NYC - GEN215B.pdf

PDF 746 KB Posted

Attached to
H345--Backflow Preventer Inspections Federal contract opportunity
Solicitation number
36C24222Q0571
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

View the file

Other files for this federal contract opportunity

Other files attached to H345--Backflow Preventer Inspections, newest first.
File Type Posted
36C24222Q0571 0001.pdf PDF
36C24222Q0571 0001_1.docx DOCX document
Brand Size Location Table.pdf PDF
36C24222Q0571_1.docx DOCX document
WD 2015-4187 Rev. 22.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NYC-DEP Form for Report on Test and Maintenance of Containment Backflow Prevention Assembly Bureau of Water and Sewer Operations

Initial Test Complete entire form Please use a separate form for each assembly

Part A- TO BE COMPLETED IN ALL CASES Annual Test – For the Year ______. Complete Parts A & B Only

Public Water Supply: NYC-DEP County: Block: Lot: Department Use Only

Name & Address of Facility: Make & Model # of Assembly

___________________________________________ Size & Serial # of Assembly

Location (Floor) of Assembly:

Part B- TO BE COMPLETED BY NYS CERTIFIED BACKFLOW PREVENTION ASSEMBLY TESTER

Procedure Check Valve No. 1 Check Valve No. 2 Differential Pressure

Relief Valve (RPZ only) Line Pressure ______ psi

Test Before Repair

Pressure drop across first check valve, psi ______ Leak ( )

Closed tight ( ) Opened at ______ psi Date: ______/______/______

Leak ( ) Closed tight ( )

Describe repairs, parts and materials used.

Name of Repairer:

Name, Lic. # & Seal of Master Plumber.

Date of Repair: _____/_____/_____

Final test

Pressure drop across first check valve, psi ______ Closed tight ( ) Opened at ______ psi Date: ______/______/______

Closed tight ( )

Water Meter Number: Meter Reading: Completion Time of Test (e.g. 3:15 pm):

Type of Water Service/System (Please Check One):

( ) Domestic ( ) Fire ( ) Combined ( ) IWM

Question 1: Are there any connections between the point of entry and the backflow prevention assembly, or other deficiencies? NO ( ) YES ( ) *If YES, please explain in detail in the space provided or on an additional paper.

CERTIFICATION: This assembly meets the requirements of an acceptable containment assembly at time of testing.

I hereby certify the foregoing data to be correct.

Signature Date

CERTIFICATION: This assembly does NOT meet the requirements.

Signature Date

PRINT NAME Telephone No. Certified Tester No. Expiration Date

Part C- TO BE COMPLETED BY NYS PE OR RA Part D – TO BE COMPLETED BY NYC LICENSED MASTER PLUMBER

Professional Engineer’s or Registered Architect’s Certification:

I have personally checked this installation and I certify that it is in accordance with the approved plans.

NYC-DEP Backflow Prevention Assembly Approval #:

[ ] I am the Designer of Record. [ ] I am NOT the Designer of Record.

PE/RA Printed Name: ___________________________________________

Company: ___________________________________________

Address: ___________________________________________

Telephone #: ___________________________________________

Signature, Seal & Date:

Master Plumber’s Certification: [ ] I am [ ] I am NOT the Licensed

Master Plumber of Record. I have personally checked this installation and I certify that it is in accordance with the Building Department’s Requirements.

Building Department Number:

(Use Sticker)

Plumber’s Printed Name: ______________________________________

Plumber’s License #: ______________________________________

Telephone #: ______________________________________

Minor Installation Changes (describe): (Attach additional sheets if required) Signature, Seal and Date:

NOTE: Send one completed form, within 30 days of installation and initial testing, with original ink signatures and original ink or impressed seals to

NYC-DEP-BWSO, Cross-Connection Control Unit, 59-17 Junction Blvd., 3rd Fl. Low-Rise, Flushing, NY 11373 NYC - GEN215B Rev 1/2019

INSTRUCTION FOR COMPLETION OF

“Report on Test and Maintenance of Containment Backflow Prevention Assembly”

(FORM GEN215B)

Use a separate form for each particular assembly

Indicate Initial Test or Annual Test by checking the appropriate choice.

Initial Test and Certification: Complete all 4 parts.

Annual Test/Re-Certification: Complete parts A and B only

Please follow these tips to have the form completed:

Part A: To be completed in ALL cases for the current address, block and lot #s, the tested BFP assembly (make, model # in full, size and serial #) and actual location of the tested assembly (floor/level, vault, hot box) along with a specific location (meter/boiler/pump room, store, garage, etc.), if any.

Part B: NYS Certified Backflow Prevention Assembly Tester shall fill out this portion in ALL cases:

Include the line pressure (taken at number 1 test cock with shutoff valve number 1 closed).

