Final_specifications_ _SOW_5-21-2015.pdf

PDF 200 KB Posted

Attached to
Remove and dispose of lead-based paint Federal contract opportunity
Solicitation number
P15PS01410
Issued by
Department of the Interior National Park Service

About this file

Specifications and Statement of work

View the file

Other files for this federal contract opportunity

Other files attached to Remove and dispose of lead-based paint, newest first.
File Type Posted
Revised_terms_and_conditions_5-29-2015.pdf PDF
Sol_P15PS01410_Amd_000001.pdf PDF
Terms_and_conditions.pdf PDF
SF25A.pdf PDF
Past_performance_questionnaire.docx DOCX document
5-19-2015_Drawings.pdf PDF
Sol_P15PS01410.pdf PDF
Davis_Bacon_Wages.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KLGO – 000000 02 83 33.13 - 1

LEAD-BASED PANT REMOVAL AND

DISPOSAL

SECTION 02 83 33.13 – SPECIFICATION AND STATEMENT OF WORK FOR LEAD-BASED

PAINT REMOVAL AND DISPOSAL

PART 1 - GENERAL

1.1 DESCRIPTION

A. Remove and dispose of lead-based paint from the east elevation of the White Pass Administration

Building (1900) in Klondike Gold Rush National Historical Park in Skagway, Alaska.

B. The Work includes all labor, equipment, materials and disposal to remove lead-based paint from approximately 2,200 square feet of painted exterior surfaces down to the wood substrate.

1. Painted surfaces to be removed shall include all exterior woodwork: siding, trim, window sills, stops, frames, and jambs.

2. Double hung sashes are EXCLUDED from the Work.

C. Abatement, containment, handling, transportation, and disposal of all hazardous and non-hazardous materials shall meet the requirements of all local, state, and federal regulations.

D. Skagway is a premier cruise ship destination at the end of the Inside Passage that receives up to 1 million visitors beginning the first week of May through the last week of September. The White

Pass Administration Building (1900) is located at the busiest intersection of town, which experiences foot traffic from up to five cruise ships per day and up to five arrivals and departures per day from the nearby train depot.

E. On-site parking is not available at the work site from early May to the end of September and a special after hours schedule may be necessary.

1.2 HISTORIC SIGINIFICANCE

A. The White Pass Administration Building (1990), is listed on the national Register of historic places, and is part of a district that has been designated a National Landmark in 1962.

B. Any work at this site must be performed in accordance with “The Secretary of the Interior’s

Standards for the Treatment of Historic Properties” using the latest technologies in Preservation so as to retain the integrity of Historic fabrics - reference: http://www.nps.gov/tps/standards.htm

1.3 REFERENCES

A. CFR 29 Part 1910 - Occupational Safety and Health Standards.

B. CFR 29 Part 1926 - Safety and Health Regulations for Construction.

C. CFR 40 Part 148 - Hazardous Waste Injection Restrictions.

D. CFR 40 Part 260 - Hazardous Waste Management System: General.

http://www.nps.gov/tps/standards.htm

KLGO – 000000 02 83 33.13 - 2

E. CFR 40 Part 261 - Identification and Listing of Hazardous Waste.

F. CFR 40 Part 262 - Standards Applicable to Generators of Hazardous Waste.

G. CRF 40 Part 263 - Standards Applicable to Transporters of Hazardous Waste.

H. CFR 40 Part 264 - Standards for Owners and Operations of Hazardous Waste Treatment, Storage, and Disposal Facilities.

I. CFR 40 Part 265 - Interim Status Standards for Owners and Operators of Hazardous Waste

Treatment, Storage, and Disposal Facilities.

J. CFR 40 Part 268 - Land Disposal Restrictions.

K. CFR 49 Part 172 - Hazardous Material Table, Special Provisions, Hazardous Material

Communications, Emergency Response Information, and Training Requirements.

L. CFR 49 Part 178 - Specifications for Packaging.

M. NFPA 701-2004 - Methods of Fire Test for Flame-Resistant Textiles and Films.

N. NIOSH OSHA Booklet 3142 - Lead in Construction.

O. UL 586-1996 - (Rev 2009 High-Efficiency, Particulate, Air Filter Units.

P. Z9.2-2006 - Fundamentals Governing the Design and Operation of Local Exhaust Systems.

Q. Z88.6-2006 - Respiratory Protection.

R. The Secretary of the Interior’s Standards for the Treatment of Historic Properties.

S. Department of the Interior Preservation Brief #37: Appropriate Methods for Reducing Lead-Paint

Hazards in Historic Housing.

T. State of Alaska Regulations:

1. 8 AAC 61 – Occupational Safety and Health Standards.

2. 18 AAC 60 – Solid Waste Management.

3. 18 AAC 62 – Hazardous Waste Management.

1.4 DEFINITIONS

A. Action Level: Employee exposure, without regard to use of respirations, to an airborne concentration of lead of 30 micrograms per cubic meter of air averaged over an 8-hour period. As used in this section, “30 micrograms per cubic meter of air” refers to the action level.

KLGO – 000000 02 83 33.13 - 3

B. Area Monitoring: Sampling of lead concentrations within the lead control area and inside the physical boundaries which is representative of the airborne lead concentrations which may reach the breathing zone of personnel potentially exposed to lead.

C. Physical Boundary: Area physically roped or partitioned off around an enclosed lead control area to limit unauthorized entry of personnel. As used in this section, “inside boundary” shall mean the same as “outside lead control area.”

D. Certified Industrial Hygienist (CIH): As used in this section, refers to an Industrial Hygienist employed by the Contractor and is certified by the American Board of Industrial Hygiene in comprehensive practice.

E. Change Rooms and Shower Facilities: Rooms within the designated physical boundary around the lead control area equipped with separate storage facilities for clean protective work clothing and equipment and for street clothes which prevent cross-contamination.

F. Competent Person: A person capable of identifying lead hazards in the work area and is authorized by the contractor to take corrective action.

G. Decontamination Room: Room for removal of contaminated personal protective equipment (PPE).

H. Eight-Hour Time Weighted Average (TWA): Airborne concentration of lead averaged over an 8-hour workday to which an employee is exposed.

I. High Efficiency Particulate Air (HEPA) Filter Equipment: HEPA filtered vacuuming equipment with a UL 586 filter system capable of collecting and retaining lead-contaminated paint dust. A high efficiency particulate filter means 99.97 percent efficient against 0.3 micron size particles.

J. Lead: Metallic lead, inorganic lead compounds, and organic lead soaps. Excluded from this definition are other organic lead compounds.

K. Lead Control Area: An enclosed area or structure with full containment to prevent the spread of lead dust, paint chips, or debris of lead-containing paint removal operations. The lead control area is isolated by physical boundaries to prevent unauthorized entry of personnel.

L. Lead Permissible Exposure Limit (PEL): Fifty micrograms per cubic meter of air as an 8-hour time weighted average as determined by 29 CFR 1910.1025. If an employee is exposed for more than

8 hours in a work day, the PEL shall be determined by the following formula. PEL

(micrograms/cubic meter of air) = 400/No. of hrs worked per day

M. Personnel Monitoring: Sampling of lead concentrations within the breathing zone of an employee to determine the 8-hour time weighted average concentration in accordance with 29 CFR

1910.1025. Samples shall be representative of the employee's work tasks. Breathing zone shall be considered an area within a hemisphere, forward of the shoulders, with a radius of 150 mm to 225 mm (6 to 9 inches) and the center at the nose or mouth of an employee.

KLGO – 000000 02 83 33.13 - 4

1.5 QUALITY ASSURANCE

A. Before exposure to lead-contaminated dust, provide workers with a comprehensive medical examination as required by 29 CFR 1926.62 (I) (1) (i) & (ii). The examination shall not be required if adequate records show that employees have been examined as required by 29 CFR 1926.62(I) without the last year.

B. Medical Records: Maintain complete and accurate medical records of employees in accordance with 29 CFR 1910.20.

C. CIH Responsibilities: The Contractor shall employ a Certified Industrial Hygienist who will be responsible for the following:

1. Certify Training.

2. Review and approve lead-containing paint removal plan for conformance to the applicable standards.

3. Inspect lead-containing paint removal work for conformance with the approved plan.

4. Direct monitoring.

5. Ensure work is performed in strict accordance with specifications at all times.

6. Ensure hazardous exposure to personnel and the environment are adequately controlled at all times.

D. Training: Train each employee performing paint removal, disposal, and air sampling operations prior to the time of initial job assignment, in accordance with 29 CFR 1926.62.

E. Training Certification: Submit certificates signed and dated by the CIH and by each employee stating that the employee has received training.

F. Respiratory Protection Program:

1. Furnish each employee required to wear a negative pressure respirator or other appropriate type with a respirator fit test at the time of initial fitting and at least every 6 months thereafter as required by 29 CFR 1926.62.

2. Establish and implement a respiratory protection program as required by 29 CFR 1910.134, 29

CFR 1910.1025, and 29 CFR 1926.62.

G. Hazard Communication Program: Establish and implement a Hazard Communication Program as required by 29 CFR 1910.1200.

H. Hazardous Waste Management: The Hazardous Waste Management Plan shall comply with applicable requirements of federal, state, and local hazardous waste regulations and address:

1. Identification of hazardous wastes associated with the work.

2. Estimated quantities of wastes to be generated and disposed of.

3. Names and qualifications of each contractor that will be transporting, storing, treating, and disposing of the wastes. Include the facility location and a 24-hour point of contact

4. Names and qualifications (experience and training) of personnel who will be working on-site with hazardous wastes.

KLGO – 000000 02 83 33.13 - 5

5. List of waste handling equipment to be used in performing the work, to include cleaning, volume reduction, and transport equipment.

6. Spill prevention, containment, and cleanup contingency measures to be implemented.

7. Work plan and schedule for waste containment, removal and disposal. Wastes shall be cleaned up and containerized daily.

8. Cost for hazardous waste disposal according to this plan.

9. Contractors considerations for weather conditions during planning of work schedule, material storage and disposal.

I. Safety and Health Compliance:

1. In addition to the requirements of this specification, comply with laws, ordinances, rules, and regulations of federal, state, and local authorities regarding removing, handling, storing, transporting, and disposing of lead waste materials. Comply with the applicable requirements of the current issue of 29 CFR 1910.1025. Submit matters regarding interpretation of standards to the Contracting Officer for resolution before starting work.

2. Where specification requirements and the referenced documents vary, the most stringent requirements shall apply.

J. National Park Service “Green Parks Plan”: Plan work to ensure 95% of all actions are energy efficient, bio-based and environmentally preferable. Plan work based on sustainability; adopt Best

Practices concerning work performance, products and environmental protection.

L. Pre-Construction Conference: Along with the CIH, meet with the Contracting Officer to discuss in detail the lead-containing paint removal work plan, including work procedures and precautions for the work plan.

1.6 SUBMITTALS

A. Manufacturer's Catalog Data:

1. Vacuum filters

2. Respirators

B. Instructions: Paint removal materials. Include applicable material safety data sheets.

C. Statement Certifications and Statements:

1. Qualifications of CIH: Submit name, address, and telephone number of the CIH selected to perform responsibilities in paragraph entitled “CIH Responsibilities.” Provide previous experience of the CIH. Submit proper documentation that the Industrial Hygienist is certified by the American Board of Industrial Hygiene in comprehensive practice, including certification number and date of certification/recertification.

2. Testing Laboratory: Submit the name, address, and telephone number of the testing laboratory selected to perform the monitoring, testing, and reporting of airborne concentrations of lead.

Provide proper documentation that persons performing the analysis have been judged proficient by successful participation within the last year in the National Institute for Occupational Safety and Health (NIOSH) Proficiency Analytical Testing (PAT) Program. The laboratory shall be

KLGO – 000000 02 83 33.13 - 6

accredited by the American Industrial Hygiene Association (AIHA). Provide AIHA documentation along with date of accreditation/reaccreditation.

3. Lead-Containing Paint Removal Plan:

a. Submit a detailed job-specific plan of the work procedures to be used in the removal of lead-containing paint. The plan shall include a sketch showing the location, size, and details of lead control areas, location and details of decontamination rooms, change rooms, shower facilities, and mechanical ventilation system.

b. Include in the plan, eating, drinking, smoking and restroom procedures, interface of trades, sequencing of lead related work, collected wastewater and paint debris disposal plan, air sampling plan, respirators, protective equipment, and a detailed description of the method of containment of the operation to ensure that airborne lead concentrations of 30 micrograms per cubic meter of air are not exceeded outside of the lead control area.

c. Include air sampling, training and strategy, sampling methodology, frequency, duration of sampling, and qualifications of air monitoring personnel in the air sampling portion on the plan.

d. Submit Material Safety Data Sheets for paint removal products.

