Sol_P15PS00491.pdf

PDF 306 KB Posted

Attached to
Replace two (2) fire alarm panels. Federal contract opportunity
Solicitation number
P15PS00491
Issued by
Department of the Interior National Park Service

About this file

P15PS00491

View the file

Other files for this federal contract opportunity

Other files attached to Replace two (2) fire alarm panels., newest first.
File Type Posted
Sol_P15PS00491_Amd_000001.pdf PDF
0110151eoc.pdf PDF
WA38.pdf PDF
PAST_PERFORMANCE.docx DOCX document
KEY_PERSONNEL.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040183597

NPS, PWR - OLYM MABO

600 E. Park Avenue

Port Angeles WA 98362-6757

PPY

Mount Rainier National Park

Attn: Contracting Office 55210 238th Ave E Ashford, WA 98304-9751

HAL HOVERSTEN 360-569-6542

102/17/2015

P15PS00491

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

The purpose of this solicitation is for all supervision, labor, materials, tools, equipment and appurtenances related to the successful removal, replacement, installation and testing of two (2) fire alarm panels in accordance with the attached scope of work. One panel is required for each of the following buildings located in the Longmire, WA work area of Mount Rainier National Park, zip code

98397; the Emergency Operations Center (EOC) building L-213 and Park Warehouse building L-201.

In accordance with FAR 36.204 the magnitude of this contract is less than $25,000.00

This is a best value procurement; all work will be performed under a single firm fixed-price contract to a single contractor, wages will be subject to the

Davis-Bacon Act. The NAICS code is 238210 and the size standard is $14 Million dollars.

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

15 30 calendar days and complete it within ________________ ________________ calendar days after receiving

Scope of work.

03/04/2015

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

DOI, NPS, PWR - OLYM MABO - MORA

55210 238th. Ave. E.

Ashford WA 98304-9751

PY2

HAL HOVERSTEN

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 16

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

P15PS00491

Government POC: Jim Fuller 360-569-6720.

All vendors shall establish and maintain an active registration status and have complete representations and certifications in the System for Award Management (SAM) database prior to close of this solicitation to be considered eligible for award. The website is:

https://www.sam.gov

Delivery: 04/22/2015

Delivery Location Code: 0009816044

NPS Mount Rainier National Park

L-201 Park Warehouse

Longmire WA 98397 US

FOB: Destination

Period of Performance: 03/23/2015 to 04/22/2015

00010 Replace the fire alarm panel in the EOC and Park

Warehouse.

Vendors shall be required to register and submit invoices via the Department of the Treasury's

Internet Payment Platform (IPP):

https://www.ipp.gov

Federal Tax Exemption #53-0197091 applies to all taxes.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

P15PS00491 Replace Fire Alarm Panels Mount Rainier National Park

Table of Contents

B - Supplies or Services/Prices 2

Contract Price Schedule 2

C - Description/Specifications 3

Scope Of Work 3

D - Packaging and Marking 5

E - Inspection and Acceptance 4

52.246-12 Inspection of Construction (AUG 1996) 4

F - Deliveries or Performance 4

G - Contract Administration Data 5

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) 5

1452.201-70Authorities and Delegations (SEP 2011) 5

H - Special Contract Requirements 6

I - Contract Clauses 6

52.213-4 Terms and Conditions-Simplified Acquisitions (Other Than Commercial Items) (DEC 2014)

1452.204-70 Release of Claims (JUL 1996) 8

1452.228-70 Liability Insurance (JUL 1996) 8

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS - Internet Payment Platform (IPP) (September 2011) 10

J - List of Documents, Exhibits and Other Attachments 11

List of Documents, Exhibits, and Other Attachments 11

K - Representations, Certifications and Other Statements of Bidders 11

L - Instructions, Conditions and Notices to Bidders 11

Frequently Asked Questions 12

M - Evalation Factors 13

B - Supplies or Services/Prices SECTION B: Contract Price Schedule

CONTRACT PRICE SCHEDULE INSTRUCTIONS

On lump-sum-priced line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of errors in summations, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.

CONTRACT PRICE SCHEDULE

All work shall be performed in accordance with the attached Statement of Work, drawings, and wage determination.

Quoters must provide a price for each line item; failure to do so may render the quote unacceptable.

