NSSL Phase 3 Industry Day Briefing - for SAM.gov.pdf

PDF 13 MB Posted

Attached to
National Security Space Launch (NSSL) Phase 3 DRAFT Request for Proposals (RFPs) #1 and Industry Day Federal contract opportunity
Solicitation number
NSSL-Ph3-dRFP1
Issued by
Department of the Air Force

View the file

Other files for this federal contract opportunity

Other files attached to National Security Space Launch (NSSL) Phase 3 DRAFT Request for Proposals (RFPs) #1 and Industry Day, newest first.
File Type Posted
DRAFT Ph3Ln2 RFP1 - 2 Mar 2023 for SAM.gov.zip ZIP file
DRAFT Ph3Ln1 RFP1 - 2 Mar 2023 for SAM.gov.zip ZIP file
DRAFT Ph3Ln1 RFP1 - 2 Mar 2023 for SAM.gov.zip ZIP file
DRAFT Ph3Ln2 RFP1 - 2 Mar 2023 for SAM.gov.zip ZIP file
Atch 1 - NSSL Ph3 Industry Day Participant Request Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NSSL Phase 3 Industry Day

DISTRIBUTION STATEMENT A: Approved for public release. Distribution is unlimited.

DESTRUCTION: Comply with distribution statement and destroy by any method that will prevent disclosure of contents or reconstruction of the document.

28 February 2023

20230228 – NSSL Ph 3 Industry Day Briefing final v6.1

Industry Day Agenda

Day 1 Time Topic Speaker Duration

0730 Arrival / Check-In 30 min

0800 Intro / Admin Details Lt. Col. Nicholas Longo 5 min

0805 Rules of Engagement Ms. Kirsten Prechtl 10 min

0815 AATS Overview Maj. Gen. Stephen Purdy 15 min

0830 NSSL Overview Col. Douglas Pentecost 15 min

0845 Phase 3 Procurement Strategy Lt. Col. Nicholas Longo 30 min

0915 Phase 3 Lane 1 dRFP Lt. Col. Nicholas Longo 30 min

0945 Tiered Mission Assurance Lt. Col. Tae Kim 20 min

1005 Break 15 min

1020 Phase 3 Lane 2 dRFP Lt. Col. Nicholas Longo 15 min

1035 NSSL Requirements & Document Changes Lt. Col. Tae Kim 15 min

1050 Systems Engineering Data Maj. Will Deavor 15 min

1105 Spaceport of the Future Mr. Mark Bontrager 15 min

1120 Q&A / Closing Remarks Lt. Col. Nicholas Longo 30 min

1150 Break for Lunch

3Semper Supra

Industry Day Agenda (Cont’d)

Day 1 Time Topic Speaker Duration

1150 Break for Lunch

1300-1600 One-on-One Discussions Phase 3 Team TBD

1300-1500 Systems Engineering Data Demo/

Unclassified Threat Brief Maj. Will Deavor/

SMSgt Ronald Lerch

TBD

1500-1700 Systems Engineering Data Demo/ Unclassified Threat Brief (Repeat)

Maj. Will Deavor/ SMSgt Ronald Lerch

TBD

Day 2 Time Topic Speaker Duration

TBD One-on-One Discussions Phase 3 Team TBD

4Semper Supra

Administrative Details

• Security

• Unclassified general briefing

• No recording of general or one-on-one sessions

• No photos

• Note-taking is permissible

• SSC will provide charts after Industry Day for all attendees

Semper Supra 5

Semper Supra

Administrative Details (cont’d)

Rules of Engagement Ms. Kirsten Prechtl

Contracting Officer kirsten.prechtl@spaceforce.mil

Disclaimer

• Information presented is for planning purposes only and subject to change

• Government is not seeking proposals at this time

• Does not constitute a promise to issue a solicitation in the future

• Does not commit the Government to contract for any supply or service

• Government will not pay for any information or administrative costs incurred in response to this event;

costs are solely at responding party’s expense

Semper Supra 8

Disclaimer (cont’d)

• Participation in this industry day and one‐on‐one discussions constitutes consent to disclosure of information to companies contracted with Space Systems Command/Assured Access to Space (SSC/AA) to provide program office support

• The above companies are required to provide equal protection to non‐ public information as the Government

Semper Supra 9

• The Aerospace Corporation

• Alpha Omega Group (AOG)

• Axient

• Boecore, Inc

• Boyles Enterprises

• Figueroa and Associates

• Integrated Data Services (IDS)

• KBR (formerly Centauri)

• Liona Enterprises Inc.

• ManTech International Corporation

• Millennium

• Nynth Company California LLC

• OMNI Consulting Solutions

• Quantum Research International

• Science Applications International Corporation (SAIC)

• SAVI LLC

• Stellar Solutions

• Tecolote Research Incorporated

• Wallender and Associates

Questions / Comments

• When asking a question or providing comments, please state:

• Name

• Company

• Government accepting written questions or comments on the comment form provided (mark if proprietary)

• Comment forms with proprietary information must be clearly labeled

• Information marked proprietary will be handled accordingly and safeguarded in accordance with applicable Government regulations

• Government shall not be liable in any way for proprietary information that is not properly identified

• Government may review the validity of proprietary markings

• Proprietary questions will be addressed during one-on-one sessions or provided via email to the company POCs

• Non-proprietary questions /comments & Government responses during one-on-ones and the general session may be posted on the Bidder’s Library at the Government’s discretion

