This scope of work document outlines the requirements for inspecting, adjusting, and reporting on 400 smoke dampers across numerous buildings at the Tomah VA Medical Center campus in Tomah, Wisconsin. Key aspects of the scope of work include surveying all smoke dampers, inspecting and adjusting damper operation as needed, installing 60 access panels, and providing a final report documenting inspection results. The contractor will be provided access to facility drawings and is responsible for field verifying damper locations and updating documentation. The performance period is 90 calendar days from notice to proceed. This pre-solicitation notice provides advance information for solicitation number 36C25221B0016 regarding inspecting the campus fire damper system (project number 676-21-101). The procurement is set aside for service-disabled veteran-owned small businesses and has an estimated price range of $25,000 to $100,000. A pre-bid site visit is scheduled for the week of June 1, 2021. Interested vendors should monitor the beta.sam.gov website for solicitation release around May 27, 2021 and any subsequent amendments.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25221B0016.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
04/13/2021
Tomah VA Medical Center Project Engineering
SCOPE OF WORK MEMORANDUM
1. Project Data:
A. Title: Correct Campus Fire Dampers B. Location: VA Medical Center, Tomah, Wisconsin Campus Wide C. Project #: 676-20-101 D. COR: James Conn E. Time requirement: 90 days from Notice to Proceed
Provide work in accordance with federal, state, and local authorities.
Project conditions:
The intent of this project is to Survey, Inspect/Adjust, and Report 400 smoke dampers in the numerous facility buildings. This will include installing 60 access panels in various locations.
SCOPE OF WORK
676-20-101
Repair Campus Fire-Smoke Damper Inspection Tomah VAMC, Tomah WI 54660
A. INSPECTION OF SITE OF PROPOSED WORK:
Before submitting a proposal on the work specified herein, the bidder shall examine the site and familiarize themselves with all existing conditions and limitations. No extra compensation will be allowed because of the Contractor’s misunderstanding as to the amount of work involved or because of lack of knowledge of any existing conditions. Permission for inspection may be obtained from James Conn, COR at (608) 790-6302.
Contractor shall contact COR prior to entry into the complex.
B. FACILITY STATUS:
The VA Tomah Campus is occupied and operated on a 24-hour basis and shall remain in this status throughout the performance of all assigned work. All construction barriers, infection control barriers, construction signs, and project identification signs shall be the responsibility of the contractor to furnish and install as necessary throughout the various phases of this project.
C. DESCRIPTION OF WORK:
1. The Contractor shall furnish all labor, equipment, tools, materials, and supervision necessary to perform all work repairs in strict accordance with this Statement of Work.
2. All work shall be performed in accordance with all current NFPA, Local, State and Federal building codes and all stated specific requirements.
D. TIME REQUIREMENTS:
1. Time requirement: Length of Repair time frame is – 90 calendar days from signed Notice to Proceed.
E. PRINCIPAL FEATURES:
1. Survey of Current Fire Dampers:
a) The contractor will be allowed access to the hard copy drawing file of the VA Projects Section. The contractor will identify all fire and smoke dampers for Buildings 400, 401, 402, 403, 404, 405, 406, 407, 408, 409, 410, 411, 412, 424, 452 and 36.
Approximately 400 fire dampers (based on square footage of buildings).
b) The contractor will field verify locations of each building, identifying locations for all dampers and update spreadsheet showing building, floor, room number, and damper ID number.
2. Inspection of Fire Dampers:
a) INSPECTION SERVICES TO BE PROVIDED. Based on current campus facility drawings and other information provided to contractor, Contractor agrees to provide the following inspection services with respect to customer’s dampers
b) Use all commercially reasonable efforts to locate and, once located and accessed, operate (i.e., actuate) ALL dampers in the facilities or otherwise identify inoperable dampers for immediate repair/replacement.
c) Remove and reset fusible links on fire dampers, to verify such Fire Damper fully closes and if necessary, replace any fusible link that is compromised (per National Fire Protection Association Code).
d) Lubricate all moving parts on each Damper.
e) Clear each damper of any debris that would impede such damper’s normal operation.
f) Coordinate with COR and local fire department to place facility fire alarm system in “test mode”, if necessary, to conduct inspection of the smoke and/or combination Dampers.
g) Manually activate actuators on electric and pneumatic smoke and/or combination
Dampers to verify proper operation of such damper.
h) If there is no existing access to a Damper, then proper sized access doors, as reasonably determined by COR, will be installed to facilitate future inspection and service.
Approximately 60 service panels will be installed.
i) Identify on contractor developed spreadsheet the location of each damper and place identification stickers/labels on ceilings or other location to assist in locating such dampers following inspection.
3. Report of Fire Dampers. On conclusion of the performance of the Inspection Services, Fire and Smoke Damper Inspection Contractor will provide Customer with a spreadsheet style report, which is intended to provide evidence of damper inspection for submission to applicable agencies, such as
Joint Commission and other Fire Protection Agencies and comply with NFPA 105 and NFPA 80 requirements. The Report shall include:
a) A listing of the location of each Damper, such Damper’s number (if no number is assigned, work with facilities staff to assign a number) and whether such damper passed or failed; if a damper failed, a detailed explanation of such failure shall be provided.
b) A stamped metal tag will be affixed to each damper with report cross-reference number.
c) Digital photographs of each damper before and after performance of the inspection services (showing each Damper opened and, where operable, closed).
4. Install Access Panels
a) Installation of access panels for up to 60 locations.
b) This portion of work requires diligent prior coordination and planning of demolition and installation.
c) Supplied Interim Life Safety Management (ILSM) forms will be completed and forwarded to the COR for all work locations 1 week prior to start of work.
d) ICRA barriers will be required for all construction work. Although not required, the use of a “shark tank” style ICRA barrier system is recommended due to the amount of locations.
e) Access panels will match existing surface color.
5. STANDARD OF INSPECTION SERVICES.
Infection Control Procedure. The Inspection Service will be completed in a workmanlike manner. While performing such inspection and services, contractor will utilize reasonable infection control procedures. Without limiting the foregoing, contractor will adhere to customer’s infection control risk assessments (“ICRAs”). Although not required, the use of a hard-sided mobile containment unit is highly encouraged for this work. Contractor shall provide all proposed repair action data and information to CO/COR for approval and before the start of repairs.
6. Other Deliverables
a) Contractor will provide the following:
1) Testing result documentation
2) Inventory sheet with locations and cross-reference number
3) Contractor to complete Utility Outage documents and coordinate utility shutdowns with COR and CCR.
4) DVD or CD with photographic evidence of damper operation. Files to be organized and identified by building, floor, room, and cross-reference number.
F. GENERAL:
1. Contractor shall be responsible for all temporary marking and construction signage during the demolition and construction phases.
2. Contractor shall submit a construction schedule for approval prior to work start. Work under this contract shall be accomplished during normal Tomah VAMC business working hours. Tomah VAMC business working hours are 7:00am through 4:30pm Monday through Friday, excluding holidays.
Construction schedule shall be approved by the COR prior to work start. Contractor may work off hours (evenings and weekends) if desired with prior approval of the COR. Contractor shall have site Superintendence represented during all requested off hour work schedules.
3. Government personnel will be responsible for the moving of any Government equipment and materials in all affected areas.
4. All phasing, scheduling, utility shutdown and coordination of government property needing to be moved/removed or provided shall be done through the COR.
5. Demolition shall be performed with a minimum amount of damage to adjacent property not included in this contract, which is to remain. Any damage to such existing work resulting from demolition work shall be considered a part of work included in this contract and is the responsibility of the contractor and shall be repaired upon completion of project.
6. If removal of materials discloses defective materials, which should be replaced, necessitating work over and above the scope of this contract, Contractor shall immediately contact the Contracting Officer or his/her duly appointed representative in order that corrective action may be taken.
7. Contractor shall take extra measures to ensure any significant amounts of dust and dirt generated from this project are contained within the immediate construction area. Any dirt and debris tracked outside of the immediate working areas will be the responsibility of the contractor for clean up if necessary. Any work being done shall be done in such a manner as to create a minimal amount of disruption to the ongoing work mission on the property and within the remainder of the complex. See attached Pre- Construction Risk Assessment (PCRA) and Infection Control Risk Assessment (ICRA) for details.
8. During the demolition and repair phases contractor shall ensure that all work is accomplished in a safe manner in accordance with OSHA requirements. Contractor shall ensure that all areas where work is to be performed are secured and safe during and at the end of each workday.
9. All non-hazardous excess material and debris generated from this project shall be disposed of off site in a
State of Wisconsin licensed landfill upon completion of project. The Contractor shall remove all debris resulting from this contract from the site.
a) With each application for progress payment, Contractor shall submit a summary of construction and demolition debris diversion and disposal including beginning and ending dates of period covered.
b) The Contractor shall quantify all materials diverted from landfill disposal through salvage or recycling during the period with the receiving parties, dates removed, transportation costs, weight tickets, manifests, invoices. Include the net total costs or savings for each salvaged or recycled material. Delivered to COR upon each site removal.
c) The Contractor shall quantify all materials disposed of during the period with the receiving parties, dates removed, transportation costs, weight tickets, tipping fees, manifests, invoices.
Include the net total costs for each disposal. Delivered to COR upon each site removal.
10. Public restrooms will be available for use during contract. Contractor shall not wash construction tools and equipment in any facility bathroom sinks/etc. The Tomah VA will provide any water needed for construction purposes. Contractor shall coordinate with COR for locations.
G. PROTECTION:
1. All existing station complex property shall be suitably protected against damage and it shall be the Contractor’s responsibility to replace any such items as may become damaged as a result of his failure or negligence in fully protecting same. Any damage done to the buildings or grounds by the contractor during the construction period will be the responsibility of the contractor and shall be repaired upon completion of project.
H. STORAGE AREA:
Storage area will be available at the VAMC Campus during construction phases. Contractor shall coordinate with project COR for storage location.
I. SAFETY:
Safety is the responsibility of the Contractor. Contractor shall submit a safety plan for approval prior to work start. Contractor shall assume all liability for damage or injury. Contractor shall cease operations and notify Contracting Officer’s Representative if safety appears to be endangered. Do not resume operations until safety is restored. All work shall be performed in accordance with all applicable VHA/OSHA standards. See Attachment B for PCRA (Pre-Construction Risk Assessment)
J. INFECTION CONTROL:
1. See Attachment C for Infection Control Risk Assessment (ICRA) for details of Contractors responsibility to maintain a clean work environment during construction.
K. INTERIM UTILITY SYSTEM OUTAGE MEASURES:
1. See Attachment E for IUSOM for details of Contractors responsibility to schedule with the COR the utility shutdown ensuring a safe work environment during repairs. Must submit 14 days in advance of expected date of outage.
L. INTERIM LIFE SAFETY ASSESSMENT:
1. See Attachment D for ILSA/ILSM for details of Contractors responsibility to schedule with the COR the patient/pedestrian traffic zone closure ensuring a safe work environment during repairs.
M. PHYSICAL SECURITY:
1. Contractor Identification
a) On the first day of work, the Contractor shall coordinate with COR/Resident Engineer to acquire the proper security badging. Identification badges shall be worn and visible on your person, at all times while on campus.
b) Contractor shall keep issued Identification badge on their person when leaving campus.
There will be instances that the VA Police will be verifying ID’s at the entrance to the campus and identification will be required. Please have ID’s with you.
c) When project is complete each person will be REQUIRED to turn their Identification Badges back into the Tomah VA Police.
2. Contractor Access and Key Requests
a) Contractor shall coordinate with COR/Resident Engineer to request any required keys needed to gain access into any required non-public spaces. Request shall be made via email to COR/Resident Engineer. COR/Resident Engineer will coordinate internal process with Contractor for issuance. Email requests for keys shall have the following information.
1) Name of Contractor
2) Name of Company that Contractor works for
3) Type(s) of key(s) that is/are being requested
4) Quantity of each key needed.
