ATTACHMENT 1 - GATE 195019 HANGAR 38 DB PROJECT SCOPE

View the file

Other files for this federal contract opportunity

Other files attached to Seaplane Hangar 38 Resiliency Repairs - Partial Deconstruction, newest first.
File Type Posted
2_GATE_195019_SOLICITATION_CLAUSES.pdf PDF
6_SECTION_5_ATTACHMENTS.pdf PDF
4_GATE_195019_HANGAR_38_SCHEMATIC_DESIGN.pdf PDF
5_WAGE_DETERMINATIONS.pdf PDF
1_P16PS00872_SF1442.pdf PDF
7_PROPOSAL_SUBMISSION_PACKAGE.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GATEWAY NATIONAL RECREATION AREA

MILLER FIELD UNIT, STATEN ISLAND, NY

SOLICITATION No. C2000081300/P09PC60860

HANGAR 38 RESILIENCY REPAIRS – PARTIAL

DECONSTRUCTION

GATE 195019

DESIGN BUILD PROJECT SCOPE

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

April 2016

Table of Contents

1.0 PROJECT INTRODUCTION

1.1 SCOPE

1.2 FUNDING LIMITATIONS

1.3 LOCATION

1.4 BACKGROUND

1.5 DESCRIPTION

1.6 SCHEDULE

1.7 INFORMATION

1.8 DATA AND MATERIALS TO BE PROVIDED BY THE NPS

2.0 PROJECT REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

2.1.2 DEFINITION OF CONTRACT LINE ITEMS

2.1.3 PROGRESS PAYMENTS

2.1.4 PROJECT MEETINGS

2.1.5 PROJECT SCHEDULE

2.2 DESIGN REQUIREMENTS

2.2.1 DB DESIGN DEVELOPMENT AND CONSTRUCTION DOCUMENTS

2.2.2 ENVIRONMENTAL REQUIREMENTS FOR DESIGNERROR! BOOKMARK NOT DEFINED.

2.3 CONSTRUCTION REQUIREMENTS

2.3.1 ENVIRONMENTAL REQUIREMENTS .... ERROR! BOOKMARK NOT DEFINED.

2.3.2 SCHEDULE OF VALUES

2.3.3 CONSTRUCTION SUPPORT

2.3.4 SUBMITTALS DURING CONSTRUCTION

2.3.5 CONSTRUCTION COORDINATION

2.3.6 DIGITAL IMAGES

2.3.7 QUALITY CONTROL

2.3.8 WORKING HOUR RESTRICTIONS

2.3.9 TEMPORARY SERVICES

2.3.10 ACCESS

2.3.11 PRESERVATION OF ADJACENT FEATURES

2.3.12 EXISTING UTILITIES

2.3.13 HAULING RESTRICTIONS

2.3.14 ACCIDENT PREVENTION

2.3.15 TEMPORARY CONTROLS

2.3.16 FIELD ENGINEERING

2.3.17 PROJECT CLOSE-OUT

2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

2.4 FORMS

3.0 PERFORMANCE REQUIREMENTS

3.1 DESIGN IMPERATIVES

3.2 INTEGRATED DESIGN PRINCIPLES

3.3 FACILITY PERFORMANCE

3.4 ELEMENTS AND PRODUCTS

4.0 TECHNICAL REQUIREMENTS

DESIGN CRITERIA

5.0 ATTACHMENTS

1.0 PROJECT INTRODUCTION

Project Name: Professional Services for Northeast Region Hurricane Sandy Recovery Projects, Design Services for Schematic Design and Design-Build Request for Proposal (RFP), Gateway

National Recreation Area (Staten Island Units), Miller Field Hangar 38 Resiliency Repairs

Project Number: PMIS GATE 195019

1.1 Scope

In accordance with the terms and conditions of the Contract, the Design-Build Contractor (DBC) shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.

All Architect-Engineer (A-E) Services required in this RFP shall be performed by licensed

Architects and Engineers registered in the State of New York.

The work of this RFP shall be performed in accordance with the Denver Service Center (DSC)

Design-Build (DB) Workflow Website http://www.nps.gov/dsc/workflows/designbuild.htm.

Listed on the DB homepage are design phases which describe the workflow process from

Predesign through DB Construction Documents. Each phase has significant amounts of hypertext that links to definitions, forms, templates, samples and guidelines. In addition to the design phases there is an Information link where the definition glossary, laws, polices, guidelines, design standards, design deliverable content and format requirements, and other categories of useful information such as the “DSC Technical Bulletins” are located.

In case of conflict between this RFP and the DSC DB Workflow Website, http://www.nps.gov/dsc/workflows/designbuild.htm, this RFP will take precedence over and will be used in lieu of such conflicting portions.

The A-E remains fully responsible for determining if the standards or provisions cited on the DSC

DB Workflow Website, http://www.nps.gov/dsc/workflows/designbuild.htm, have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO) requesting direction.

1.2 Funding Limitations

The Design-Build Contractor (DBC) team is responsible for providing all design and construction services required for the final total lump-sum firm-fixed amount negotiated with the

DBC. The total contract amount for all design and construction services is estimated to be between $5,500,000 and $6,200,000.

http://www.nps.gov/dsc/workflows/designbuild.htm

1.3 Location

This project is located off New Dorp Lane, on the eastern shore of Staten Island, New York. The historic, former Seaplane Hangar #38 anchors the southeast corner of the Miller Field Unit of

Gateway National Recreational Area.

1.4 Background

Miller Field was established prior to World War I as part of a system of aerial coast defenses for

New York City. An early aviation building, Seaplane Hangar 38 was constructed at Miller Field in 1920 for the U.S. Army and is the sole survivor of a hangar group and base comprising approximately 40 buildings. Hangar 38 remains significant as one of the last extant examples of its type remaining on the eastern seaboard.

On October 29, 2012, Superstorm Sandy inundated Miller Field, bringing salt water, debris, and wave action to the Seaplane Hangar 38 and the rest of the site, triggering the need for mitigation of life-safety hazards and protection of the historic resource. Carrying contaminated mud and sludge into the hangar bays, the storm surge damaged features and exacerbated ongoing deterioration of interior and exterior finishes. The park is currently in the recovery phase and has been methodically repairing and rebuilding, making use of funds appropriated via the Sandy Recovery

Improvement Act. The purpose of this project is to mitigate hazards, increase resiliency and reduce the risk of damage from future flooding.

1.5 Description

Consisting of two adjacent hangar bays, the original Seaplane Hangar 38 building was extensively renovated in 1939 as a federal Works Progress Administration (WPA) project; the

WPA work included a two-story addition on the west and one-story additions on the south and east sides of the hangar. The two-story office/support facilities wing is reinforced concrete-framed with masonry infill, while the one-story utility, shop and support spaces are predominantly constructed of concrete piers and walls supporting wood roof framing.

The extant two-bay hangar structure is characterized by riveted trusses built up from steel angles and clear-spanning 110 feet in the east-west direction, over each hangar bay. Roof trusses and supporting columns are spaced 20 feet on center in the north-south direction.

Supporting columns are built up from four riveted steel angles and a web plate, all encased in terra cotta tile and stucco finishes. At each hangar bay, a pair of doubled roof truss added to the original hangar structure span the north-facing hangar door opening; tying together an assembly of pylons, pulleys cables and counterweights, the inner truss pair carries the massive hangar doors and the original trusses supports the gable end and roof deck above.

In general terms, the project entails removal of all additions and all original and subsequent enclosure elements, fixtures, finishes and appurtenances, leaving only the original structural steel framing and corrugated steel roof decking in place, followed by structural repairs, lateral reinforcement, surface preparation and application of a high-performance coating throughout, in order to create a stabilized steel “skeleton” with retained roof decking.

View of Hangar 38 from north, February 2013.

Interior of west hangar bay. Hangar door and louver-vented plywood “overframe”

(to be removed).

View from southeast, showing chimney (left), boiler house and WPA-era additions (to be removed).

1.6 Schedule

The work in this RFP shall be completed in accordance with the following schedule:

DB Design Development Documents:

DB Design Development Documents submitted no later than __60__ calendar days after award.

NPS Review completed no later than __20__ calendar days after submission of DB Design

Development Documents.

100% Draft DB Construction Documents:

100% Draft DB Construction Documents and written responses to the NPS DB Design

Development Document Review Comments submitted no later than 45 calendar days after receipt of NPS review comments on DB Design Development Documents.

NPS Review completed no later than __20__ calendar days after receipt of 100% Draft DB

Construction Documents.

100% Complete DB Construction Documents:

100% Complete DB Construction Documents and written responses to the 100% Draft DB

Construction Documents Review Comments submitted no later than 14 calendar days after receipt of NPS review comments on the 100% Draft DB Construction Documents.

NPS Review completed no later than __30__ calendar days after receipt of 100% Draft DB

Construction Documents.

Complete Stamped and Signed DB Construction Documents:

Complete Stamped and Signed DB Construction Documents and written responses to the

NPS 100% Draft DB Construction Document review comments submitted no later than 7 calendar days after receipt of NPS 100% Draft DB Construction Document review comments.

Construction:

Construction Notice-to-Proceed shall be issued upon receipt of Complete Stamped and

Signed DB Construction Documents. Construction shall be completed no later than 180 calendar days after award issuance of the Construction NTP.

As-Constructed Drawings:

As- Constructed Drawings completed no later than __30__ calendar days after Project

Completion.

All DB Design Development, DB Construction Documents and As-Constructed Drawings shall be submitted to the NPS Project Manager.

1.7 Information

NPS Points of Contact:

Contractual:

Contracting Officer (CO): Victoria Nosal; 303-969-2203; victoria_nosal@nps.gov

Contract Specialist (CS): Paula Johnson; 303-987-6643; paula_johnson@nps.gov

Technical:

Project Manager (PM) and Alternate Contracting Officer’s Representative (ACOR):

Bret Nickels, Jeremy_nickels@nps.gov

Project Specialist (PS) and Contracting Officer’s Representative:

Paula Aldrich, 303-987-6717; paula_aldrich@nps.gov

Address:

National Park Service – Denver Service Center

12795 West Alameda Parkway

P.O. Box 25287

Denver, CO 80225

1.8 Data and Materials to be provided by the NPS

The following data and materials will be provided to the DBC and are included in Section 5 of this RFP:

Hangar 38 Mini-CBA Report (Sept. 2014)

Schematic Design Documents

CardnoATC Hazardous Materials Survey – summary (Oct. 2013)

Product Cut Sheets

HABS/HAER Drawings

Existing Site Map (Aerial Photo)

Existing Conditions Photographs

Project SD Level Sustainability Checklist

2.0 PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 Scope of Work and Project Summary/Requirements

Without limitation, the project consists of the following coordinated work items:

Abatement and removal of hazardous materials, including all roofing and flashing assemblies, materials and sealants, slurry/sludge washed into the building, and insulated wood-frame partitions and ceilings currently or previously determined to be contaminated with mold and animal waste.

Selective demolition and removal of designated load-bearing concrete-embedded structural steel columns and beams, all wood joists and floor and roof sheathing, reinforced concrete

“pony walls” and structured floor and roof slabs.

Selective demolition and removal of non-load-bearing clay masonry, glass block, lath-and-plaster and wood-framed partitions, stucco panel assemblies, plywood door and window boarding, and corrugated fiberglass cladding, together with all associated wood strapping and mounting hardware.

Selective demolition and removal of brick masonry chimney, concrete boiler house, iron boilers and all associated heating pipes and fittings throughout the building.

Selective demolition and removal of all fire sprinkler pipes, devices and equipment and all electrical fixtures, devices, panels, conduit and wiring not reserved for salvage and delivery to the NPS.

Selective demolition and removal of metal door, industrial-sash window and skylight monitor window assemblies, steel railing assemblies and fire escapes, metal gutters and downspouts.

Retention and protection during construction work of designated components and features;

retention of existing slabs on grade, hydraulic lift wells, etc.

Photographic documentation and selective demolition and removal of hangar door assemblies, including glass and steel door components, extant door frames, door lifting mechanisms and counterweights.

Deconstruction and salvage of double-hung window sash.

Deconstruction and salvage of selected interior light fixtures and exterior flood lights.

Repair of structural steel columns, including associated footings, fasteners and grout.

Surface preparation and application of high-performance coating at all exposed existing and all new steel framing, roof decking and associated fasteners (other than new prefinished and/or stainless steel hardware).

Supply and installation of complete and functional new roof drainage system to collect roof drainage between the two hangar bays and route it to grade in a controlled manner.

Supply and installation of a bird deterrent system. Deterrent shall be mounted on the horizontal truss members throughout. System shall be a stainless steel post and tensioned cable type. Basis of design is Birdmaster Springuard Bird Proofing System.

The project will include, without limitation, the following tasks:

Review the Schematic Design provided in the RFP package.

Review site data and examine existing conditions in detail.

Upon award, determine and provide design schedule of work.

Submit list of required permits.

Engineer and design alterations and additions to existing framing.

Submit DB Design Development and DB Construction Documents for review and approval, as required.

Provide schedule of construction work.

Secure work area and provide for NPS staff access to the facility for review of work progress and for required park operations (e.g. safety, law enforcement).

Construct project.

Create and provide operations and maintenance manuals.

Provide as-constructed drawings.

2.1.2 Definition of Contract Line Items

The intent of this section shall explain, in general, what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include the costs in a related line item.

CONTRACT LINE ITEM NO. 1 – DESIGN: This item consists of:

A. Engineering and design of selective demolition throughout the work area, repairs, alterations and additions to the existing steel hangar framing and decking, and the introduction of a new roof drainage system.

CONTRACT LINE ITEM NO. 2 – HAZARDOUS MATERIALS: This item consists of:

A. Abatement and removal of hazardous materials throughout the existing hangar building.

CONTRACT LINE ITEM NO. 3 – CONSTRUCTION: This item consists of:

A. Selective demolition throughout the work area; repairs, alterations and additions to the existing steel hangar framing and corrugated roof decking; provide new roof drainage system, complete.

2.1.3 Progress Payments

Design Phase - Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables.

Construction Phase - Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the % complete shall be initiated by the Contractor under the direction of a representative of the

Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Contractor shall make the computations for payment based on the governments verification of work completed and in place for any periods for which progress payments are requested.

The Contractor shall furnish the originals of all field notes and all other records relating to the basis for payment, to the Contracting Officer, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.

2.1.4 Project Meetings

Design Meeting

After the award of the contract and acceptance of the Performance and Payment bonds, the CO will arrange a design meeting with the DBC. The meeting agenda shall include the following as a minimum:

Review and emphasize the Park needs and design objectives.

Environmental requirements.

Schedule of Values.

Design schedule (provide minimum of two color hard copies)

Note: No portion of the work can begin construction until 100% Complete DB

Construction Documents are approved for that portion and any other portion of the work that may be affected by it.

Modifications during design.

Submittals during design.

Areas available for use by the DBC.

Access requirements of the Park.

Natural and Cultural Resource Protection.

Payments to the DBC.

Preconstruction Meeting

The following Part 2 Project Requirement deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting:

Letter designating your Project Superintendent

Project Schedule with construction portion fully developed.

Accident Prevention Program

A list of subcontractors for this project (must be same as in your proposal)

Waste Management Plan

Quality Control Plan

Historic Preservation Treatment Program

After 100% Complete DB Construction Documents (“DBCDs”) are approved and prior to the start of construction, the CO will arrange an on-site Preconstruction meeting with the DBC. The on-site meeting agenda will include the following, as a minimum:

Correspondence procedures.

Roles and responsibilities.

Lines of Authority.

Progress Payments.

Submittal process.

Resolution to comments provided by NPS on the Part 2 Project Requirements.

Construction schedule (provide a minimum of two color hard copies and electronic copy in software it was created in)

Note: No portion of the work can begin construction until 100% Complete DB

Construction Documents are technically approved for that portion and any other portion of the work that may be affected by it.

Labor standards.

Payroll reports.

Modifications.

Accident reporting.

Park Rules and Regulations.

Medical emergency processes, availability, emergency numbers, and contacts.

Rules of the road, alcohol use, housekeeping, firearms, natural and cultural resource concerns.

Bridge, access road and site constraints.

Visitation and public relations.

Environmental and sustainability requirements for the Project.

Saturdays, Sundays, holidays and night work.