Semper Supra 10

Semper Supra 11

Role Name Email

Contracting Officer Kirsten Prechtl kirsten.prechtl@spaceforce.mil

Contract Specialist Lane 1 Tyler Davis tyler.davis.39@spaceforce.mil

Contract Specialist Lane 2 Capt. Bryan Smith bryan.smith.75@spaceforce.mil

Role Name

Program Manager Col. Douglas Pentecost

Senior Materiel Leader Col. Chad Melone

Materiel Leader Lt. Col. Nicholas Longo

NSSL Phase 3 Leadership

NSSL Phase 3 dRFP Contracting Team

Please include all Contracting Members in emails regarding dRFP related topics

Role Name Email

Technical Lead Lane 1 Jonathan Hernandez jonathan.hernandez.20@spaceforce.mil

Technical Lead Lane 1 Capt. Charles Guertler charles.guertler@spaceforce.mil

Technical Lead Lane 2 Gregory Pierson gregory.pierson@spaceforce.mil

Technical Lead Lane 2 Capt. Foster Davis foster.davis@spaceforce.mil

Range POC Scott Chappie scott.chappie@spaceforce.mil

NSSL Phase 3 dRFP Technical Team

Points of Contact

Purpose

• Provide Phase 3 Dual‐Lane Acquisition Strategy Overview and draft Request for Proposals (RFP) Overview

• Solicit and gather industry dRFP feedback and recommendations as well perspective on areas of interest

Semper Supra 12

Encourage open discussion regarding draft RFP approach

Assured Access to Space (AATS) Overview Maj. Gen. Stephen Purdy

Program Executive Officer

SPACE ACCESS

ORBITAL RESILIENCY

Mission Lifecycle Management

Sub‐Orbital Rapid Strategic Mobility

Rocket Cargo AFRL Vanguard Program;

Point‐to‐Point Rapid Global Mobility

RAPID DELIVERY

On‐Orbit Servicing, Maneuver, & Debris Removal Next‐Gen Range

Services & Mission Assurance

Operate Vandenberg SFB, Patrick SFB, Cape Canaveral SFS, Eastern and Western Ranges

SV Processing Management;

Building Capacity

Commercial Range Ops &

Business Models

AATS‐Level Ops Centers for Monitoring Hardware Movements and Assets

National Federation of Spaceports USG and State Spaceports

Collaborations

New Effort Currently Executing

Multi‐Use Range Facilities;

Complex Allocation

LTRS ‐ Range Sustainment;

Materiel and Services

Procurements;

NSSL, RSLP;

Multi‐Mission Manifesting

AATS Inherent Activities

2 USSF RANGES 2 ARMED SERVICES

3 TRACKING SITES 9 LOCATIONS

100+ MISSION PARTNERS 10K PERSONNEL

TacRS Provide responsive warfighter space capabilities on demand to maintain space superiority through all phases of conflict

Tactically Responsive Space

Pillar PointVSFB

LAAFB

OO‐ALC HAFB

Wake Atoll Kodiak PMRF

JBPHH

YPG

Camp Navajo

Fort Wingate

KAFB

WSMR

Centennial, CO

Decatur, AL

MDA

CCSFS PSFB

Ascension Island

San Juan, PR

Malabar

JDMTA

WFF

Operating Location AATS Personnel Assigned Tracking Site Storage Site Ancillary LocationAATS Controlled Locations

CAO 10 Aug 22

Assured Access to Space The Future of Assured Access to Space

Orbital Servicing Remove/Replace Payloads On‐Orbit;

Drive Common Standards;

Commercial Refueling Capability

Orbital Maneuver Leverage commercial industry for on‐orbit maneuvers;

Small‐launch to LEO, use on‐orbit stages to higher altitudes

Debris Removal Engage and Energize Industry Solutions

OPERATIONS INTEGRATION

Spaceports/Launch/Satellite Ops

AATS Policy, Requirements & Funding

SSC Spaceflight Worthiness & Certification

AATS Program Incubator

DoD Mission Manifesting

SSC/S3

AATS

AA3/5/

Enterprise Mission Assurance Team

COCOM Space Effect IntegratorOrbital/Sub‐Orbital Launches; Storage, Surveillance, and Refurbishment of Decommissioned ICBM Motors

UNCLASSIFIED

Supply Chain Risk Management

NSSL Overview Col. Douglas Pentecost

Program Manager, Space Systems Command/Assured Access to Space (SSC/AA)

100% Launch Success is Vital to Countering the Pacing Challenge

CAO 23 Jan 23

Launch Programs Key Enabler for the Space Domain

USSF launches the most critical National Security Space satellites

Falcon 9 (5 On Contract) Next: USSF-124

(17 Jul 23)

Delta IV Heavy (2 on Contract) Next: NROL-68

(28 Mar 23)

Falcon Heavy (1 On Contract) Next: USSF-52

(23 Jun 23)

Vulcan (8 On Contract) Next: USSF-106

(Nov 23)

Atlas V (2 On Contract)

Next: Silent Barker (21 Jul 23)