END OF SECTION
VAMC TOMAH
Pre-Construction Risk Assessment (PCRA)
Attachment B (MCM FS – 50)
Project: Location(s): Start Date:
COTR: Contractor:
Brief Description of Work:
Category Factors YES N/A Initials Noise *Industrial Hygienist (IH)
Impact, Duration
Vibration *Industrial Hygienist (IH)
Tool use, Demolition, Distance
Infection Control *Infection Control Coordinator
Category of Risk [1] see below Level: I - II - III - IV
Dust *Infection Control Coordinator
Cutting, Grinding, Sanding, etc.
Life Safety Impact *Fire Department
ILSM Issues: [2] – see below
Security *Chief, Police Service
Site Security, Access Control
Disruption of Utilities *COTR - Facilities
Planned Shutdowns, Construction Near Utility System Supplies
[1] Infection Control Risk Assessment (ICRA) is for evaluation of the level of practices necessary to provide appropriate levels of patient safety.
[2] ILSM Risk Assessment is for determining whether ILSM are necessary and which ILSM are to be implemented.
Other Risk Assessments: YES N/A Permit Required Confined Space (PRCS) entry will be necessary. *FD Asbestos/lead or other hazardous abatement will be necessary. *IH Construction debris will be produced. (Recycling Program) *IH Chemicals will be on site. (Hazard Communication/MSDS sheets necessary.) *IH Compressed gas cylinders will be on site. (Appropriate storage) *IH Penetration in floors, walls, ceilings will be necessary. (Permit required) *FD Cutting, burning, or welding will be necessary. (Hot Work Permit) *FD Off tour construction/work will be necessary. (Supervision) *FD Lock-Out/Tag-Out of the following systems be necessary: *Facilities
□ Domestic Water □ Electrical Systems □ HVAC System □ Medical Gas
□ Steam Systems □ Security Alarms □ IT Systems
Safety/FD/designee COR Date
Concerns to address: Measures to take:
Select Control Procedures:
Impact of Building Trades on Healthcare
System Possible Interruption Possible Effect to Patients Electrical - Changing position of switches and breakers
- Cutting or splicing into wires
- Disconnecting wires or terminals
- Disturbing Junction
Boxes/Electrical Panels
- Core Drilling
- Demolition of walls
- Excavation
Electrical Systems provides LIFE SUPPORT (Directly and Indirectly)
- Can cause DEATH to patients
Water Lines - Turning valves
- Cutting into lines
- Demolition & Excavation
HVAC, GPICU, X Ray, etc Can cause DEATH to patients Infection Control issues Major Cleanup issues
Medical Gases:
Oxygen Air Vacuum Nitrous Oxide Nitrogen
- Cutting or disturbing into lines (labeled, unlabeled)
- Changing valve positions
- Deactivating alarms
- Demolition & Excavation
Oxygen, vacuum, air, etc.
GPICU, Med/Surg.
Can cause DEATH to patients
HVAC - Shutting down
- Modifying
- Changing controls
- Cutting into the roof
- Producing foul odors near intakes
- Cutting into chilled water lines
- Obstruct fresh air intake
Temperature is critical in GPICU, etc. Infection Control issues Major Air Quality Issues
Fire Alarm and Sprinklers - ANY modifications
- covering or removing smoke heads
- Demolition & Excavation
- Damage or set off sprinkler heads
- Duct work modifications
- Compromising Fire Safety
- False Alarms
- Floods
- Major disruptions and distractions
ALL THE ABOVE CAN
RESULT IN DEATH
Code Alarms Nurse Call Wander Guards
- Demolition & Excavation
- Unplugging
- Changing position of switches/breakers
Lack of communicating system can result in patient death or injury
Select Control Procedures:
VAMC TOMAH
Infection Control Risk Assessment (ICRA)
Attachment C (MCM FS – 50)
Step 1. - Use the following chart to identify the Type of Construction Project Activity (Type A-D)
Type A
Inspect and Non-invasive Activities: Includes, but not limited to:
Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet
Painting (but not sanding) Wallcovering, electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection
Type B Small scale, short duration activities which create minimal dust: Includes, but not limited to:
Installation of telephone and computer cabling Access to chase spaces Cutting of walls or ceiling where dust migration can be controlled
Type C Work that generates a moderate t high level of dust or requires demolition or removal of any fixed building components or assemblies: Includes, but not limited to:
Sanding of walls for painting or wall covering Removal of floorcovering, ceiling tiles and casework New wall construction Minor duct work or electrical work above ceilings Major cabling activities Any activity which cannot be completed within a single work shift
Type D
Major demolition and construction projects: Includes, but not limited to:
Activities that require consecutive work shifts.
