Ft_Funston_Coastal_Trail_SOW_Final.docx
DOCX document 43 KB Posted
- Attached to
- GOGA - ASPHALT the SUNSET LOOP TRAIL Federal contract opportunity
- Solicitation number
- P15PS00829
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_P15PS00829.pdf | ||
| Past_Performance_Sheet.doc | DOC document | |
| CA29.txt | TXT text file | |
| PRESOLICITATION_NOTICE_P15pS00829.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fort Funston/Coastal Trail Asphalt overlay project P15PS00829 National Park Service, Golden Gate National Rec Area
1.0 Background
Fort Funston is a highly visited area of Golden Gate National Recreation Area. The Coastal Trail leading out of the southwest corner of the main parking area is the only Fort Funston trail that is paved, making it the only option in the area for our mobility impaired users. Due to age, wear, and exposure to the elements, the current path surface has developed cracks and buckles that leave the trail difficult for some of our visitors to use. Eroding edges of the current pathway have created drop-off points and tripping hazards for the regular users that frequent the site.
The project will reinforce the edges of the pathway and widen it to 8’. After wall edging and grade preparation has been completed (performed by NPS Trails staff) the successful contractor shall perform a 2-4” asphalt (average of 3”) overlay to the existing trail. The improvements that are intended with this project will provide an Architectural Barriers Act Accessibility Standard (ABAAS), smooth, easily traveled pathway, reduce running grades, and provide accessibility that will be suitable for all visitors.
2.0 Scope
2.0.1. Contractor shall install 15,300 square feet/ 1800’l, X 8.5’w, X 3-4” average asphalt overlay (with tack oil) of the Coastal Trail at Fort Funston. Approximately 700’l.f. will be laid on newly prepped/constructed base (mayacama red) rock surfaces. Asphalt will vary in thickness to meet specs provided by the project manager and to adjust current surface condition to (ABASS) standards for surface cross slope and running grade
2.0.2. Asphalt overlay shall be installed within an 8-9’ wide dry laid stone wall (constructed by the N.P.S.) and shall include 2 bench areas approximately 20’ X 15” or totaling 600 sq.
3.0 Objectives
3.0.1 NPS trail crew will construct an elevated stone causeway and prep the area for a contractor to install an asphalt overlay to the existing and prepared surface on the Coastal trail at Golden Gate National Recreation Area: Fort Funston, San Francisco CA with the end goal of bringing the trail to the (ABAAS) Standard.
4.0 Tasks (general)
Contractor Shall:
4.0.1 Install 1800’l, X 8.5’w, X 3” average asphalt overlay (with tack oil) of the Coastal Trail at Fort Funston. Approximately 700’l.f. shall be laid on newly prepped/constructed base (mayacama red) rock surfaces. Asphalt will vary in thickness to meet specs (provided in Tasks 4.0.6, 4.0.7, and 4.0.8.) and to adjust current surface condition to (ABASS) standards for surface cross slope and running grade.
4.0.2 Clean, sweep and blow surfaces within a half hour before applying bituminous tack oil.
4.0.3 Ensure that all causeway wall stones, park structures, and natural areas outside causeway wall are covered with drop cloths to prevent overspray of bituminous tack oil
4.0.4 Apply water to prepared surface before applying bituminous tack oil.
4.0.5 Apply bituminous tack oil at industry standard temperature to existing asphalt and pre-prepped surfaces before laying asphalt.
4.0.6 Install a 1.5” to 2” asphalt leveling course to reduce surface variations in existing asphalt surface.
4.0.7 Apply a second application of bituminous tack oil at industry standard temperature in between lifts (4.0.6. and 4.0.8.)
4.0.8 Install a finishing asphalt course equaling 1.5” to 2” in thickness as final surface layer consistent with ABAAS standard.
4.0.9 Deliver the approximate amount needed the asphalt overlay of the project totaling 200 cy (before compaction) to produce an overall average of a 3.5” surface overlay.
4.0.10 Overall compacted asphalt thickness may vary from 3” to 4” dependent upon imperfections in the existing trail with the end/finished result within ABAAS Standards.
4.0.11 Asphalt shall be laid within an 8’-9’ wide trail between dry-laid stone retaining walls, damage to stone walls during asphalt paving will be the responsibility of the contractor to repair to original state.
4.0.12 Hand tamp areas that cannot be compacted by rollers or traditional asphalt compaction machinery. Stone walls lining the outside edges of the existing asphalt or prepped areas of trail will have natural irregular shapes when needed.
4.0.13 Adhere to finished surface specs: "Contractor shall be responsible for checking to ensure the following requirements are met per Architectural Barriers Act Accessibility Standard (ABAAS), Chapter 10: Recreation Facilities, Section 1017 Trails, sub-section 1017.7.2 Cross Slope. The cross slope shall be not be steeper than 1:48. The Contractor shall construct to 1:57 cross slope in all directions. This shall allow the contractor to ensure the final product will be below 1:48. The requirements in this document are for asphalt material. If other materials will be used, it must be consulted with the NPS project manager, as other materials have different requirements."
4.0.14 Work/Project Schedule will be weather dependent, according to restrictive weather events such as heavy fog winds (due to sand build up) or other natural events that would negatively affect the outcomes of the project.
4.0.15 The park will remain open during construction. Park visitors will be present during construction, and some minor delays may occur due to visitor interactions.
4.0.16 Conduct operations to ensure the least inconvenience to the public. Trail and Parking lot closures will be permitted, when required, upon specific approval of Contracting Officer
4.0.17 Confine storage of materials to the specific job site for each project/task order. Park COR will designate a lay-down area.
4.0.18 Confine all operations to work areas of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
4.0.19 Maintain project area access for National Park Service trail crew, COTR, and other official business throughout the construction phase.
4.0.20 Allow access to and inspection of equipment by the designated Under an Acre Pollution Protection Plan (UPPP) UPPP Inspector/Project Manager.
4.1 Contractor Safety Program Requirements
4.1.1. The Contractor shall outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
4.1.2. Contractor or Foreman shall conduct onsite daily safety meetings and equipment inspections.
4.1.3. The contractor shall provide all applicable Personal Protective Equipment that meets approved NIOSH and OSHA requirements. .
4.1.4 Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual. All equipment to meet at least the NIOSH, OSHA or ANSI standards whichever apples for the particular usage.
4.1.5 Contractor or contractor foreman shall inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
4.1.6. First Aid: Contractor will provide on-site First aid kits and adequate training to ensure prompt and efficient first aid if needed.
4.1.7. Contractor shall provide approved fire extinguishers for all equipment with the potential of igniting grass, brush, trees, park furnishings, other equipment, or construction materials.
4.1.8. . A hard hat area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
4.2 Qualifications of Contractors Employees
4.2.1. The contractor shall ensure that employees are physically qualified to perform their assigned duties in a safe manner. Contractor must provide any required certifications.
4.2.2. The contractor shall not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
4.2.3. The Contractor shall ensure the operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
4.2.4. Upon request, the contractor shall submit proof of employees' qualifications to perform assigned duties in a safe manner.
4.5 Hazardous Material handling and storage
4.5.1. Hazardous Material: Contractor must train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
4.5.2. The contractor shall be responsible for all operators, contractors and equipment entering onto the work site. While functioning within the park the contractor will be required to properly cleanup, maintain, mitigate, and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous materials (either chemical or biological) from their vehicle fleet and/or other vehicle or stationary sources. Response shall be consistent with guidelines established by Federal, state and local regulations, and as outlined within the operator/contractor Safety or Hazardous materials Business Plan.
4.5.3. If a spill and release occurs, the Contractor, foreman, or operator shall contact, without impeding cleanup, notify the National Park Service emergency dispatch, 415-561-5606.
4.5.4. All vehicles rated 2 tons or greater shall be provided with enough absorbent materials to effectively immobilize the total volume of fluids contained within the vehicle. Additional absorbent materials will be stationed on site to handle spills from all other equipment.
4.5.5 Vehicles and operators transporting hazardous materials shall be DOT certified and/or registered and operators must be state licensed and knowledgeable of local emergency response and personal safety protocol.
4.5.6. Oil leaks and spills will be repaired or corrected immediately on discovery. Repairs shall be performed at the site of discovery. Oil pans and absorbent materials shall be available to effect immediate containment. Contractor shall take all necessary actions to eliminate the possible entry into any water way any oil or fuel discharges.
4.5.7. If an oil or fuel spill occurs the contractor will ensure that all contaminated soils shall be dug up and placed in appropriate safety containers, removed from the Park and disposed of according to California State regulations.
4.5.8. Post telephone numbers and reporting instructions for ambulance, poison control, physician, hospital, fire department, and police at locations on the work site and vehicles used during the execution of the project.
4.5.9. Contractor shall refuel all equipment and vehicles being used within Park boundaries at a site designated by the Project manager. All refueling will take place on an impermeable surface.
4.5.10 Contractor shall review and adhere to the rules and regulations Under an Acre Pollution Protection Plan (UPPP) Document.
4.5.11. If contractor supplies porta john or mobile restroom facilities it shall follow all standards found in the Under an Acre Pollution Protection Plan (UPPP) Document.
4.6 Accident reporting
4.6.1. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Contractor shall notify contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
4.6.2. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
4.7 Housekeeping
4.7.1. The contractor shall dispose of any and all trash generated by the project or employees on a daily basis
4.7.2. The contractor shall furnish trash receptacles with closing lids for employees waste to be kept within the designated project site or laydown space. Overnight storage of all contractor trash receptacles will be emptied daily and moved inside fenced lay down area after daily work shift is completed.
4.7.3. Upon completion of the project the Contractor shall remove all equipment, tools, materials, and waste generated by the project from the project area, laydown space, or otherwise affected areas of the Park property.
4.8 Meetings
4.8.1. After award of contract and a minimum of two weeks before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following:
1. Tentative construction schedule.
2. Correspondence procedures/exchange of pertinent contact information.
3. Park rules and regulations.
4. Project site inspection.
5. Discussion of expected timelines.
6. Designation of lay down/storage areas.
7. Review of specifications/expectations.
8. Verify equipment to be used.
9. Review contract conditions and submit an Under an Acre Pollution Protection Pan (UPPP).
10. Set schedule for future meetings.
4.8.2. Before project begins the Contractor shall field verify all new and existing dimensions affecting the work of this contract before ordering products or setting delivery schedules. The Contractor shall notify Contracting Officer/Project Manager prior to field inspection/dimension verification for final walkthrough before beginning scheduled work.
4.8.3. The Contractor shall be available to meet during project to correct quality control, safety, and logistical issues as they arise.
4.8.4. The contractor shall meet with the Project Manager before completion of the project to discuss closeout of project.
4.8.4. The contractor shall be available to discuss project issues by phone through the duration of the project.
4.9 Quality Control
4.9.1. Except for tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
4.9.2. The Contractor's job supervisory staff shall be used for quality control, supplemented as necessary by additional technicians/subcontractors. The Contractor's designated Quality Control Supervisor shall be employed full time at the project site whenever contract work is in progress.
4.9.3. The contractor shall provide means to prevent and protect the surface of dry laid stone causeway walls, park structures, and natural areas outside causeway wall from being spattered or marred.
4.9.4. Surface Tolerance: The variation between any two contacts with the surface shall not exceed 3/16 inch at their meeting/joining point. Correct all humps or depressions exceeding the specified tolerance by removing defective work and replacing it with new material at no additional expense to the Government.
4.9.5.
Density: Acceptable density of the in-place bituminous concrete pavement shall be 95 percent of the optimum values as determined from the job-mix formula. Field sampling and density determinations will be made by the Contracting Officer in accordance with AASHTO T230-68, or an acceptable nuclear procedure.
4.9.6. Along walls, and other places not accessible to the rollers, thoroughly compact mixture with hand tampers or with mechanical tampers.
4.9.7. Remove mixture that becomes loose and broken, mixed with dirt, or is in any way defective, and replace with fresh hot mixture; compact to conform to the surrounding area.
4.9.8. The running grade and cross slope of finished asphalt surface will not have obstructions, ripples, dips, gaps, or noticeable seams. The cross slope shall be not be steeper than 1:48. The Contractor shall construct to 1:57 cross slope in all directions.
4.9.9. The contractor shall ensure that all asphalt is installed at the industry standard temperature to provide results in accordance with given specifications
4.9.10. The contractor shall use a smooth steel drum roller for final rolling of asphalt surface
4.9.11. The project manager will test the finished asphalt surface with a straightedge or similar device. The variation between any two contacts with the surface shall not exceed ½ inch, any areas not complying with these tolerances shall be reworked to obtain conformity.
4.9.12. The contractor shall be responsible for any and all repairs needed to reach specifications set forth in this contract.
4.10 Special Park Land Construction Considerations
4.10.1 Work/Project Schedule shall be weather dependent, according to restrictive weather events such as heavy fog winds (due to sand build up) or other natural events that would negatively affect the outcomes of the project.
4.10.2 The park will remain open during construction. Park visitors will be present during construction, and some minor delays may occur due to visitor interactions.
4.10.3 Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Trail and Parking lot closures will be permitted, when required, upon specific approval of Contracting Officer
4.10.4 Confine storage of materials to the specific job site for each project/task order. Park COR will designate a lay-down area.
4.10.5 Preservation of Natural Features: Confine all operations to work areas of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
4.10.6 The contractor must maintain project area access for National Park Service trail crew, Project Manager, and other official business throughout the construction phase.
5.0 Delivery
5.0.1. Delivery of asphalt materials shall occur during normal project hours (from 7:00 a.m. to 4:00 p.m.) no deliveries of materials that would cause the contactor or contractor staff to remain on the Park premises beyond 5:30 p.m.
6.0 Government Furnished Property
6.0.1. The NPS project manager will designate a lay down/storage area near the worksite for the overnight and daily storage of contractor equipment, vehicles, tools and materials at the Fort Funston parking area.
6.0.2. The contractor shall not stage equipment not in use in areas outside the laydown space or project areas. During materials transfer or waiting periods contractor shall ensure that park visitor traffic will not be affected by project needs.
6.0.3. Existing Utilities: No utilities will be affected by the performance of the contract. No onsite utilities will be needed in the performance of job tasks.
6.0.4. On-site portable toilet facilities are available for use by Contractor staff.
6.0.5. Any Damage done to government property both on and off project site shall be the responsibility the of the contractor to replace, repair, or refurbish to its original state according to the direction of Project Manager. Any and all damages done to government property will be repaired at no additional cost to the government within timelines set by the Project Manager.
7.0 Security
7.0.1. Contractor must provide security fencing for all equipment left overnight in designated laydown/storage areas at worksite.
7.0.2. The government will not be held liable for the theft, vandalism, or damage of contractor property during the storage, or execution of the project.
7.0.3. Access to Northern end of project area (Muir Drive) will be subject to Project managers permission and will require contractors vehicles or equipment to be escorted by designated NPS staff.
8. Place of Performance
8.0.1. The Coastal trail at Golden Gate National Recreation Area: Fort Funston, San Francisco CA
9.0 Period of performance
9.0.1. Project shall take place approximately between July 13th and August 18th dependent upon readiness of project area and favorable weather.
10.0 Submittals
All submittals will be due before contract is granted unless otherwise stated:
10.0.1. Contractor shall present examples of similar projects within the San Francisco Bay Area that can be accessed by project manager.
Submittals of examples shall include:
1. Directions to project site.
2. Month/Year of project.
3. Any significant project information as it pertains to this contract.
4. Before and after photos of project site.
5. List of equipment used on project.
6. Accident/safety record of project containing any documentation or accidents under the definition of “reportable accidents” stated in section 4.6.1.
7. Project records including Contract stating name of company and contracting license number.
10.0.2 Contractor shall submit Division 01 documents
Division 1 documents the following items shall be submitted a minimum of one week prior to the pre-construction conference. Contracting officer will notify contractor of tentative date for the preconstruction conference.
1. Letter designating Project Superintendent
2. Construction Schedule.
3. Site Specific safety and Health plan.
4. A list of Subcontractors for this project.
5. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
6. Satisfactory evidence of liability insurance coverage and workman’s compensation for contractor and all subcontractors.
7. Waste Management plan.
8. Quality Control plan.
9. Where necessary a wildlife exclusion plan.
10.0.3 Safety record.
1. Documentation of all accidents falling within one calendar year of start date of project, accidents are defined as “reportable accidents” as defined in section 4.6.1.
2. Documentation of follow up actions/corrections of “reportable accidents”.
10.0.4 The contractor shall supply the Contracting office with the source information of asphalt as follows:
1. Name, location and address of company providing asphalt
2. Name, location, and address of Asphalt pick up site (if different than company location)
3. Type of asphalt mix
4. Weigh information/loading tag including net tonnage, load time, and company name and address.
5. All weigh tags shall equal the approximate estimation of project averages (181.3 cubic yards uncompact hot mix asphalt)
6. Distance and drive time to and from plant
10.0.5. Compaction testing will be done by the contractor showing that asphalt has been compacted to the 95% industry standard. Documentation of testing showing 95% compaction
10.0.6. The contractor shall submit an Under an Acre Pollution Prevention Plan (UPPP) and adhere to its contents where applicable throughout the project. The contractor shall discuss document conditions with the project manager during first scheduled meeting before construction.