4. Field Test Reports: Monitoring Results: Submit results of air monitoring samples signed by the testing laboratory employee performing the air monitoring, the employee that analyzed the sample, and the CIH within 24 hours after the air samples are taken. Notify the Contracting

Officer immediately of exposure to lead at or in excess of the action level of 30 micrograms per cubic meter of air outside of the lead control area.

5. Records:

a. Completed and signed hazardous waste manifest from treatment or disposal facility.

b. Certification of Medical Examinations.

c. Employee training certification.

PART 2 PRODUCTS

A. Paint Removal Products: Use the least toxic product suitable for the job.

PART 3 EXECUTION

3.1 PROTECTION

A. Notification: Notify the Contracting Officer 30 days prior to the start of any paint removal work.

B. Lead Control Area Requirements.

1. Establish a lead control area by completely enclosing with containment screens the area or structure where lead-containing paint removal operations will be performed.

2. Contain removal operations by the use of a negative pressure full containment system with at least one change room and with HEPA filtered exhaust.

C. Protection of Existing Work to Remain: Perform paint removal work without damage or contamination of adjacent areas. Where existing work is damaged or contaminated, restore work to its original condition.

D. Boundary Requirements: Provide physical boundaries around the lead control area by roping off the area or providing curtains, portable partitions or other enclosures to ensure that airborne

KLGO – 000000 02 83 33.13 - 7

concentrations of lead will not reach 30 micrograms per cubic meter of air outside of the lead control area.

E. Heating, Ventilating and Air Conditioning (HVAC) Systems: Shut down, lock out, and isolate

HVAC systems that supply, exhaust, or pass through the lead control areas. Seal intake and exhaust vents in the lead control area with 6-mil plastic sheet and tape. Seal seams in HVAC components that pass through the lead control area.

F. Change Room and Shower Facilities: Provide clean change rooms and shower facilities within the physical boundary around the designated lead control area in accordance with requirements of 29

CFR 1926.62.

G. Mechanical Ventilation System:

1. Use adequate ventilation to control personnel exposure to lead in accordance with 29 CFR

1926.57.

2. To the extent feasible, use fixed local exhaust ventilation connected to HEPA filters or other collection systems, approved by the industrial hygienist. Local exhaust ventilation systems shall be designed, constructed, installed, and maintained in accordance with ANSI Z9.2.

3. If air from exhaust ventilation is recirculated into the work place, the system shall have a high efficiency filter with reliable back-up filter and controls to monitor the concentration of lead in the return air and to bypass the recirculation system automatically if it fails. Air may be recirculated only where exhaust to the outside is not feasible.

H. Personnel Protection: Personnel shall wear and use protective clothing and equipment as specified herein. Eating, smoking, or drinking is not permitted in the lead control area. No one will be permitted in the lead control area unless they have been given appropriate training and protective equipment.

I. Warning Signs: Provide warning signs at approaches to lead control areas. Locate signs at such a distance that personnel may read the sign and take the necessary precautions before entering the area. Signs shall comply with the requirements of 29 CFR 1926.62.

3.2 HISTORICAL PROTECTION

A. Work performed shall be in accordance with “The Secretary of the Interior’s Standards for the

Treatment of Historic Properties” and the “Department of the Interior Preservation Brief #37:

Appropriate Methods for Reducing Lead-Paint Hazards in Historic Housing.” The Contractor shall be familiar with these publications prior to the commencement of work. Copies are available through the Department of the Interior website or project Contracting Officer.

3.3 WORK PROCEDURES

A. Perform removal of lead-containing paint in accordance with approved lead-containing paint removal plan. Use procedures and equipment required to limit occupational and environmental exposure to lead when lead-containing paint is removed in accordance with 29 CFR 1926.62.

B. Dispose of removed paint chips and associated waste in compliance with federal, state, and local requirements.

KLGO – 000000 02 83 33.13 - 8

C. Monitoring: Monitoring of airborne concentrations of lead shall be in accordance with 29 CFR

1910.1025 and as specified herein. Air monitoring, testing, and reporting shall be performed by a

CIH or an Industrial Hygiene (IH) Technician who is under the direction of the CIH:

1. The CIH or the IH Technician under the direction of the CIH shall be on the job site directing the monitoring, and inspecting the lead-containing paint removal work to ensure that the requirements of the Contract have been satisfied during the entire lead-containing paint removal operation.

2. Take personal air monitoring samples on employees who are anticipated to have the greatest risk of exposure as determined by the CIH. In addition, take air monitoring samples on at least

25 percent of the work crew or a minimum of two employees, whichever is greater, during each work shift.

3. Notify the Contracting Officer immediately of exposure to lead at or in excess of the action level of 30 micrograms per cubic meter of air outside of the lead control area.

D. Monitoring During Paint Removal Work:

1. Perform personal and area monitoring during the entire paint removal operation. Sufficient area monitoring shall be conducted at the physical boundary to ensure unprotected personnel are not exposed above 30 micrograms per cubic meter of air at all times. If the outside boundary lead levels are at or exceed 30 micrograms per cubic meter of air, work shall be stopped and the CIH shall immediately correct the condition(s) causing the increased levels and notify the

Contracting Officer immediately.

2. The CIH shall review the sampling data collected on that day to determine if condition(s) requires any further change in work methods. Removal work shall resume when approval is given by the CIH. The Contractor shall control the lead level outside of the work boundary to less than 30 micrograms per cubic meter of air at all times. As a minimum, conduct area monitoring daily on each shift in which lead paint removal operations are performed in areas immediately adjacent to the lead control area.

3. For outdoor operations, at least one sample on each shift shall be taken on the downwind side of the lead control area. If adjacent areas are contaminated, clean and visually inspect contaminated areas. The CIH shall certify that the area has been cleaned of lead contamination.

3.4 LEAD-CONTAINING PAINT REMOVAL

A. Remove paint within the areas designated in order to completely expose the substrate. Take whatever precautions are necessary to minimize damage to the underlying substrate.

B. Outside Lead Paint Removal: Select removal processes to minimize contamination of work areas with lead-contaminated dust or other lead-contaminated debris/waste. This paint removal process should be described in the lead-containing paint removal plan. Perform manual sanding and scraping to the maximum extent feasible.

3.5 CLEANUP AND DISPOSAL

A. Cleanup: Maintain surfaces of the lead control area free of accumulations of paint chips and dust.

Restrict the spread of dust and debris; keep waste from being distributed over the work area. Do not dry sweep or use compressed air to clean up the area. At the end of each shift and when the

KLGO – 000000 02 83 33.13 - 9

paint removal operation has been completed, clean the area of visible lead paint contamination by vacuuming with a HEPA filtered vacuum cleaner and wet mopping the area.

B. Certification: The CIH shall certify in writing that the inside and outside the lead control area air monitoring samples are less than 30 micrograms per cubic meter of air, the respiratory protection for the employees was adequate, the work procedures were performed in accordance with 29 CFR

1926.62, and that there were no visible accumulations of lead-contaminated paint and dust on the worksite. Do not remove the lead control area or roped-off boundary and warning signs prior to the Contracting Officer's receipt of the CIH's certification. Reclean areas showing dust or residual paint chips.

C. Testing of Lead-Containing Paint Residue and Used Abrasive: Where indicated or when directed by the Contracting Officer, test lead containing paint residue and used abrasive in accordance with

40 CFR 261 for hazardous waste.

D. Disposal:

1. Collect lead-contaminated waste, scrap, debris, bags, containers, equipment, and lead-contaminated clothing, which may produce airborne concentrations of lead particles.

2. Store removed paint, lead-contaminated clothing and equipment, and lead-contaminated dust and cleaning debris into U.S. Department of Transportation (49 CFR 178) approved 55-gallon drums. Properly label each drum to identify the type of waste (49 CFR 172) and the date lead-contaminated wastes were first put into the drum. Comply with land disposal restriction notification requirements as required by 40 CFR 268.

E. Disposal Documentation Submit written evidence that the hazardous waste treatment, storage, or disposal facility (TSD) is approved for lead disposal by the EPA and state. Submit one copy of the completed manifest, signed and dated by the initial transporter in accordance with 40 CFR 262.

F. Final Cleaning: Building shall be HEPA vacuumed and then washed with a trisodium phosphate

(TSP) solution using soft brushes and gentle spray.

END SECTION 02 83 13.13