Include the pressure drop across the first check valve (the pressure differential between the second and the third test cocks).

Include the condition of check valves # 1 and 2.

Describe repairs, parts and materials used, replacement of assembly and details of procedures. If any, complete final test.

Indicate the water meter # (8 digits) and reading.

Completion time of test refers to the time of day (e.g. 8:00 am) and test date.

Check actual type of the water service/system (Internal Water Main “IWM”).

Be sure to answer (check) Question 1. If the answer is “YES”, explain in the space provided. A connection for a properly installed and certified parallel assembly should not be construed as a connection. Hose cocks and spigots shall be considered as connections. Tees/ells shall be removed completely and hard pipe. Cross-connections upstream of the assemblies are prohibited except otherwise allowed and approved for the parallel assemblies’ installations.

Then, clearly print, type or rubber stamp: Date, Name, Phone #, Certified Tester # and Certified Tester Expiration Date.

Part C: Complete for Initial Test Report only!

The NYS Licensed Professional Engineer or Registered Architect (PE/RA) shall complete Part C. Be sure to fill in the following:

The “NYC-DEP Backflow Prevention Assembly Approval #”.

Indicate whether being the designer of record or not.

Indicate minor changes, if any. Use back or additional pages as required. Indicate “See Back” or “See Additional Pages” as appropriate. If an equivalent make and model # of assembly is used, the PE or RA shall certify that the submission is acceptable and will not cause any adverse hydraulic effects on the water system. Also satisfy the submersion calculations (for RPZ/RPD assemblies only, if installed below grade level).

If the installation changes meet DEP requirements while deviating from the approved plans, the job shall be resubmitted for re-approval or an as-built plans shall be submitted to legalize the on-site condition/discrepancy.

When the installation deviates from the approved plans and minimum requirements are not satisfied, the job should NOT be certified.

Part D: NYC Licensed Master Plumber shall complete Part D. Be sure to fill in the following:

Indicate whether being the Licensed Master Plumber of record or not

The Department of Buildings Number (ARA #, ALT #, NB #, LAA #, etc.). Use of sticker is preferred.

Licensed Master Plumber’s Name.

Licensed Master Plumber’s License #.

Licensed Master Plumber’s Telephone Number.

Original Ink Signature, raised impression Seal of Licensed Master Plumber & Date.

Notes: The PE/ RA, Licensed Master Plumber & Certified Tester shall sign the same form for each particular assembly.

For each completed form, USE ORIGINAL INK SIGNATURES & ORIGINAL INK OR RAISED IMPRESSION SEALS.

Mail one completed form to: NYC- DEP-BWSO

Cross-Connection Control Unit

59-17 Junction Boulevard, 3rd Fl.

Low-Rise, Flushing, NY 11373-5108

Refer to “NEW YORK CITY CROSS-CONNECTION CONTROL PROGRAM HANDBOOK”, latest version on DEP web site.

NYC - GEN215B Rev. 1/2019 | DCN: BWSO-FRM-1-2019

Initial Test:
Annual Test For the Year:
County:
Block:
Lot:
Name Address of Facility 1:
Name Address of Facility 2:
Name Address of Facility 3:
Make Model of AssemblyName Address of Facility:
Size Serial of AssemblyName Address of Facility:
Size Serial of AssemblyName Address of Facility_2:
Location Floor of Assembly:
Line Pressure:
check valve psi:
Opened at:
Date:
undefined_2:
undefined_3:
Opened at psiDescribe repairs parts and materials used:
Date of Repair:
undefined_4:
undefined_5:
check valve psi_2:
Opened at_2:
Date_2:
undefined_6:
undefined_7:
Water Meter Number:
Meter Reading:
Type of Water ServiceSystem Please Check One:
I hereby certify the foregoing data to be correct:
undefined_8:
undefined_9:
undefined_10:
undefined_11:
undefined_12:
PRINT NAME:
undefined_13:
undefined_14:
undefined_15:
undefined_16:
undefined_17:
Certified Tester No:
Expiration Date:
NYCDEP Backflow Prevention:
that it is in accordance with the Building Departments Requirements:
PERA Printed Name 1:
PERA Printed Name 2:
PERA Printed Name 3:
PERA Printed Name 4:
Plumbers Printed Name 1:
Plumbers Printed Name 2:
Plumbers Printed Name 3:
Annual Test:
Leak for valve 1:
Close tight for valve 2:
Close tight for valve 1:
Close tight at final test-valve2:
Close tight at final test-valve 1:
Name of Repairer:
Leak for valve 2:
Combined:
IWM:
I am:
I am NOT:
I am the Designer of Record:
Fire:
I am NOT the Designer of Record:
NO:
Domestic:
YES:
Minor Installation Changes describe Attach additional sheets if required:
Please Explian: