract award;
(ii) If no base fee is specified in the contract, 30 percent of the amount of each award fee otherwise payable to the
Contractor for each award fee evaluation period or at each award fee determination point.
(4) For fixed-price-incentive contracts, the Government may—
(i) Reduce the contract target price and contract target profit both by an amount equal to the initial target profit specified in the contract at the time of contract award; or
(ii) If an immediate adjustment to the contract target price and contract target profit would have a significant adverse impact on the incentive price revision relationship under the contract, or adversely affect the contract financing provisions, the Contracting Officer may defer such adjustment until establishment of the total final price of the contract.
The total final price established in accordance with the incentive price revision provisions of the contract shall be reduced by an amount equal to the initial target profit specified in the contract at the time of contract award and such reduced price shall be the total final contract price.
(5) For firm-fixed-price contracts, by 10 percent of the initial contract price or a profit amount determined by the Contracting Officer from records or documents in existence prior to the date of the contract award.
(c) The Government may, at its election, reduce a prime contractor’s price or fee in accordance with the procedures of paragraph (b) of this clause for violations of the statute by its subcontractors by an amount not to exceed the amount of profit or fee reflected in the subcontract at the time the subcontract was first definitively priced.
(d) In addition to the remedies in paragraphs (a) and (c) of this clause, the Government may terminate this contract for default. The rights and remedies of the Government specified herein are not exclusive, and are in addition to any other rights and remedies provided by law or under this contract.
(End of clause)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS
(OCT 2010)
(a) Definitions. As used in this clause— “Agency” means “executive agency” as defined in Federal Acquisition Regulation (FAR) 2.101.
“Covered Federal action” means any of the following actions:
(1) Awarding any Federal contract.
(2) Making any Federal grant.
(3) Making any Federal loan.
(4) Entering into any cooperative agreement.
(5) Extending, continuing, renewing, amending, or modifying any Federal contract, grant, loan, or cooperative agreement.
“Indian tribe” and “tribal organization” have the meaning provided in section 4 of the Indian Self-Determination and
Education Assistance Act (25 U.S.C. 450b) and include Alaskan Natives.
“Influencing or attempting to influence” means making, with the intent to influence, any communication to or appearance before an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with any covered Federal action.
http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%203_1.html#wp1139280 https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508
Document Title
GRSM 189465 – Implement a Sustainable Energy System
“Local government” means a unit of government in a State and, if chartered, established, or otherwise recognized by a
State for the performance of a governmental duty, including a local public authority, a special district, an intrastate district, a council of governments, a sponsor group representative organization, and any other instrumentality of a local government.
“Officer or employee of an agency” includes the following individuals who are employed by an agency:
(1) An individual who is appointed to a position in the Government under Title 5, United States Code, including a position under a temporary appointment.
(2) A member of the uniformed services, as defined in subsection 101(3), Title 37, United States Code.
(3) A special Government employee, as defined in section 202, Title 18, United States Code.
(4) An individual who is a member of a Federal advisory committee, as defined by the Federal Advisory Committee
Act, Title 5, United States Code, appendix 2.
“Person” means an individual, corporation, company, association, authority, firm, partnership, society, State, and local government, regardless of whether such entity is operated for profit, or not for profit. This term excludes an Indian tribe, tribal organization, or any other Indian organization eligible to receive Federal contracts, grants, cooperative agreements, or loans from an agency, but only with respect to expenditures by such tribe or organization that are made for purposes specified in paragraph (b) of this clause and are permitted by other Federal law.
“Reasonable compensation” means, with respect to a regularly employed officer or employee of any person, compensation that is consistent with the normal compensation for such officer or employee for work that is not furnished to, not funded by, or not furnished in cooperation with the Federal Government.
“Reasonable payment” means, with respect to professional and other technical services, a payment in an amount that is consistent with the amount normally paid for such services in the private sector.
“Recipient” includes the Contractor and all subcontractors. This term excludes an Indian tribe, tribal organization, or any other Indian organization eligible to receive Federal contracts, grants, cooperative agreements, or loans from an agency, but only with respect to expenditures by such tribe or organization that are made for purposes specified in paragraph (b) of this clause and are permitted by other Federal law.
“Regularly employed” means, with respect to an officer or employee of a person requesting or receiving a Federal contract, an officer or employee who is employed by such person for at least 130 working days within 1 year immediately preceding the date of the submission that initiates agency consideration of such person for receipt of such contract. An officer or employee who is employed by such person for less than 130 working days within 1 year immediately preceding the date of the submission that initiates agency consideration of such person shall be considered to be regularly employed as soon as he or she is employed by such person for 130 working days.
“State” means a State of the United States, the District of Columbia, or an outlying area of the United States, an agency or instrumentality of a State, and multi-State, regional, or interstate entity having governmental duties and powers.
(b) Prohibition. 31 U.S.C. 1352 prohibits a recipient of a Federal contract, grant, loan, or cooperative agreement from using appropriated funds to pay any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with any covered Federal actions. In accordance with 31 U.S.C. 1352 the Contractor shall not use appropriated funds to pay any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the award of this contractor the extension, continuation, renewal, amendment, or modification of this contract.
(1) The term appropriated funds does not include profit or fee from a covered Federal action.
(2) To the extent the Contractor can demonstrate that the Contractor has sufficient monies, other than Federal appropriated funds, the Government will assume that these other monies were spent for any influencing activities that would be unallowable if paid for with Federal appropriated funds.
(c) Exceptions. The prohibition in paragraph (b) of this clause does not apply under the following conditions:
(1) Agency and legislative liaison by Contractor employees.
Document Title
GRSM 189465 – Implement a Sustainable Energy System
(i) Payment of reasonable compensation made to an officer or employee of the Contractor if the payment is for agency and legislative liaison activities not directly related to this contract. For purposes of this paragraph, providing any information specifically requested by an agency or Congress is permitted at any time.
(ii) Participating with an agency in discussions that are not related to a specific solicitation for any covered Federal action, but that concern—
(A) The qualities and characteristics (including individual demonstrations) of the person’s products or services, conditions or terms of sale, and service capabilities; or
(B) The application or adaptation of the person’s products or services for an agency’s use.
(iii) Providing prior to formal solicitation of any covered Federal action any information not specifically requested but necessary for an agency to make an informed decision about initiation of a covered Federal action;
(iv) Participating in technical discussions regarding the preparation of an unsolicited proposal prior to its official submission; and
(v) Making capability presentations prior to formal solicitation of any covered Federal action by persons seeking awards from an agency pursuant to the provisions of the Small Business Act, as amended by Pub. L. 95-507, and subsequent amendments.
(2) Professional and technical services.
(i) A payment of reasonable compensation made to an officer or employee of a person requesting or receiving a covered Federal action or an extension, continuation, renewal, amendment, or modification of a covered Federal action, if payment is for professional or technical services rendered directly in the preparation, submission, or negotiation of any bid, proposal, or application for that Federal action or for meeting requirements imposed by or pursuant to law as a condition for receiving that Federal action.
(ii) Any reasonable payment to a person, other than an officer or employee of a person requesting or receiving a covered Federal action or an extension, continuation, renewal,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .