Questions and Answers.docx

DOCX document 13 KB Posted

Attached to
HVAC System Repair Federal contract opportunity
Solicitation number
N6893620Q0262
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

View the file

Other files for this federal contract opportunity

Other files attached to HVAC System Repair, newest first.
File Type Posted
Floor Plan.pdf PDF
20Q0262 Amendment 2.docx DOCX document
20Q0262 Amendment.docx DOCX document
20Q0262 Solicition.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Visit on 10/5/2020:

Point Mugu NAWS, Building 531 Questions from Contractors

1. Is there a brand name of system you would like installed?

Carrier to match the existing equipment in the mechanical room

2. Does the existing electrical system have adequate capacity to install two new units?

Yes

3. Can you provide pictures of the equipment in the mechanical room?

This will be a long process, as all photos will have to be cleared for public release. Approximately 2 weeks to complete.

4. How many BTU’s do you want the two new units to handle?

100,000. BTU

5. Do you want air purification added to the new systems?

No

6. How many square feet are being cooled on the 1st floor of the building?

Square Footage of required areas is approximately 3600Sqft.

7. How many square feet are being cooled on the 2nd floor of the building?

Square Footage of required areas is approximately 2200Sqft.

8. Can you provide a diagram of the office layout for both the 1st and 2nd floor?

See attached

9. How many thermostats do you want each floor and where do want the thermostats located? One thermostat for each floor see attached drawing for locations.

10. Do you want Costal Coatings on the Air Conditioning Units?

Yes coastal coating will be required

11. Can you provide pictures of the old units, ducting and the electrical panel in the mechanical room?

See answer on #3

12. How much clearance do you need between the condensing units and the generator located outside the Mechanical room?

Minimum 3 foot clearance for maintenance.