Requires heavy demolition or removal of a complete cabling system.
New construction
Selected Type of Construction:
Step 2. - Using the following table, identify the Patient Risk Group that will be affected. If more than one group is affected, select the higher risk group.
Low Risk Medium Risk High Risk Highest Risk Office areas Cardiology
Echocardiography Endoscopy Nuclear Medicine Physical Therapy Radiology/MRI Respiratory Therapy
CCU
Emergency Room Laboratories Outpatient Surgery Pharmacy Post Anesthesia Care Unit Surgical Units
Any area caring for immunocompromised patients
Cardiac Cath Lab Central Supply Intensive Care Units Medical Units Negative airflow rooms Oncology Operating Rooms
Select Patient Risk Group:
Step 3. - Match the Patient Risk Group with the planned Construction Project Type (A, B, C, D) on the following matrix, to find the Class of Precautions (I, II, III, IV) or level of infection control activities required.
Patient Risk Group
Type A Type B Type C Type D
Low risk I II II III/IV Medium risk I II III IV High risk I II III/IV IV Highest risk II III/IV III/IV IV
Attachment C (MCM FS – 50)
During Construction Project
Upon Completion of Projects
C la ss I
1. Execute work by method to minimize raising dust from construction operations
2. Immediately replace a ceiling tile displaced for visual inspection
1. Clean work upon completion of task
C la ss
II
1. Provide active means to prevent airborne dust from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting
3. Seal unused doors with duct tape
4. Block off and seal air vents.
5. Place dust mat at entrance and exit of work area.
6. Remove or isolate HVAC system in areas where work is being performed
1. Wipe work surfaces with disinfectant.
2. Contain construction waste before transport in tightly covered containers.
3. Wet mop &/or vacuum before leaving work area.
4. Remove isolation of HVAC system in area where work is being performed.
C la ss
II
I
1. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers, i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering & sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within worksite utilizing HEPA-equipped air filtration units.
4. Contain construction waste before transportation in tightly covered containers.
5. Cover transport receptacles or carts. Tape covering unless solid lid is used.
1. Do not remove barriers from work area until completed project is inspected by Safety Management & Infection Control & thoroughly cleaned by Environmental Management.
2. Remove barrier materials carefully to minimize spreading of dirt & debris associated with construction.
3. Vacuum work area with HEPA-filtered vacuums.
4. Wet mop with disinfectant.
5. Remove isolation of HVAC system in areas where work is being performed.
C la ss
IV
1. Isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers, i.e., sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering & sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within worksite utilizing HEPA-equipped air filtration units.
4. Seal holes, pipes, conduits and punctures appropriately.
5. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site; or the can wear cloth or paper coveralls that are removed each time they leave the work site.
6. All personnel entering the work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.
7. Do not remove barriers from work area until completed project is inspected by Safety Management & Infection Control & thoroughly cleaned by Environmental Management.
1. Remove barrier materials carefully to minimize spreading of dirt & debris associated with construction.
2. Contain construction waste before transport in tightly covered containers.
3. Cover transport receptacles or carts.
Tape covering unless solid lid.
4. Vacuum work area with HEPA-filtered vacuums.
5. Wet mop with disinfectant.
6. Remove isolation of HVAC system in areas where work is being performed.
Note: Infection Control approval will be required when Construction Activity and Risk Level indicate that Class III or Class IV control procedures are necessary.
Project Class Type
VAMC Tomah Interim Life Safety Measures (ILSM)
Attachment D (MCM FS -50)
Project: Location(s): Evaluation Date: Start Date:
COTR: Contractor:
Guidelines Y/N If any answer is no, need ILSM in place:
Will exit egress routes from occupied areas remained unchanged?
Will exit stairs remain unobstructed & fire separated?
Will sprinkler system stay functional?
Will fire and smoke compartments remain intact and unchanged?
Will fire alarm detection systems remain functional & unimpaired?
Will construction area be separated by noncombustible smoke tight partitions?
Will access to emergency access by fire department remain unobstructed?
Will the construction area have two remote exits?
Adequate distance to exit?
Hazardous areas protected?
Interim Life Safety Measures (ILSM) – circle the letters for action required (Refer to Matrix)
a. Ensure Egress h. Prohibit Smoking
b. Ensure Emergency Forces Access i. Conduct 2 Fire Drills per Shift per Quarter
c. Ensure Fire Department Notification j. Increase Hazard Surveillance
d. Ensuring Operational Life Safety Systems k. Compartmentation Training of Personnel
e. Temporary Construction Partitions l. Conduct Organizational Training on Life
Safety
f. Additional Fire Fighting Equipment m. Daily removal of debris and hazardous waste material
g. Control Combustible Loading n. Institute a Fire Watch
Life Safety Narrative:
Assessed by: Fire Department Date
Agreed by: COTR Date
Contractor Date
O
AFFECTED SYSTEMS: STEAM WATER NORMAL POWER EMERGENCY POWER
NURSE CALL MED. GAS
OTHER
FIRE PANEL FIRE SUPPRESSION ELEVATOR
AFFECTED BUILDINGS/LOCATIONS:
INTERIM MEASURES REQUIRED:
AFFECTED STAFF NOTIFIED COMMENTS:
ADDITIONAL EQUIPMENT REQUIRED SPECIFY:
BACK-UP PROCEDURES IN PLACE SPECIFY:
EMERGENCY PROCEDURES REVIEWED COMMENTS:
OTHER:
OTHER:
ADDITIONAL COMMENTS:
REQUEST APPROVED BY: APPROVED DATE:
WORK COMPLETION REVIEW: WORK COMPLETION DATE:
OUTAGE FOLLOW UP:
INTERIM UTILITY SYSTEM OUTAGE MEASURES
REQUESTING SHOP: Project Section NAME OF REQUESTER: David Martin
DATE REQUESTED:
WORK START DATE:
PROJECT NUMBER:
676-19-116
AFFECTED TIMEFRAME:
DESCRIPTION OF W RK/PROJECT: Repair Campus Life Safety Findings
NEW EQUIPMENT CHECK – IN SHEET
Equipment Nomenclature: PM# Additional Replacement Replacement EE# Turn-in:
Parent System Child of Parent System Manufacturer:
Model: Serial #:
Service: CMR: CMR Official’s:
Location: Tomah Bldg: Wing: Room:
Vendor:
Address:
Phone: ( ) PO#: Acq. Value: $ Acq. Date: Warranty Exp: Life Exp: Years
CSN:
Safety & Operational Inspection
1. Ground Resistance: 2. Electrical Leakage: ua
3. Operational/Functional Check:
4. Manuals:
A. Operator: B. Service:
C. Schematics/Parts Lists/Diagrams:
5. Set Up/Assembled by: Vendor:
6. Technical/Maintenance Training Needed? YES NO
Accepted Not Accepted By: Date:
Comments:
PM Program Evaluation/Assignment
1. Equipment Category: 2. Resp. Shop:
3. Has this type of equipment been evaluated before? YES NO
4. PM: A. Electrical Safety Inspection Only
B. PM Needed, PM Program Guide # , or Procedures to be written by:
C. None
5. Freq/hrs: Standard Equipment Category Freq. Hours & Criticality
Change Defaults: Freq: Hrs: Criticality:
Freq: Hrs: Criticality:
676-CXXXX
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
VHATOMConnJ Highlight
| 676-20-101 Correct Campus Fire Dampers SOW 04132021 |
| SCOPE OF WORK MEMORANDUM |
| A. Title: Correct Campus Fire Dampers |
| 1. The Contractor shall furnish all labor, equipment, tools, materials, and supervision necessary to perform all work repairs in strict accordance with this Statement of Work. |
| Note: Infection Control approval will be required when Construction Activity and Risk Level indicate that Class III or Class IV control procedures are necessary. |