Progress Meetings

The DBC shall participate in weekly telephone conference calls with the Contracting Officer, and other project team members to update them on the following meeting agenda items:

Approval of minutes of previous meetings.

Submittal status.

Review off-site fabrication and delivery.

Requests for Information (RFI’s) and issues.

Modifications.

Work in progress and projected.

Schedule update.

Status of Project Record Drawings and O&M Manuals.

Other business relating to work

The DBC shall provide an agenda and take notes for each weekly conference call. Notes will be provided to the project team for review, comment, and acceptance within two days of the weekly meeting.

2.1.5 Project Schedule

General: The DBC shall provide two (2) color copies and one electronic copy of the project schedule after award and before the design meeting. The schedule shall include a detailed design phase with design deliverable submission dates, review periods as well as a summary construction schedule with important milestones included for both phases.

Fully develop the construction portion of the schedule and submit to the Contracting Officer before the Preconstruction meeting or any construction begins. The project schedule shall be updated on a monthly basis throughout the entire contract period and until project substantial completion. The status date of each schedule update shall be 10 days before the progress payment request date.

Purpose: The purpose of the project schedule shall ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the DBC. The project schedule will assist the DBC and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the DBC's monthly progress payment requests

Software: The software shall be the latest version of Microsoft Project, Primavera Project

Planner, SureTrak, or approved equal.

Schedule Development: The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.

The DBC shall use the Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The DBC's project schedule shall consist of procurement activities

(including mobilization, submittal, and the fabrication and delivery of key and long-lead procurement items) and construction activities.

The DBC's project schedule shall consist of, but not be limited to, the following for each activity:

Identify each and every activity number with numerical designations (maximum 5-digit).

Numbering of activities shall be in increments of 10.

Concise description of the work represented by the activity (maximum 48 characters).

Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.

Activity duration in whole working days with a maximum duration of 15 work days each, unless otherwise approved by the Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

In developing the project schedule, the DBC shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.

The developed project schedule shall show the sequence and interdependence of activities required for complete performance of the work. The DBC shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be the DBC's best estimate of time required to complete the activity considering the scope and resources planned for the activity. Resource loading of each activity shall list all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown. Include permit requirements and constraints.

Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the contract time.

Project Schedule Updates

Monthly updates: The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract.

If, in the judgment of the Contracting Officer, the DBC fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the DBC shall be deemed to have not provided the required information upon which the progress payment may be made, and shall be subject to retainage of a portion of the payment.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor

Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or the DBC desires to revise the project schedule, the DBC shall submit to the

Contracting Officer a written time impact analysis illustrating the influence of each modification, change, delay, or DBC request on the contract time.

Time Extensions: Activity delays shall not automatically mean that an extension of the contract time is warranted or due the DBC. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the project schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

Float: Float is not for the exclusive use or benefit of either the National Park Service or the

DBC. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.

2.1.6 Contract Modification Procedures

This section consists of administrative and procedural requirements for contract modifications.

Definitions and Allowances: Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal

Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment

Bond guarantees that the contractor will pay the labor and material costs they have incurred.

Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

Modification Proposal Pricing Requirements

General:

1. Your proposal must be received in the format and within the time frame specified in the

Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of

Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a

Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires

& tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US

Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

Establishment of Overhead and Profit Procedures:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31 which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10%

Profit………………..…8.0%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

2.2 Design Requirements

2.2.1 DB Design Development and Construction Documents

This element of work shall consist of the preparation of the DB Design Development Documents and DB Construction Documents. All documents shall be prepared using the English System of

Weights and Measurements, and shall be prepared in accordance with the DSC Design Standards.

http://www.nps.gov/dsc/workflows/dstandards.htm http://www.nps.gov/dsc/workflows/dstandards.htm

Refer to the DSC Workflows Website for detailed information and requirements for preparation of

DB Design Development Documents and DB Construction Documents.

Deliverables

The following deliverables are required (refer to Section 1.6 for schedule):

DB Design Development

DB Design Development Documents for NPS Review:

Submit paper copies of the following Draft DB Design Development Documents for review:

10 paper copies of the DB-Design Development Drawings (half-size)

10 paper copies of the Divisions 2 through 49 Outline Specifications (spiral bound, double-sided)

1 paper copy Sustainability Checklist completed through DD

Product File – electronic only

Trend chart that documents components of the SD package that have been removed and those in which have been added during the design phase

Submit one electronic copy of the Draft DB Design Development Drawings

DB Construction Documents

100% Draft DB Construction Documents for NPS Review

Submit paper copies of the following 100% Draft DB Construction Documents

10 paper copies of the DB-Construction Drawings (half-size)

10 paper copies of the Divisions 2 through 49 Construction Specifications

(Construction Specifications Institute (CSI) MasterFormat 04 Edition) A/E shall utilize and modify their own Divisions 2 through 49 Construction

Specifications templates. Divisions 2 through 49 Construction (spiral bound, double-sided)

1 paper copy Sustainability Checklist completed through CD

Product File – electronic only

10 paper copies of Design Calculations

10 paper copies of written responses to the DB Design Development

Documents Review Comments (Utilize NPS Review Form)

Trend chart that documents components of the DD package that have been

Submit one electronic copy all 100% Draft DB Construction Documents.

100% Complete DB Construction Documents for NPS Review http://www.nps.gov/dsc/workflows/del_designdevelopdb.htm http://www.nps.gov/dsc/workflows/del_constructiondb.htm

Submit paper copies of the following 100% Draft DB Construction Documents

10 paper copies of the DB-Construction Drawings (half-size)

10 paper copies of the Divisions 2 through 49 Construction Specifications

(Construction Specifications Institute (CSI) MasterFormat 04 Edition) A/E shall utilize and modify their own Divisions 2 through 49 Construction

Specifications templates. Divisions 2 through 49 Construction (spiral bound, double-sided)

1 paper copy Sustainability Checklist completed through CD

Product File – electronic only

10 paper copies of Design Calculations

10 paper copies of written responses to the 100% Draft Construction

Documents Review Comments (Utilize NPS Review Form)

Trend chart that documents components of the CD package that have been

Submit one electronic copy of resolution to all NPS 100% Complete Document

Review Comments.

Complete Stamped and Signed DB Construction Documents

Address and incorporate 100% Complete DB Construction Documents comments into the Complete Stamped and Signed DB Construction Documents and submit, for approval, per the following table, the record set of Complete Stamped and Signed

DB Construction Documents for construction, NPS archiving and general use.

COMPLETE STAMPED AND SIGNED DB

CONSTRUCTION DOCUMENTS

ELECTRONIC

FORMATS *

HARDCOPY

FORMATs

DB-Construction Drawings AutoCAD

2 Full-Size

Paper (ANSI

D)

8 Half-Size

Divisions 2 through 49 Construction Specifications PDF & MS-Word 10 sets, double sided,spiral bound

Product File PDF N/A

NPS Project Sustainability Checklist PDF & MS-Excel N/A

Supplemental Design Reports (if applicable) PDF N/A

Design Calculations (if applicable) PDF N/A

Written responses to the 100% Draft DB

Construction Documents review comments PDF & MS-Excel N/A

* The recipient of the electronic files is TIC.

2.2.2 Environmental and Sustainability Requirements for Design

The National Park Service has established environmental and sustainability requirements for the project. Notify the CO if conflicts arise between performance of the work and environmental and sustainability requirements. The National Park Service does not intend to limit alternative means of achieving these requirements.

Specific sustainability requirements for design may be found in Part 3, Performance

Requirements, of this document and the NPS Project Sustainability Checklist, http://www.nps.gov/dscw/publicforms.htm#psc. Complete this checklist by concisely explaining how each credit/requirement will be met.

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to part 3, Performance Requirements, of this document and the NPS Project Sustainability Checklist. The following are general requirements:

Air: Employ construction practices that minimize dust production and combustion byproducts.

Water: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains.

Soil: Protect against erosion and topsoil depletion.

Habitats: Protect natural habitats and ecological systems on facility site.

Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.

Waste Management: Employ processes that ensure the generation of as little waste as possible. Waste disposal in landfills shall be minimized. Recycling is a requirement of this project. Specific recycling goals were established in the NPS Project Sustainability

Checklist. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.

All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.

The DBC shall designate an on-site party (or parties) responsible for instructing workers and overseeing the environmental requirements of this project. Distribute copies of the environmental requirements to the Job Site Foreman and each Subcontractor.

http://www.nps.gov/dscw/publicforms.htm#psc

Storm Water Pollution Prevention Plan (SWPPP) or Under-An-Acre Pollution Prevention Plan

(UPPP): Plan shall describe pollution prevention control methods at Contractor staging areas, material storage areas, hazardous material abatement areas, etc.

Waste Management Plan: Prior to the scheduled Preconstruction meeting, the Contractor shall submit a draft Waste Management Plan to the Contracting Officer for approval. Develop and implement in accordance with ASTM E1609 and as required in the contract documents. The plan shall include (but not be limited to) the following:

List of the recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.

List of materials that cannot be recycled or reused with explanation or justification.

Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.

Revise and resubmit Plan as required by the Contracting Officer. Approval of the

Contractor’s Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations.

Prior to the commencement of the Work, schedule and conduct a meeting with the Contracting

Officer to discuss the proposed Waste Management Plan and to develop mutual understanding relative to details of environmental protection.

Minimize Construction Impacts

The following mitigation measures shall be implemented to minimize the impacts of construction activities:

Soil Erosion

Protect against erosion and topsoil depletion. Storm Water Pollution Prevention Plan / Under-

An-Acre Pollution Prevention Plan required.

Air and Water Pollution Control

Air quality impacts are expected to be temporary and localized. To minimize these impacts, the following actions shall be taken:

To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.

To reduce construction dust, water shall be applied to problem areas. Equipment shall be limited to the fenced project area to minimize soil disturbance and dust generation.

Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Keep volatile wastes in covered containers.

2.3.2 Schedule of Values

After contract award and before the Design Meeting, submit a schedule of dollar values based on the Contract Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. The total costs for the component parts of work shall equal the contract line item amount for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include mobilization, general condition costs, overhead or profit as a separate item.

Do not break down unit price items. Use only the contract line item amount for unit price items.

The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments.

An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting

Officer before the first progress payment is processed. A cost loaded project schedule is an acceptable substitute for a schedule of values.

2.3.3 Construction Support

Staging Areas

Construction staging sites will be limited to the smallest feasible area and located on the concrete apron adjacent to Hangar 38. Staging areas must be adequately fenced for public safety and security. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.

All staging areas shall be returned to pre-construction conditions once construction is complete.

Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the CO.

Construction access shall be via New Dorp Lane at Cedar Grove Avenue.

Structures: Trailers, Storage, Field Offices, Staging Area and Sheds: Location to be approved by the Contracting Officer.

DBC's Field Office: Field office shall be structurally sound construction, and weather tight. The location will be determined by NPS prior to issuing a Start Work Notice.

Storage Sheds: If used, provide weather tight sheds or other covered facilities for storage of materials subject to weather damage.

If used, all temporary water, sewer, sanitary facilities and electric utilities, shall be completely removed upon project completion. Remove temporary utility connections.

The location of the Staging Area for construction equipment will require CO approval.

Construction Camp: Establishment of a construction camp will not be permitted.

Construction Zones

Construction zones shall be fenced with CO approved construction barrier fencing, plastic or portable fencing, before any construction activity. The fencing shall define the construction zone and confine activity to the minimum area required for construction. All protection measures shall be clearly stated in the construction specifications, and workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing.

Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with MUTCD-2003.

Vines and “volunteer trees” growing on wall and roof surfaces can and should be removed to facilitate execution of the work. The DBC shall protect other tree trunks and root systems of trees adjacent to the work area.

Parking of Construction Vehicles

Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s).

2.3.4 Submittals during Construction

Material Submittal and Approval Procedures

The following submittals will require government approval prior to procurement or performance of the work:

All submittals pertaining to selective demolition and salvage.

All submittals pertaining to new finishes.

Submittals required to document compliance with hazardous materials abatement and disposal and waste management requirements.

All remaining materials used on the project shall be submitted to the DB Contractor’s AE.

Material submittals and AE approval documentation shall be submitted to the NPS as

“informational” submittals, no NPS approval required.

Submit all submittals required in the Project and Performance Requirements and those marked

(GOV) in the Specifications. Submit sufficient information based upon the performance specifications for the Government to make an…