P09_Attachment 1_PWS.pdf

PDF 336 KB Posted

Attached to
J045--Type B Dead Leg Removal SDVOSB Set Aside Federal contract opportunity
Solicitation number
36C24123Q0591
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1

View the file

Other files for this federal contract opportunity

Other files attached to J045--Type B Dead Leg Removal SDVOSB Set Aside, newest first.
File Type Posted
36C24123Q0591_1.docx DOCX document
S02_Attachment 5_VARR 852.219-75_Certificate of Compliance.pdf PDF
S02_Attachment 2_PWS Drawings.pdf PDF
S02_Attachment 4_Past Performance Worsheet.xlsx XLSX spreadsheet
S02_Attachment 3 Price Schedule.xlsx XLSX spreadsheet
S02 - Combined Synopsis-Solicitation_Dead Leg.docx DOCX document
36C24123Q0591.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement Department of Veterans Affairs (VA)

Medical Center, Leeds MA Type B Dead Leg Removal

1. GENERAL

The VA Central Western Mass requires the removal of Type B dead legs. Type B dead legs are defined as any stretch of piping greater in length than two times the diameter of the source piping terminating at an infrequently used fixture. Type B dead legs have been identified in Buildings 1, 4, 5, 7, 9, 12, 16 and 22 that shall be removed from the domestic water distribution system.

2. PROJECT SCOPE OF WORK

Work shall consist of the removal of Type B dead legs and associated fixtures, This includes the following task:

a) Review Contract Drawings.

b) Provide the names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA Competent/Qualified Person(s) requirements.

c) No work shall be performed unless a designated Competent Person is present on the job site.

d) Contractor to comply with ICRA requirements.

e) Where the source of a dead leg could not be isolated and other areas will be impacted, the

Contractor is to submit the request in writing 15 calendar days prior to the desired time and shall receive approval before shutdown.

f) Dead leg piping identified, and associated fixtures shall be demolished back to source piping as noted on drawings. The existing “Tee” at connection to source piping shall be removed from the source piping. Source piping shall be modified to replace the existing “Tee” configuration with union fittings and a straight run of piping to completely eliminate all dead legs. Note only select fixtures shown with demolition hatching shall be demolished, otherwise the fixture shall remain and the associated piping serving that fixture shall be demolished back to the source and the existing fixture shall remain in place.

a. Prior to removal of any dead leg piping, Contractor shall verify pipe size, routing, and fixtures served to ensure that removal of dead leg piping will not impede service to active fixtures.

b. The use of press connect type fittings is prohibited.

g) Contractor is responsible for cutting existing wall/ceiling/floor and patching to match

(like in kind) existing . The Contractor shall remove/replace existing ceiling tiles and grid as required to accomplish indicated plumbing work.

h) The contractor shall repair or replace pipe insulation.

i) When removal of dead leg piping or associated fixtures require architectural demolition, Contractor shall restore to match existing finish and fire rating of the existing surface.

j) Penetrations shall be properly sealed with approved firestop or joint sealants according to wall rating. Spray foam is not permitted.

k) The Contractor shall patch and repair all pipe penetrations where existing piping is demolished to match existing finish and fire rating.

l) Asbestos containing material directly related to work being performed shall be remediated and properly disposed of per Massachusetts Department of Environmental Protection and Department of Labor Standards regulations.

m) All piping that has been exposed as a result of any work within the contract shall be re-insulated.

n) Abandoned Lines:

a. Pipes and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but cannot be entirely removed, shall be sealed, capped or plugged at the main or branch they originate from in an approved method and as accepted by the COR.

b. The intent is that those that are so embedded in existing concrete walls or floors that they cannot fully be removed without compromising the structure can be capped. These shall be fully investigated by the contractor and reviewed and accepted by the COR.

c. The lines shall not be capped in any finished or unfinished areas, but shall be removed and sealed, capped or plugged only in masonry, CMU, concrete walls, concrete ceilings or concrete floors where they penetrate those materials or if accepted by the COR within walls or partitions, so that they are completely behind the finished surface.

o) Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. All hot work will require a permit. Coordinate with COR 72 hours in advance to obtain a hot work permit.

p) Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in designated areas (subject to change). Parking in designated patient parking areas is strictly prohibited. Parking on grass is also prohibited. Parking in roadways is prohibited. Parking for equipment necessary to perform the work will be authorized in advance of starting the project.

q) At the end of each workday, the site shall be left clean and free of construction debris.

r) Work will be in accordance with applicable VHA and OSHA standards and regulations.

s) Building 1 Type B dead leg removal will have to be off hours (6pm-7am).

t) Building 4 noisy work will have to be off hours (6pm-7am).

u) All work in crawl spaces are considered confined spaces.

3. The performance period for this work is 120 calendar days from the time of award, unless other time frames are approved in writing by the Contracting office.