Nation’s Eyes & Ears

Positioning, Navigation & Timing

Secure Comms

Space Domain Awareness

Enables Resilient Space Order of Battle

>$82B in On-Orbit Capability

97 Successful NSSL Launches

Govt Mission Assurance = 100% Mission Success

Multi-Mission Manifesting

Launcher One Next: STP-28B

Late 2023

Minotaur Next: Mk21A-2

Late 2023 Ravn X

Next: ASLON-45

TBD

RS-1

Next: STP-AR1

Late 2023

23 of 25 Successful RSLP Launches since 2015

Alpha Next: TacRS-3

NET Apr 23

USSF Space Access Portfolio

Sounding Rocket Program – 4

Suborbital targets and experimental flights

- Unique/specialized msns

- IDIQ with 2 providers

- 9-18 month procurement

- 2018 through 2025

Small Rocket Program – Orbital LEO access through very small launch

- Compete every launch

- SBIR opportunities

- 9-18 month procurement

- 2019 through 2029

Orbital Services Program – 4

Small and medium launches to LEO

- Tailorable Msn Assurance

- 11 IDIQ providers

- 12-24 month procurement

- 2019 through 2028

National Security Space Launch

Highly reliable medium to heavy spacelift

- Phase 2: two providers

- 12-24 mo procurement

- 2020 through 2024

- Phase 3: 2025-TBD

Mission Manifest Office

- Coordinates all USSF missions and is single entry point for customers

- Utilizes excess launch vehicle performance to maximize on-orbit capability

- Demonstrated late-stage secondary payload swap as late as one month prior to launch

- MMO uses its Launch Enterprise; Launch Manifest Systems Integrator (LMSI) contract to integrate SVs onto auxiliary payload adapters

MDAPNon-MDAP Scope of Launch Enterprise Contracts

17Semper Supra

Trends Driving AATS

UNCLASSIFIED

UNCLASSIFIED

Multiple changes are driving the USSF from a Launch to a Logistics Model

18Semper Supra

NSSL Future Needs

• Transition to resilient space architecture

• Increase in higher energy missions

• More multi-manifested missions (dedicated / excess)

• Potential new orbits / mission areas

• Increase number and type of launch systems

• Increase number of and geographic dispersion of launch sites

• Operate through threats like weather, cyber, etc.

• Varied payload security requirements

• Ability to do traditional and rapid SV/LV integration

• Supporting anticipated launch tempo increase

• Harness innovative best practices

• No significant launch development RDT&E investment

Semper Supra 19

Mission Success!

Phase 3 Procurement Strategy Lt. Col. Nicholas Longo

Materiel Leader, Mission Procurement Branch

NSSL Phase 3 Lead

Long-term Program Schedule

22Semper Supra

EoQ: Economic Order Quantities IDIQ: Indefinite Delivery Indefinite Quantity LSP: Launch Service Provider

Phase 3 Dual-Lane Approach

Lane 2 Upfront Commitment

Lane 1 Rolling Competitions

Secures launch capacity/AATS

Provides consistent demand, gain EoQ

Addresses manifest flexibility

Ensures capability for hard missions

Dual Lane Advantages

Provides annual opportunities so systems in development can on-ramp when ready

Provide additional resiliency through new launch systems

• Operational Imperative: Launch must deliver national security space capability to the warfighter to deter/defeat current, emerging and future threats

• Approach to meet imperative: Provide assured access to space to the integrated space architecture at affordable prices

• Phase 3 Acquisition Strategy: Execute a dual-lane approach with two separate contract types to fulfill program requirements

Indefinite Delivery, Indefinite Quantity (IDIQ) contract to on-ramp new systems & emerging providers for missions that are more risk tolerant

Longer-term Indefinite Delivery, Requirements contracts - commitment to assure access to space for missions that cannot fail

Industry Perspective/Feedback

• Requesting Industry Feedback

• Lane 1 Tiered Mission Assurance Process

• Systems Engineering Data

• Launch acceleration (quantity for Lane 2)

• Timelines for Monte Carlo Orbital Parameter accuracy and mass to orbit

(MTO) analysis

• Integrated Master Schedule (IMS) format

• For Industry Information

• Range availability/agreements/leases

Semper Supra 24

Submit CRM with RFP Comments NLT 17 Mar 23 @ 1300PST

Lane 1

RFP

FY23 FY24 FY25

Industry Engagement

Release RFPs

Lane 1 Source Selection

On- Ramp

Lane 1 Annual

On-ramping Opportunities

Proposal Dev

Lane 2

RFP

Phase 2 Ordering

Period Ends

Proposal Dev

TO Source Selection

Lane 1 TO Award

Lane 1

TO RFP

Lane 1 Contract Awards

Lane 2 Source Selection

Lane 2 TO Award

Lane 1

RFP

Lane 2 Contract Awards

Today

Phase 3 Schedule

Proposal DevdRFPs #1 & 2 dRFPs #1 & 2

Industry Day

Industry Feedback on dRFPs

OY1 EISs

Proposals Received

Contract Award

Release RFP

Early Integration Studies (EIS) for First Ordering Year of Phase 3 Lane 2

• Early Integration Studies (EIS) is vital for first-time missions and/or new entrant launch vehicle configuration for first ordering year

• Risk reduction activity

• Informs Government on compatibility between launch vehicle (LV) and spacecraft

• Identifies space vehicle’s (SV’s) mission unique requirements

• Assesses LV’s ability to meet SV interfaces

• Offerors interested in conducting EIS for missions ordered in the first ordering year of Lane 2 must be:

• LSP with certified system; or

• LSP with approved certification plan for your proposed launch system

• If an Offeror is neither of these but is interested in conducting EIS

• LSP must submit a Statement of Intent (SOI) to initiate a certification plan for your proposed launch system