QUANTITY & UNIT UNIT

ITEM DESCRIPTION OF MEASURE PRICE

BASE ITEMS

1 Fire Alarm Panel Replacement at EOC 1 LS @ $___________

2 Fire Alarm Panel Replacement at Park Warehouse 1 LS @ $___________

3 Site wiring, repairs and testing. 1 LS @ $___________

__4__ Mobilization 1 LS @ $___________

Grand Total 1 LS @ $_______________

Insert your business name: _______________________________________, DUNS number: _________________________, Point of contact e-mail: __________________________________________ and

Fax number: ____________________.

My business is registered in SAM __yes __no (check one);

We have completed the online representations and certifications therein __yes __no (check one).

C - Description/Specifications Scope of Work This contract is for the replacement of the Longmire Central Fire Alarm Panel in the Emergency Operations Center (EOC) and the building fire alarm panel in the Warehouse, in Longmire, WA, Mount Rainier National Park. The work of this contract consists of the following:

EOC Central Panel: (Existing Panel is a Cerberus Pyrotronics PXL, with conventional devices)

Remove the existing fire alarm panel and dispose of out of the Park Supply and install in the same location a fire alarm panel of equal functions and zone capacities as the existing unit, with an integral dialer Connect new panel to existing 120 volt AC circuit and phone lines Identify all zones as currently labeled and label each zone in the panel

All notification or control devices (bells, door controls, etc.) shall be identified with markings that begin with a letter followed by sequential numbers for additional circuits as follows:

Signaling Line Circuits: S1, S2, S3, etc.

Initiating Device Circuits: Z1, Z2, Z3, etc.

Audible Notification (bell) Circuits: B1, B2, B3, etc.

Visible Appliance (strobe) Circuits:V1, V2, V3, etc.

Install all existing low voltage conductors from area buildings and pull stations to appropriate terminals to maintain current alarm functions

Install EOC building zones on terminal blocks and identify each location Activate new panel Test individual zones and all alarm panel functions, including call-out function to Federal

Protection Services, while accompanied by designated NPS employee

Warehouse Panel: (Existing Panel is a Gamewell Flex 404, with conventional devices) Remove the existing fire alarm panel and dispose of out of the Park Supply and install in the same location a fire alarm panel of equal functions and zone capacities as the existing unit Connect new panel to existing 120 volt AC circuit Identify all zones as currently labeled and label each zone in the panel

All notification or control devices (bells, door controls, etc.) shall be identified with markings that begin with a letter followed by sequential numbers for additional circuits as follows:

Signaling Line Circuits: S1, S2, S3, etc.

Initiating Device Circuits: Z1, Z2, Z3, etc.

Audible Notification (bell) Circuits: B1, B2, B3, etc.

Visible Appliance (strobe) Circuits:V1, V2, V3, etc.

Install all existing low voltage conductors from building devices and to Central Alarm Panel to appropriate terminals to maintain current alarm functions

Activate new panel Test individual zones and all alarm panel functions, including connection to EOC panel while accompanied by designated NPS employee

General:

All drawings, design work, construction/installation, and acceptance testing shall comply with the applicable requirements of the National Fire Protection Association (NFPA) and other applicable codes as outlined below. The standards listed, as well as all other applicable codes, standards, and good engineering practices, shall be used as "minimum" design and installation standards and guidance.

1. NFPA 13D

2. NFPA 70 – 2005 (National Electrical Code)

3. NFPA 72 – 2007 (National Fire Alarm Code)

4. NFPA 101 – 2006 (Life Safety Code)

5. NFPA 170

6. The International Building Code (IBC), 2006 edition.

7. International Fire Code (IFC), 2006 edition.

8 . UL 1971, Standard for Safety Signaling Devices for the Hearing

Impaired, 1995 edition.

9. UL 38, Standard for Safety Manually Actuated Signaling Boxes for Use with Fire Protection Signaling Systems, 2001 edition.

10. UL 268, Standard for Safety Standard for Smoke Detectors for

Fire Protective Signaling Systems, 2002 edition.

11. UL 521, Standard for Safety Heat Detectors for Fire Protection

Signaling Systems, 1994 edition.

12. UL 864, Standard for Safety Standard for Control Units for Fire

Protective Signaling Systems, 1996 edition.

13. UL 2166 - Standard for Halocarbon Clean Agent Extinguishing

System Units.

Underwriters Laboratories, Inc American Society of Mechanical Engineers American Water Works Association The Secretary of the Interior’s Standards for the Treatment of Historic Properties, Revised 1992 (36CFR 67) P.L. 89- 665 Applicable state and local codes.

D - Packaging and Marking

No clauses.

E - Inspection and Acceptance

52.246-12 Inspection of Construction (AUG 1996)

F - Deliveries or Performance

G – Contract Administration Data

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 30 calendar days after the date the Notice to Proceed is issued. The target completion date is (April 17th, 2015). The time stated for completion shall include final cleanup of the premesis.

1452.201-70Authorities and Delegations (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award.

The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor.

Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

The Contracting Officer Representative for this contract will be:

Jim Fuller Mount Rainier National Park 55210 238th Ave E Ashford, WA 98304-9751 Phone: 360-59-6720 E-mail: jim_fuller@nps.gov

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of clause) mailto:jim_fuller@nps.gov

H - Special Contract Requirements

Wage Determination Attachment 1, U.S. Department of Labor General Wage Decision WA 140038 dated 02/06/2015, is incorporated into this solicitation/contract.

I - Contract Clauses

52.213-4 Terms and Conditions—Simplified Acquisitions (Other Than Commercial Items) (DEC 2014)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.222-3, Convict Labor (June 2003) (E.O. 11755).

(ii) 52.222-21, Prohibition of Segregated Facilities (Feb 1999) (E.O. 11246).

(iii) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).

(iv) 52.222-50, Combating Trafficking in Persons (Feb 2009) (22 U.S.C. 7104(g)).

(v) 52.225-13, Restrictions on Certain Foreign Purchases (June 2008) (E.o.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

(vi) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(vii) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78 (19 U.S.C. 3805 note)).

(2) Listed below are additional clauses that apply:

(i) 52.232-1, Payments (Apr 1984).

(ii) 52.232-8, Discounts for Prompt Payment (Feb 2002).

(iii) 52.232-11, Extras (Apr 1984).

(iv) 52.232-25, Prompt Payment (Jul 2013).

(v) 52.232-39, Unenforceability of Unauthorized Obligations (Jun 2013).

(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Dec 2013)

(vii) 52.233-1, Disputes (May 2014).

(viii) 52.244-6, Subcontracts for Commercial Items (Oct 2014).

(ix) 52.253-1, Computer Generated Forms (Jan 1991).

(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013) (Pub. L.

109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at $25,000 or more).

(ii) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Jan 2014) (E.O. 13126).

(Applies to contracts for supplies exceeding the micro-purchase threshold.)

(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (May 2014) (41 U.S.C. chapter 65) (Applies to supply contracts over $15,000 in the United States, Puerto Rico, or the U.S. Virgin Islands).

(iv) 52.222-35, Equal Opportunity for Veterans (Jul 2014) (38 U.S.C. 4212) (applies to contracts of $100,000 or more).

(v) 52.222-36, Equal Employment for Workers with Disabilities (Jul 2014) (29 U.S.C. 793). (Applies to contracts over $15,000, unless the work is to be performed outside the United States by employees recruited outside the United States.) (For purposes of this clause, “United States” includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)

(vi) 52.222-37, Employment Reports on Veterans (Jul 2014) (38 U.S.C. 4212) (applies to contracts of $100,000 or more).

(vii) 52.222-41, Service Contract Labor Standards (May 2014) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed https://acquisition.gov/far/current/html/52_222.html#wp1147479 https://acquisition.gov/far/current/html/52_222.html#wp1147656 https://acquisition.gov/far/current/html/52_222.html#wp1147711 https://acquisition.gov/far/current/html/52_222.html#wp1151848 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t21t25+618+103++%2822%29%20%20AND%20%28%2822%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t21t25+618+103++%2822%29%20%20AND%20%28%2822%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t21t25+618+103++%2822%29%20%20AND%20%28%2822%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t21t25+618+103++%2822%29%20%20AND%20%28%2822%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t21t25+618+103++%2822%29%20%20AND%20%28%2822%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://acquisition.gov/far/current/html/52_223_226.html#wp1169608 https://acquisition.gov/far/current/html/52_233_240.html#wp1113329 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://acquisition.gov/far/current/html/52_233_240.html#wp1113344 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/52_232.html#wp1152483 https://acquisition.gov/far/current/html/52_232.html#wp1152592 https://acquisition.gov/far/current/html/52_232.html#wp1152616 https://acquisition.gov/far/current/html/52_232.html#wp1152998 https://acquisition.gov/far/current/html/52_232.html#wp1160005 https://acquisition.gov/far/current/html/52_232.html#wp1160491 https://acquisition.gov/far/current/html/52_233_240.html#wp1113304 https://acquisition.gov/far/current/html/52_241_244.html#wp1129139 https://acquisition.gov/far/current/html/52_248_253.html#wp1120078 https://acquisition.gov/far/current/html/52_200_206.html#wp1141649 https://acquisition.gov/far/current/html/52_222.html#wp1147630 https://acquisition.gov/far/current/html/52_222.html#wp1147649 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/52_222.html#wp1158632 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://acquisition.gov/far/current/html/52_222.html#wp1162802 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+2+78++%2829%29%20%20AND%20%28%2829%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+2+78++%2829%29%20%20AND%20%28%2829%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+2+78++%2829%29%20%20AND%20%28%2829%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+2+78++%2829%29%20%20AND%20%28%2829%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+2+78++%2829%29%20%20AND%20%28%2829%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://acquisition.gov/far/current/html/52_222.html#wp1148123 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+200+2++%2838%29%20%20AND%20%28%2838%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://acquisition.gov/far/current/html/52_222.html#wp1160021 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf.)

(viii) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).

(ix) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR® Program or Federal Energy Management Program (FEMP) will be—

(A) Delivered;

(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;

(C) Furnished by the Contractor for use by the Government; or

(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance.)

(x) 52.225-1, Buy American—Supplies (May 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold and the acquisition—

(A) Is set aside for small business concerns; or

(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).

(xi) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (May 2014) (42 U.S.C. 1792) (Applies to contracts greater than $25,000 that provide for the provision, the service, or the sale of food in the United States.)

(xii) 52.232-33, Payment by Electronic Funds Transfer—System for Award Management (Jul 2013).

(Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) database as its source of EFT information.)

(xiii) 52.232-34, Payment by Electronic Funds Transfer—Other than System for Award Management (JUL 2013). (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)

(xiv) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C.

App. 1241). (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)

(xv) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2014) (Executive Order 13658) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.)

(2) Listed below are additional clauses that may apply:

(i) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013) (Applies to contracts over $30,000).

(ii) 52.211-17, Delivery of Excess Quantities (Sept 1989) (Applies to fixed-price supplies).

(iii) 52.247-29, F.o.b. Origin (Feb 2006) (Applies to supplies if delivery is f.o.b. origin).

(iv) 52.247-34, F.o.b. Destination (Nov 1991) (Applies to supplies if delivery is f.o.b. destination).

(c) FAR 52.252-2, Clauses Incorporated by Reference (Feb 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://acquisition.gov/far

(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights—

(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

https://acquisition.gov/far/current/html/52_223_226.html#wp1168831 https://acquisition.gov/far/current/html/52_223_226.html#wp1194323 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2023_2.html#wp1081346 https://acquisition.gov/far/current/html/52_223_226.html#wp1192900 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2019_5.html#wp1086841 https://acquisition.gov/far/current/html/52_223_226.html#wp1183820 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/52_232.html#wp1153351 https://acquisition.gov/far/current/html/52_232.html#wp1153375 https://acquisition.gov/far/current/html/52_247.html#wp1156217 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t45t48+351+1++%2846%29%20%20AND%20%28%2846%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://acquisition.gov/far/current/html/Subpart%2047_5.html#wp1072915 https://acquisition.gov/far/current/html/52_222.html#wp1163027 https://acquisition.gov/far/current/html/52_222.html#wp1147505 https://acquisition.gov/far/current/html/52_222.html#wp1160021 https://acquisition.gov/far/current/html/52_207_211.html#wp1140926 https://acquisition.gov/far/current/html/52_207_211.html#wp1141265 https://acquisition.gov/far/current/html/52_247.html#wp1155640 https://acquisition.gov/far/current/html/52_247.html#wp1155803 https://acquisition.gov/far/current/html/52_248_253.html#wp1120047 https://acquisition.gov/far

(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.

(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

1452.204-70 Release of Claims (JUL 1996) After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

1452.228-70 Liability Insurance (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$100,000.00 each person $500,000.00 each occurrence $1,000,000.00 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

(c) The Contractor shall also maintain compensation insurance for employees engaged in the work, complying with the worker's compensation laws of the State in which the work is to be performed, and furnish evidence of such coverage to the Contracting Officer at the same time as the liability insurance certificate.

52.222-6 Construction Wage Rate Requirements (MAY 2014)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records (MAY 2014)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination-Debarment. (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility (MAY 2014)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)

52.232-23 Assignment of Claims. (MAY 2014

52.232-27 Prompt Payment For Construction Contracts. (MAY 2014)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

52.236-5 Material and Workmanship. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

(APR 1984)

52.236-13 Accident Prevention. (NOV 1991)

52.242-14 Suspension of Work. (APR 1984)

52.243-5 Changes and Changed Conditions. (APR 1984)

52.244-6 Subcontracts for Commercial Items. (OCT 2014)

52.246-21 Warranty of Construction. (MAR 1994) - Alternate I (APR 1984)

52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS - Internet Payment Platform (IPP) (September 2011)

Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP); https://www.ipp.gov

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions- Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Contractor’s business invoice,

2. Contractor’s signed certification required by FAR clause 52.232-5,

3. Reference schedule of base items (from Section B) for work being performed, and

4. If submitting a final invoice, also attach a signed copy of the Release of Claims form (DI 137).

CONTRACTOR’S FAILURE TO ATTACH THE REQUIRED DOCUMENTATION AS

SPECIFIED ABOVE WILL RESULT IN THE IPP INVOICE BEING REJECTED.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in www.SAM.gov record) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

ARCHEOLOGICAL FINDINGS

Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery;

notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, s/he will be compensated by an equitable adjustment under the General Provisions of the Contract.

CONDUCT OF OPERATIONS

At all times the Contractor shall conduct their organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with prior approval of the Contracting Officer.

J - List of Documents, Exhibits and Other Attachments

List of Documents, Exhibits, and Other Attachments

Attachment Number Title Date Number of Pages Cross-Reference Material Document Version

1 Davis Bacon Wage Determination 02/06/2015 7

2 Key Personnel 2 3 Past Performance 1 4 EOC Wiring Diagram 01/10/2015 1

K - Representations, Certifications, and Other Statements of Bidders

52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. (DEC 2012)

L - Instructions,Conditions, and Notices to Bidders

52.204-6 Data Universal Numbering System Number. (JUL 2013)

52.204-7 System for Award Management. (JUL 2013)

52.204-13 System for Award Management Maintenance (JUL 2013)

52.215-1 Instructions to Offerors - Competitive Acquisition. (JAN 2004)

52.222-5 Construction Wage Rate-Secondary Site of the Work. (May 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.225-10 Notice of Buy American Act Requirement - Construction Materials. (May 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American—Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before https://acquisition.gov/far/current/html/52_223_226.html#wp1169273 submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of provision)

FREQUENTLY ASKED QUESTIONS

Q1: Where can I find the specifications and drawings?

A1: All documents are attached to the solicitation at www.FedConnect.net.

Q2: Where can I find the SF1442 (Solicitation/Offer/Award form for construction, alteration, or repair) and SF30 (amendment) documents?

A2: At www.FedConnect.net website, locate the solicitation and click on the proper document links.

Q3: Can I fax or e-mail my quote?

A3: Yes, you may e-mail a copy to hal_hoversten@nps.gov or it may be faxed to 360-569-6549.

If it is <10 pages to print and contains a signature; e-mail is preferred. The offeror bears full responsibility for on-time delivery of the quote to the Contracting Officer; there will be no relief given for undeliverable e-mails or faxes that aren't received in time. You may also send it by mail.

Q4: Are there any other requirements?

A4: Prior to submission of a quote, you must:

(a) Maintain a current profile in the System for Award Management database (www.SAM.gov);

(b) Have completed the online submission of annual representations and certifications (part of www.SAM.gov).

Q5: What should I include so that my quote is complete? Note that incomplete quotes may be disqualified from further consideration, particularly if the government is unable to perform a meaningful evaluation based on the submitted materials; see below.

A5: * Completed SF1442, with amendments acknowledged (if any are posted) and signature, and price schedule (use Section B of this document);

https://acquisition.gov/far/current/html/52_223_226.html#wp1169273 https://acquisition.gov/far/current/html/52_223_226.html#wp1169273 https://acquisition.gov/far/current/html/FormsStandard62.html#wp1177057 https://acquisition.gov/far/current/html/FormsStandard62.html#wp1177057 https://acquisition.gov/far/current/html/FormsStandard62.html#wp1177057 https://acquisition.gov/far/current/html/FormsStandard62.html#wp1177057 https://acquisition.gov/far/current/html/FormsStandard62.html#wp1177057 https://acquisition.gov/far/current/html/52_223_226.html#wp1169273 file:///C:/Users/hhoversten/Desktop/MORA-MNT-Fire%20Alarm%20Panels/hal_hoversten@nps.gov

* A brief work plan describing your approach to the project that demonstrates your understanding of the requirements and the capabilities and experience you bring to it.