Please submit SOI for your proposed system by 1300 PDT on 9 March 2023

Phase 3 (dRFP) Lane 1 Overview Lt. Col. Nicholas Longo

Materiel Leader, Mission Procurement Branch

Phase 3 Dual Lane Approach Lane 1 Contract Parameters

Parameter Lane 1: ~27 Specified Missions Indefinite Delivery Indefinite Quantity Contracts

Contract Type Multi-award IDIQ contracts (Fixed Firm Price)

Order Period 5-yr Base + 5 yr Option (FY25-FY34)

PoP 13 years; covers launches FY27-37

# LSPs Multiple LSPs/Systems, Lane 2 awardees may compete/bid

Requirements Meet a subset of NSSL requirements

Certification None, LSPs must provide evidence demonstrating 1 successful launch in Task Order proposal

On-ramping Annual for new LSP/System

Ordering Procedures Annual task order competitions (individually or in-blocks), allows for non-standard (1 to 3-year) integration cycle

Launch Svc Support

(LSS)

None, pricing will be fully burdened; tiered Msn Assurance framework

Lane 1 1st Draft RFP (Released 16 Feb 23)

Model Contract (FA8811-23-R-0001)

Exhibit A Contract Data Requirements List (CDRL)

Attachment 1 Performance Work Statement (PWS)

Attachment 2 Ordering Guide

Attachment 3 Addendum to FAR 52.212-04, Contract T&Cs – Commercial Items

Attachment 4 Small Business Subcontracting Plan [cover page only]

Attachment 5 Small Business Participation Commitment Doc [cover page only]

Attachment 6 Government Property [cover page only]

Attachment 7 Organizational Conflicts of Interest (OCI) Plan [cover page only]

Attachment 8 Instructions to Offerors [solicitation only]

Attachment 9 Evaluation Criteria [solicitation only]

Lane 1 1st Draft RFP (Released 16 Feb 23)

Model Contract (FA8811-23-R-0001) (Cont’d) Model Launch System Readiness Study Task Order

Projected Manifest (non-public information; posted to Bidders Library only)

Compliance & Ref Docs (100+ including some non-public info; posted to Bidders Library)

Comment Resolution Matrices (CRMs)

Lane 1 CLIN Structure

CLIN Description Type

0002 Launch Service FFP

Launch Service Orders

Other Orders

CLIN Description Type

0001 Launch System Readiness Studies (Minimum Order) FFP

0003 Quick Reaction/Anomaly Resolution FFP

0004 Special Studies FFP

0005 Data And Reports NSP

Lane 1 dRFP Key Features

Basic Contract / On-Ramping

• Instructions of Offerors – Basic award and yearly on-ramping to receive min order and ability to compete for mission task orders

• Evaluation Criteria – Acceptable or Unacceptable

Min Order PWS – Launch System Readiness Study: Initial Risk Assessment, Technical Insight, Targeted EIS

Launch Service Task Order Level

• Ordering Guide – Contains task order level ITO; 1 successful flight;

Full NRDV not required; EC similar to Lane 2 (tailored to each msn)

• PWS – Tiered Mission Assurance approach, Commercial Rideshare, Systems Engineering, Fully burdened (No LSS), Tailored mission requirements

• Small Business Participation Plan – Maintain 4% of contract award

• CDRL’s – Tailored to msn; added CDRLs for Min Order and Tiered MA

IDIQ Base Contract Evaluation Criteria

IDIQ Task Order Evaluation Criteria

Lane 1 IDIQ Base & Task Order Criteria

Lane 1 TOs Could Utilize Several Options from Full Trade-off to LPTA

Lane 1 Tiered Mission Assurance Lt. Col. Tae Kim Systems and Logistics Branch Chief, AAE

Lane 1 IDIQ MA Glance

Semper Supra 35

IDIQ On-Ramp Eligibility

Domestic LSP

Lift 20klbs to LEO

Plan to 1st Launch Within 12 months

Plan for AS9100

CTR MA Plan for Targeted Lane 1

Tiers

IDIQ Minimum Order

Tailored NRDV Plan Development

Initial Tech, Schedule, & Risk

Assessments

Targeted EIS

Technical Insight

LSTO Bid Eligibility

1 Successful Flight

Meet Mission Requirements

Risk / Schedule Assessment

Complete AS9100 Audit w/ Plan to

Completion

Execute LSTO Mission Award

Tier 0 No MA

Tier 1 Minimal MA

Tier 2 Some MA

Tier 3 Moderate MA

Lane 1 IDIQ

LSP Tiered MA Plans

Tailored NRDV Plan Execution

Lane 1 Minimum Order Scope

• Technical Insight (e.g., vehicle design, test data, command media) provides support to USG’s monitoring of launch services (§ 5.3)

• Deliver Mission Assurance Plan to support mission specific assessments according to Tiered Mission Assurance framework (§ 5.4)

• Targeted Early Integration Studies to gain knowledge of LSP’s mission integration and launch execution activities (§ 5.5)

• LSP conducts Process and Launch System Design Review in support of USG’s initial technical, schedule, and risk assessments (§ 5.6 & 5.7)

• Tailored IDIQ NRDV plan development based on USG assessments (§ 5.8)

• Deliver data product list to support NRDV plan (§ 5.9)

Semper Supra

Launch System Readiness Study Provides Lane 1 LSPs, LVs, and CONOPS Capability Assessment to USG

Lane 1 LSTO Tiered MA Framework

Semper Supra 37

NSSL Phase 3 Lane 1 Tiered MA Framework to Tailor MA Efforts in PWS Appendix I (LSTO)

Tier 0

MA

Consistent w/ Commercial

Missions

(FAA

Licensing

Reqs)

Tier 1 Deviations from Engines and

Motors Qual Baseline

Deviations to MA Reqs Allowed w/ Risk Assessment

High risks must be mitigated to Medium

Review Top NCs;

QTP/ATP/NCs for Mission

Unique and FFI

Very Small DOL Ops Team w/o Gov MD

Tier 2 Deviations from Propulsion, Separation, Fairing, and Tank Systems Qual Baseline

Deviations to MA Reqs Allowed w/ Risk Assessment

Medium+ risks must be mitigated to Low-Medium

Review Top NCs; ATP/NCs for Flight Critical HW (1st Flt), then will reduce

Small DOL Ops Team w/ Gov

MD

Tier 3 Deviations from Flight

Critical Items Qual Baseline

Deviations to MA Reqs Allowed w/ Risk Assessment

Medium+ risks must be mitigated to Low-Medium

Review Top NCs; ATP/NCs for Flight Critical HW

Full DOL Ops Team

“Minimal” Space Flight Worthiness Certification

“Some” Space Flight Worthiness Certification

“Moderate” Space Flight Worthiness Certification

Lane 1 LSTO MA Framework Example

38Semper Supra

Full MA Scope

Hardware Reviews; Flight Mechanics, Guidance and

Navigation; Flight Controls, Dynamics and Loads;

Thermal, Fluids, and

Contamination; Software;

DOL Software Load

Verification; DOL; DOL Placards; DOL Winds Analysis;

Structures; Orbital Debris Mitigation Data; Booster

Propulsion Analysis; Upper Stage Propulsion Analysis;

Solid Rocket Booster; Rocket Engine(s); Avionics; Ground Software Baseline; Ground Support Equipment; and Launch Site Operations …

Tailored based on Tiered MA Framework

Tier 1 MA Hardware Reviews of Engines and Motors; …

Tier 2 MA Hardware Reviews of

Propulsion, Separation, Fairing, and Tank Systems;

Guidance and Navigation;

Dynamics and Loads; …

Tier 3 MA Hardware Reviews of Flight Critical Items; Mostly Review of Contractor Documentation; Targeted IV&V; …

Tier 0 MA

Break (15 min)

Day 1 Time Topic Speaker Duration

0730 Arrival / Check-In 30 min

0800 Intro / Admin Details Lt. Col. Nicholas Longo 5 min

0805 Rules of Engagement Ms. Kirsten Prechtl 10 min

0815 AATS Overview Maj. Gen. Stephen Purdy 15 min

0830 NSSL Overview Col. Douglas Pentecost 15 min

0845 Phase 3 Procurement Strategy Lt. Col. Nicholas Longo 30 min

0915 Phase 3 Lane 1 dRFP Lt. Col. Nicholas Longo 30 min

0945 Tiered Mission Assurance Lt. Col. Tae Kim 20 min

1005 Break 15 min

1020 Phase 3 Lane 2 dRFP Lt. Col. Nicholas Longo 15 min

1035 NSSL Requirements & Document Changes Lt. Col. Tae Kim 15 min

1050 Systems Engineering Data Maj. Will Deavor 15 min

1105 Spaceport of the Future Mr. Mark Bontrager 15 min

1120 Q&A / Closing Remarks Lt. Col. Nicholas Longo 30 min

Phase 3 dRFP Lane 2 Overview Lt. Col. Nicholas Longo

Materiel Leader, Mission Procurement Branch

Phase 3 Dual Lane Approach Lane 2 Contract Parameters

Lane 2 1st Draft RFP (Released 16 Feb 23)

Model Contract (FA8811-23-R-0002)

Exhibit A Contract Data Requirements List (CDRL)

Attachment 1 Performance Work Statement (PWS)

Attachment 2A DD 254 Contract Security Classification Specification

Attachment 2B DD 254 SCI Addendum (non-public info; posted to Bidders Library)

Attachment 2C DD 254 SAP Addendum (non-public info; posted to Bidders Library)

Attachment 3 Small Business Subcontracting Plan [cover page only]

Attachment 4 Small Business Participation Commitment Doc [cover page only]

Attachment 5 Acceptance Criteria

Attachment 6 Government Property [cover page only]

Attachment 7 Pricing Tables

Attachment 8 Payment Plan

Model Contract (FA8811-23-R-0002) (Cont’d)

Attachment 9 Cumulative Mission Success Incentive Plan

Attachment 10 Award Fee Plan

Attachment 11 Addendum to FAR 52.212-04 Contract T&Cs –Commercial Items

Attachment 12 NRO DD 254

Attachment 13 NRO Requirements Descriptions and CDRL

Attachment 14 Organizational Conflicts of Interest (OCI) Plan [cover page only]

Attachment 15 Instructions to Offerors [solicitation only]

Attachment 16 Evaluation Criteria [solicitation only]

Projected Manifest (non-public information; posted to Bidders Library only)

Compliance & Ref Docs (100+ including some non-public info; posted to Bidders Lib)

Comment Resolution Matrices (CRMs)

Lane 2 1st Draft RFP (Released 16 Feb 23)

Lane 2 CLIN Structure

CLIN Description Type

0001 Launch Service FFP

0003 Mission Unique Services – Procurement (if necessary) FFP

0004 Mission Unique Services – R&D (if necessary) FFP

0005 Mission Acceleration FFP

Launch Service Orders

Other Orders CLIN Description Type 0002 Launch Service Support (Annual) FFP 0006 Quick Reaction/Anomaly Resolution/Special Studies FFP 0007 Early Integration Studies/Special Studies FFP 0008 Data and Reports NSP 0009 Cumulative Mission Success Incentive FFP 0010 Award Fee Incentive FFP

Lane 2 dRFP Key Features

• CDRL’s - New CDRL for Business Management Review

• PWS - Systems Engineering Data, Enhanced Classified Operation Support and security requirements, Revised EIS categories, Multi-manifest enhancements, Fleet Surveillance revision

• Instructions of Offerors - Proposal must meet Minimum Gate, Approved Launch System Certification Plan required

• Evaluation Criteria - Increased fidelity in Past Performance use of confidence assessment rating

• Small Business Participation Plan – Maintain 4% of contract award

• Award Fee - $20 M per year for each Launch Provider; Performance based

• Cumulative Mission Success Incentive (CMSI) - $10M / per successful mission paid after 1st 3 successful missions then after every 5 missions thereafter

To increase competition, flight will not be required as a gate to advance in proposal evaluation When Combined Factors 1 thru 3 are significantly more important than Factor 4 Price

Best value tradeoff where technical is more important than price

Lane 2 IDR Base Evaluation Criteria

NSSL Lane 2 Requirements & Document Changes Lt. Col. Tae Kim Systems and Logistics Branch Chief, AAE

NSSL Requirements

Semper Supra 48

NSSL Requirements: System Performance Requirements Document (SPRD), Standard Interface Specification (SIS); Other Specs, Standards, Compliance items ….

Examples of Key NSSL Requirements:

• Mass to Orbit

• Orbital Insertion Accuracy

• Overflight

• GPS Key handling – “Zeroizing”

• Full ODMSP Compliance

• Vertical Integration

• Eastern & Western Ranges

• 5-m diameter Fairing (min)

• 62-in, 103-inch, and 173-in

Payload Interfaces

• Autonomous Flight Safety Sys

• Secure GPS / M-code

• End-to-end USSF Mission

Assurance Support: Data, Fleet Surveillance, & Risk Mitigation

NSSL Primary Payload Mass-to-Orbit Reference Orbits (SPRD Rev C, 2023)

Reference Orbit

Apogee Altitude (nmi)

Perigee Altitude (nmi)

Inclination (deg)

Mass‐to‐ Orbit (lbm)

Semimajor Axis (nmi) Eccentricity

LEO NS NS 63.40 15,000 3,944 0

Polar 1 NS NS 98.20 15,500 3,894 0 Polar 2 NS NS 98.20 37,500 3,894 0 MEO Direct NS NS 50.0 20,000 13,259 0

MEO Transfer 10,998 540.0 55.00 9,000 NS NS

GTO 19,323 100 27.00 18,000 NS NS

Molniya 21,150 650 63.4 11,500 NS NS

GEO 1 NS NS 0.0 5,000 22,767 0

GEO 2 NS NS 0.0 14,500 22,767 0

MEO Direct 2 NS NS 55.0 6,450 14,442 0

GEO 1.5 NS NS 0.0 8,000 22,767 0

Retrograde NS NS 120 15,000 7,444 0

Revisions

Noteworthy Updates in SPRD Revision C

Semper Supra 49

• Updated Mass to Orbit Reference Orbits and Orbital Parameter Accuracy limits based on recent SV mission survey

• Updated Overflight requirement to focus more on minimizing unintended disclosure of critical technology

• Updated Orbital Debris, Range Safety, Protected GPS, Disposals, and Cyber Security requirements

• Removed Category A Payload Envelope

• Added 103-inch (2624mm) diameter payload interface as standard service

• Added Payload Fairing Internal Pressure limits for venting and mitigating risks

• Added LV-to-Payload Shock levels for

LSP-provided separation systems

• Added tabular data for graphical data

• Updated routine access, SV mass properties, ground ops, electrical interfaces, environments, mission design, LV commands, RF attenuation, and MSE accommodations requirements

Noteworthy Updates in SIS Revision D

NSSL New Entrant (NE) Process Overview (Lane 2 Requirement)

Semper Supra 51

NSSL Program Manager Approval NECT Assessment / NE Feedback

CRADA = Cooperative Research and Development Agreement NECT = New Entrant Certification Team NRDV = Non-Recurring Design Validation SIS = Standard Interface Specification

NE meets Entry

Rqmts AND is Viable?

Yes Begin NRDV*/ Certification via CRADA

Entry Requirements: Proposed System Must

• Lift payload mass of 20,000 lbs to LEO of 100 nm altitude with 28.5 degrees inclination

• Meet 97.5% mission reliability **

• Provide 3-sigma orbit insertion accuracy **

• Meet interface requirements in SIS **

• Be a U.S. launch system and company

New Entrant Viability

• One or more launches of proposed launch system, or

• Previous experience as Launch Service Provider, or

• Established manufacturer of space launch propulsion systems

NECT

Interacts with NE

NE Contacts NSSL Program for NE Process

Info

NE Submits Statement of Intent

* NRDV includes meeting all NSSL requirements ** These are consistent with the SPRD rev C (2023) and SIS rev D (2023)

Note: See New Entrant Certification Guide (NECG) for details on Certification Process

NSSL Flight Worthiness Process

Semper Supra 52

New Entrant Certification occurs any time during NRDV

Space Flight Worthiness Cert of a single mission occurs just before launch

Non-Recurring Design Validation

(NRDV)

Qualify the Design (Margins & Reliability)

Qualify the Processes (Ability to Produce the Hardware Design)

Verify that Test Hardware Meets Qualification

Evaluate Build of Flight Hardware in Accordance with Qualified Design & Processes

Mission Specific

Verification

Mitigate All Issues to an Acceptable Risk Level for Flight

NRDV is Foundation of Mission Specific Verification & Flight Worthiness Certification

Systems Engineering Data Maj. Will Deavor Digital Innovation Chief, AAE

Digital Modernization Imperative

Semper Supra 54

The New Digital Acquisition Reality

(2020)

DoD Data Strategy (2020)

DoD Digital Engineering

Strategy (2018)

USSF Vision for a Digital Service

(2021)

DoD Digital Modernization Strategy (2019)

The USSF will become the world’s first fully Digital Service. We will be an interconnected, innovative, digitally dominant force.

– Gen Raymond, USSF Vision for a Digital Service (2021)

This Vision of a Digital Space Force is defined as: an interconnected, innovative, digitally dominant force

– USSF Vision for a Digital Service (2021)

DoD’s approach is to securely and safely connect people, processes, data, and capabilities across an end-to-end digital enterprise

– DoD Digital Engineering Strategy (2018)

[Digital Modernization] will enable increased lethality for the Joint warfighter, empower new partnerships that will drive mission success, and implement new reforms enacted to improve capabilities across the information enterprise.

– DoD Digital Modernization Strategy (2019)

AATS Digital Vision

Semper Supra 55

• AATS is establishing a Gov-owned secure digital ecosystem to modernize and streamline mission process and realize USSF vision for digital service

• AATS Digital Ecosystem will enable:

• Development of operational tools for high tempo Phase 3 execution

• Cross-organizational integration under one system and link current “silos of excellence”

• Information transfer with external parties

• Automation, streamlined processes, and rapid data driven decisions…

• ADE provides IL5 level security to handle CUI and proprietary data near-term and higher impact levels in future

AATS Digital Ecosystem (ADE)

AATS

Gov

Gov CTRs

FFRDCs Launch Service

Providers

SV

Partners

Msn Partners

AATS Gov ‐ Ecosystem owner and operator ManTech – System Admin/Infrastructure Architect Aerospace – System Admin/Tool Architect

New Systems Engineering Data Requirements

Systems Engineering Data to review qualification data in machine readable format

Data Analytics to perform focused MA tasks and analyze big dataDigital Twin to digitally exercise flight software and associated hardware Digital Mission

Milestone Reviews to review requirements verification in electronic dashboards

Digital Supply Chain Transparency to support capabilities in MA, risk assessments, and flight worthiness

Streamlined Cross-Platform Collaboration Across Industry Partners

Spaceport of the Future (SOTF) Mr. Mark Bontrager

Technical Director, SSC/S3

Spaceport Of The Future (SOTF) Overview

58UNCLASSIFIED

UNCLASSIFIED

Vision: “Preserve and advance national security interests through globally competitive Ranges with capacity to support launch and test operations on demand.”

- Gen. John “Jay” Raymond, USSF ROTF 2028 Strategic Intent

• Priority 1: Evolve Eastern and Western Range capabilities to support all phases of launch and test operations for multiple users simultaneously.

• Priority 2: Deliver streamlined, equitable access to Range resources while creating and improving upon public services and infrastructure at both the Eastern and Western Range.

• Priority 3: Transform Range Business Model to be agile and responsive to Commercial Space Industry while preserving DoD test capabilities.

• Priority 4: Evolve and integrate U.S. Space Force Ranges into national space transportation and commerce system.

The Time Is Now!

*Image from Google Image Search

SOTF Lines of Effort/Focus Areas

– Implement comm upgrades

– Provision PaaS & IaaS via RSHP

– Plug-and-play based on use cases

– Transition to DevSecOps delivery

Architecture

– Installation Planning and Roadmaps

– Vehicle and Spacecraft Processing

– Multi-user / maximize launch pads

Infrastructure

– LISC Follow-on

– Consistent ER/WR Processes

– Streamline Governance/Bureaucracy

Operations / Business Model

– AFSS Transition

– Legislative Proposal

– Policy changes (FMR, DoDI, etc.)

Policy / MRTFB

– Interagency Planning Group

– Management Structures

Spaceports

Operate as a Single, Innovative Enterprise & Address Unique Customer Needs

LTRS R&PC

SLD 30/45

SLD 30/45

SSC/S3

SSC/S3

Preserve and advance National Security interests by building globally competitive Ranges with capacity to support launch and test operations on demand

SOTF

Policy/MRTFB

Senior Steering Group

– DS3, SLD CV-Os, Sr Aerospace Advisor

– Monthly meetings, in-person quarterly, decisive vectors for ROTF IPTs, projects and emergent needs

UNCLASSIFIED

UNCLASSIFIED

SOTF Lines of Effort Architecture

• Modernized IP-based networks

• Enables modernized capabilities at the edge

• Enhanced data transport

• Removes critical obsolescence risk

• Modernized equipment at the edge

• Upgraded telemetry antennas for simultaneous pad coverage

• Improved weather sensor systems

• Enhanced tracking radar signal processing

• Range Services Hosting Platform (RSHP)

• Cyber hardened on-premise IT infrastructure

• Enables capability for data exchanges between ER & WR

• Steppingstone to hybrid cloud and data strategy

• Migrating capabilities to hybrid cloud for speed of delivery & break apart monolithic systems

UNCLASSIFIED

UNCLASSIFIED 60

SOTF Lines of Effort Infrastructure

• Infrastructure improvements -- mutually beneficial to government & industry

• Increased launch & landing locations

• Launch Pad Allocation Strategy / Multi-user sites

• Expand land development

• Increased capacity for SV processing facilities

• Power grid/water treatment/road upgrades

• Water transport: dock/harbor development and improvements

• Infrastructure funding:

• Combined ER/WR infrastructure project list FY24-28 → $1.268B

• Provided to OMB and SAC-D, per their request

• Both ranges partnering with state and local authorities

• Mutually beneficial investment opportunities

• Space Florida

• California GoBiz/Reach

UNCLASSIFIED

UNCLASSIFIED

AATS is positioning to Leverage Commercial Space-Lift Market Boom

• ER/WR transitioning from manual Flight Termination System (FTS) to AFSS

• Govt. standard identified (RCC 319); industry develops compliant systems

• Range Safety and FAA certify commercial systems

• 1 Oct 2025 implementation deadline set by CSO (Gen Raymond)

• AFSS is a key enabler for spaceport operations

• Increased throughput; allows parallel pre-launch, launch and test operations

• Reduces launch-on-time risk and increases flight-paths

• Provides significant cost savings to range and range users

• ~50% saving for commercial providers on an AFSS Range

• Allows divestment of range critical systems and manpower

• SSC/S3 monitoring launch service provider (LSP) progress

• Industry developing variety of vehicle specific and commercially available systems

• Current & projected ER/WR LSPs on track to meet mandate; NASA SLS currently at risk

AFSS key to increased range capacity/cadence

UNCLASSIFIED

UNCLASSIFIED

SOTF Lines of Effort - Policy Automated Flight Safety System (AFSS)

Global Spaceport Transition

DoD Range Model Port Model

Port Model Evaluation

• Targeted studies

• Aerospace assessment (Jan 2021)

• Arizona State University (Dec 2022)

• Phase 2 pending

• BCA underway to inform port model

• Working groups

• National Spaceport Interagency

Working Group

• Spaceport Directors Council

• Global Spaceport Alliance

• Commercial Spaceflight Federation

Infrastructure Planning

• Civil engineering assessments

• Infrastructure Development Plan

• Infrastructure Roadmap

• Conducting supply chain SWOT

• Optimizing property use

• Launch pad allocation strategy

Policy

• Legislative policy

• Phased approach

• Legislative Prop. (409) in interagency coord.

• Developing FY25 legislative proposal

• Spaceport Governance

• Informed by trade studies & working groups

Funding

• ROTF infrastructure funding

• Submitted prioritized funding requirements at OMB request

• Charging Model Study

• Spaceport Funding; indirect cost allocation

• Analysis informs future policy proposals

Architecture Modernization

• Modernize/replace/divest legacy systems

• IP-based networks

• Equipment at the Edge

• Hybrid cloud migration

• Range Service Hosting platform

• Transition to Autonomous Flight Safety System

Infrastructure Execution

• Executing Infrastructure Master Plan

• Paced/prioritized for resource constraints

• Roads, bridges, power, commodities

• Defend the mission

• Identify/mitigate vulnerabilities

• Launch thru degradation

Infrastructure Planning

Infrastructure Execution

FundingPolicy

Architecture Modernization

Port Model

Space Launch Delta POCs

UNCLASSIFIED

UNCLASSIFIED

• SLD 30 Plans and Programs Office

• Mr. William Prenot: SLD30.XPWORKFLOW@us.af.mil

• SLD 45 Plans and Programs Office –

• Ms. Shaunna Lovell: 45SWXP@us.af.mil

Questions & Answers

Lunch Break

Day 1 Time Topic Speaker Duration

0730 Arrival / Check-In 30 min

0800 Intro / Admin Details Lt. Col. Nicholas Longo 5 min

0805 Rules of Engagement Ms. Kirsten Prechtl 10 min

0815 AATS Overview Maj. Gen. Stephen Purdy 15 min

0830 NSSL Overview Col. Douglas Pentecost 15 min

0845 Phase 3 Procurement Strategy Lt. Col. Nicholas Longo 30 min

0915 Phase 3 Lane 1 dRFP Lt. Col. Nicholas Longo 30 min

0945 Tiered Mission Assurance Lt. Col. Tae Kim 20 min

1005 Break 15 min

1020 Phase 3 Lane 2 dRFP Lt. Col. Nicholas Longo 15 min

1035 NSSL Requirements & Document Changes Lt. Col. Tae Kim 15 min

1050 Systems Engineering Data Maj. Will Deavor 15 min

1105 Spaceport of the Future Mr. Mark Bontrager 15 min

1120 Q&A / Closing Remarks Lt. Col. Nicholas Longo 30 min

Systems Engineering Data Demonstration Maj. Will Deavor Digital Innovation Chief, AAE

Unclassified Threat Brief SMSgt Ronald Lerch Senior Enlisted Leader, Intel Directorate

One-on-One Discussions Phase 3 Team/Industry