This document is a Request for Quotation (RFQ) for the removal of an existing boiler and installation of a new boiler at the Naval Construction Battalion Center in Gulfport, Mississippi. The contractor will be required to furnish labor, materials, equipment, and supervision to remove the existing Hurst boiler and feed water system and install a new Hurst Fire-tube Scotch Marine Steam Boiler, 150 PSIG Design Pressure, with an oil-fired Power Flame burner and Hurst Feed water Tank. The contractor will also be responsible for tying into the existing flue gas piping, wiring in vent louvers to the boiler controls, and installing all necessary piping and valves for water, steam, and fuel. The work shall be performed during core business hours of 0700 to 1600 Monday through Friday and excludes after-hours, weekends, and federal holidays. The offer due date is 31 May 2024 by 12:00 PM local time. This is a fixed-price requirement, and the North American Industry Classification System (NAICS) code is 113110 with a $19,000,000 size standard. The acquisition is set aside for small business.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6883624Q0095 0002.pdf | ||
| 2.05 Amendment U00001.pdf | ||
| 2.03a PPQ.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
N6883624Q0095 21-May-2024
b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME
12:00 PM 31 May 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
N688369. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
DYLAN L. DOUGLAS
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
1301157311
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
NAVSUP FLC JACKSONVILLE CONTRACTS DIV
DYLAN DOUGLAS
110 YORKTOWN AVE 3RD FLOOR
JACKSONVILLE FL 32212-0097
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE N65971 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
NAVAL CONSTRUCTION TRAINING CENTER
PAMELA SIMMONS
5510 CBC 8TH STREET
BUILDING 443
GULFPORT MS 39501-5003
TEL: 228-871-2977 FAX:
904-542-1095FAX:
TEL: 904-542-1058 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$19,000,000
NAICS:
113110
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF68
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
N6883624Q0095
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Each
BOILER REMOVAL INSTALL
FFP
Remove existing boiler and install new boiler in accordance with the statement of work.
FOB: Destination
MILSTRIP: 1301157311
PURCHASE REQUEST NUMBER: 1301157311
PSC CD: J044
NET AMT
SOW
STATEMENT OF WORK
Boiler Installation
1.0 INTRODUCTION
The Naval Construction Battalion Center is a 1,100-acre U.S. Navy industrial complex located in Gulfport, Mississippi. It serves as home base for the Atlantic Fleet Seabees, which are the Navy's construction battalions.
Scope
This Description of Requirement (DOR) states that a Contractor shall furnish labor, materials, equipment and supervision to remove existing Hurst boiler and feed water system located in the UT Training Bldg. 385 and install one (1) new Hurst Fire-tube Scotch Marine Steam Boiler, 150 PSIG Design Pressure and equipped with oil fired Power Flame burner and Hurst Feed water Tank. Tie-in to the existing flue gas piping (stack) as needed, wire in vent louvers to boiler controls, and install and provide all necessary piping and valves for water, steam and fuel. Tee off the newly installed steam line to tie in a “steam discharge” into the existing 4” vent/drain pipe, to vent stream into the outside drain with control valve. In addition, the contractor will perform a combustion tuning and check operating and safety controls and interlocks tested for proper setting and functionality.
1.3. Hours of Operation. Work shall be performed during the core business hours of 0700 through 1600 Monday thru Friday Central Daylight Time (CDT) and shall not include afterhours, weekends, and holidays.
1.4. Federal Government Holidays.
a. New Years Day 1st day of January Martin Luther King Jr.'s Birthday 3rd Monday of January Presidents Day 3rd Monday of February Memorial Day Last Monday of May Juneteenth Day 19th day of June Independence Day 4th day of July
Labor Day 1st Monday of September Columbus Day 2nd Monday of October Veterans Day 11th day of November Thanksgiving Day 4th Thursday of November Christmas Day 25th day of December
b. When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the proceeding Friday is observed as a legal holiday. This list of holidays relates to Government duty days and is not intended to supplement or otherwise alter the provisions of any Wage Determination regarding applicable paid holidays.
c. When the Department of Defense grants excused absence to its employees, the Contractor agrees to continue to provide sufficient personnel to perform critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the Contracting Officer (KO) or the DGR. Changes in employee work schedules shall comply with the terms and conditions of the contract, to include payment provisions.
1.7. Motor Vehicle Operators. Contractor’s personnel, whose tasks involve operation of any vehicles, shall possess a valid U.S. state driver’s license, certificates and permits, applicable for the type and class of vehicle being operated.
1.7.1 Contractor Vehicles. All Contractor vehicles shall be readily identifiable. Identification shall include displaying Contractor’s name in a clear and unobstructed location on the vehicle.
Motor vehicles entering Naval Construction Battalion Center (CBC) Gulfport Operational Area shall be properly licensed, insured, and registered with the Installation Access Pass Office.
1.8. Contractor Access and Use of Premises. The Contractor shall be responsible for securing the necessary permits and base access passes for Contractor personnel, vehicles, and equipment for the duration of the contract. CBC Security Forces reserve the right to refuse issuance of a pass to an employee of the Contractor for any reason deemed valid by the Government.
Contractors must identify themselves as either a U.S. Owned or a Foreign Owned, Controlled or Influenced (FOCI) entity.
1.8.1. Citizenship. Visitors must be U.S. citizens. Foreign nationals are rarely granted access unless certain arrangements have been made with CBC Security Forces.
U.S. citizen personnel of a Foreign Owned, Controlled or Influenced (FOCI) entity will be required to provide the security forces at the Pass and ID office located at 4701 Marvin Shields Blvd, Bldg 1, Gulfport MS 39501-5003 with vehicle registration, proof of insurance, driver’s license, and a second form of picture ID. A Visit / Access Request on company letterhead is also required at least 48 hours (recommend at least five days) in advance of VI repair service.
U.S. Owned company personnel will be required to provide the security forces with vehicle registration, proof of insurance, and driver’s license.
1.8.2. Infrequent Access (<30 days/year). Unless the Contractor is registered in the Defense Biometric Identification System (DBIDS), all infrequent visitors of less than 30 consecutive days will be required to stop at the Pass and Decal office every day to obtain a one-day pass until work is completed. Information regarding how to obtain the day passes will be provided by the
DGR.
1.9. Employment of Federal Employees. The Contractor shall not employ or enter into a contract with any person to perform work under this contract who is an employee of the United States Government, either military or civilian, unless such person receives approval IAW applicable Federal and DOD regulations.
1.10. Personnel Compliance. The Contractor shall ensure that Contractor employees observe and comply with all local and higher authority policies, regulations, and procedures concerning fire, safety, environmental protection, sanitation, security, traffic, parking, energy conservation, flag courtesy, “off -limits” areas, and possession of firearms or other lethal weapons. When two or more directives or instructions apply, the Contractor shall comply with the more stringent of the directives or instructions.
1.11. Identification (ID) Badge. The Contractor (to include Subcontractors) shall provide each employee an Identification (ID) Badge, which includes at a minimum, the Company Name, Employee Name and a color photo of the employee. ID Badges shall be worn at all times during which the employee is performing work under this contract. Each Contractor (to include Subcontractors) employee shall wear the ID Badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit. The Contractor (to include Subcontractors) shall be responsible for collection of ID Badges upon completion of the contract or termination of employee. A listing of issued identification cards shall be furnished to the KO and DGR prior to the contract performance date and updated as needed to reflect Contractor and Subcontractor personnel changes.
1.12. Smoking/Drug/Alcohol Policy. The Contractor shall comply with local command smoking policies and workforce requirements. The Contractor shall also comply with all Federal statues, laws, and regulations to implement a Drug Free Workplace Program (DFWP) as well as work force requirements and local command policies.
1.13. Personnel Conduct. The selection, assignment, reassignment, transfer, supervision, management, and control of Contractor personnel employed to perform the work specified herein shall be the responsibility of the Contractor. The Contractor shall be responsible for the performance and conduct of Contractor and Subcontractor employees at all times. The Contractor shall ensure that personnel present a professional appearance. Personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the installation shall abide by the security regulations listed in the contract and shall be subject to such checks by the Government as deemed necessary. The Contractor shall not employ for performance under this contract any person whose employment would result in a conflict of interest with the Government’s standards of conduct.
1.14. Personnel Removal. Government rules, regulations, laws, directives, and requirements that are issued during the term of the performance period relating to law and order, installation administration, and security shall be applicable to all Contractor employees and representatives who enter the installation. Violation of such rules, regulations, laws, directives, or requirements shall be grounds for removal (permanently or temporarily as the Government determines) from the work site or installation. Removal of employees does not relieve the Contractor from the responsibility for the work defined in this performance work statement. The Contractor is expected to provide support services despite personnel removal or other unforeseen condition(s).
Should replacement become necessary, the Government reserves the right to review all resumes of proposed candidates.
1.15. Interaction with Other Activities. Government and Contractor personnel will be working in common areas during working hours. Contractor performance shall not interfere with Government work in the area where any service is being performed. In the event the Contractor believes that Government and other Contractor personnel are interfering with the performance of the tasks described in this PWS, the Contractor shall notify the DGR immediately. The Contractor is obligated to continue performance of the effort described in this contract unless there is authorization from the KO or DGR to stop work. Failure by the Contractor to notify the DGR and receive necessary instructions could result in denial of any additional costs incurred in performance of the contract under such conditions. Other Government Contractor’s may be performing required services in areas that interrelate with the requirements of this contract. The Government will facilitate initial contact between Contractor’s performing other contracts and this contract. The Contractor shall provide all further required coordination between other Contractor’s for any task specified in this contract that relates to or impacts on any other contracted work.
1.16. Safety. The Contractor is solely responsible for compliance of all safety regulations of employees while working on Government owned facilities. All accidents which may arise out of, or in connection with, performance of services required herein which result in injury, death, or property damage, shall be reported in writing to the KO and DGR within twenty-four hours of such occurrence. Reports shall provide full details of the accident, including statements from witnesses. The fore-going procedures shall also apply to any claim made by a third party against the Contractor as a result of any accident that occurs in connection with performance under this contract.
1.17 Security Access.
1.17.1. Defense Biometric Identification System (DBIDS). Defense Biometric Identification System (DBIDS) increases installation security and communications by receiving frequent database updates on changes to personnel/credential status, law enforcement warrants, lost/stolen cards, and force protection conditions. The system provides a continuous vetting anytime the DBIDS card is scanned at an installation entry point.
If you currently have a Navy Commercial Access Control System (NCACS) card, the following is required to get a DBIDS credential:
• Present your NCACS Card and a completed copy of the SECNAV FORM 5512/1 to the base Visitor Control Center representative.
• The VCC will pull up your information in the computer, ensuring all information is current and correct.
• Once your information is validated, a temporary DBIDS credential is provided.
• Your temporary credential will have an expiration date, prior to which you will need to obtain your permanent DBIDS credential (~ 180 days).
• For each additional U.S. Navy installation to which you need access, the first time you visit you only need to bring your DBIDS credential and statement of purpose for base access when arriving at the Visitor Control Center.
• The representative will enter base access authorization and then you may proceed to work.
If you do NOT have an NCACS Card, the following is required to obtain a DBIDS credential:
• Present a letter or official document from my Government sponsoring organization that provides the purpose for your access.
• Present valid identification, such as a passport or Real ID Act-compliant state driver's License.
• Present a completed copy of the SECNAV 5512/1 form to obtain your background check.
• Upon completion of the background check, the Visitor Control Center representative will complete the DBIDS enrollment process, which includes your photo, finger prints, base restrictions, and several other assessments; after all this is done, you will be provided with your new DBIDS credential.
• You may now proceed to work.
For additional questions about obtaining a DBIDS card, contact your local base visitor control center.
Additional information is available at https://www.cnic.navy.mil/om/dbids.html.
1.17.2. Physical Security. The Contractor shall be responsible for safeguarding all Government equipment, information and property provided for Contractor use IAW OPNAVINST 5530.14E CH-2, Navy Physical Security and Law Enforcement Program. At the close of each work period, Government facilities, equipment and materials shall be secured.
2.0 DESCRIPTION OF ITEM
Installation of a 150 PSIG Hurst Fire-tube Scotch Marine Steam Boiler with Hurst Feedwater tank in accordance with the National Board Inspection Code (NBIC), Part 1, Installations, American Society of Mechanical Engineers (ASME) and applicable local codes
PART 2
GOVERNMENT FURNISHED ITEMS AND SERVICES
2. Government Furnished Items and Services.
2.1. Materials. The Government will provide (1)Hurst Fire-tube Scotch Marine Steam Boiler and Hurst Feedwater Tank for the boiler install.
2.2. Services. The Government will provide services to facilitate Contractor access to NCTC Gulfport and NCTC buildings where the boiler equipment is located.
2.3. Facilities. The Government will provide access to facilities for the Contractor’s use in support of this contract. Any alterations to facilities shall be approved in writing and property shall be returned to its original condition prior to completion of this contract. Contractor shall be responsible for any damages or loss of use due to their negligence. Any signage shall conform to standard Navy/Installation signs/format, shall be approved by the KO and DGR in writing prior to placement and may not be permanently affixed to any Government property or structure.
2.4. Utilities. The Government will provide all utilities in the facility and will be available for the Contractor’s use in performance of tasks outlined in this PWS. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities.
PART 3
CONTRACTOR FURNISHED ITEMS AND SERVICES
3. Contractor Furnished Items and Responsibilities.
3.1. Contractor Furnished Items. Everything included in this paragraph and its subparagraphs is basic to the contract and should be included in the contract price.
3.1.1. The Contractor shall provide all labor, supervision, transportation, vehicles, supplies, equipment, materials, facilities and services required to perform work under this contract that are not listed under Section 2 of this SOW.
3.2. Responsibilities of the Contractor.
a. The Contractor shall provide a safe working environment for all persons in his/her employment as prescribed by 29 CFR 1910 “Occupational Health and Safety.” The Contractor shall be responsible for all damages to persons and property that occur in connection with the work and service under this contract, without recourse against the Government.
b. Contractor shall be responsible for all loss or damage to Government property, while in the performance of these contract requirements, which result in whole or in part from the negligence or omissions of the Contractor, any of its Subcontractors, or any employee, agent, or representative of the Contractor or Subcontractor(s).
c. Contractor shall be certified and or licensed and bonded to perform boiler technician services within the state of Mississippi. All work performed must meet federal and state regulations by law. Contactor must provide reference(s) with contact information to the Contracting Officer at request and prior to award of the contract of at least one boiler installed by their company of this same size or larger within the past two years.
d. The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
PART 4
SPECIFIC TASKS
4.1 Period of Performance:
Upon receipt of award, contractor shall begin removal and installation on 11 July 2024 and finish NLT 02 August 2024.
4.2 Site Visit
An optional site visit will occur on 29 May 2024 at the installation location (see below) at 0900. The primary point of contact for this site visit will be Mr. Dylan Douglas (dylan.l.douglas.civ@us.navy.mil). All attendees must email the POC listed in 4.2 no later than noon eastern, 24-May-2024.
4.3 Installation LOCATION
Install Address:
Naval Construction Training Center 5510 CBC 8th Street, building 385 Gulfport, MS 39501
Points of Contacts
Technical: To be made available at time of award.
WAWF: To be made available at time of award.
SPECIAL DELIVERY INSTRUCTIONS
N/A.
INSPECTION REQUIREMENTS
N/A
PART 5
AUTHORIZED CHANGES ONLY BY THE CONTRACTING OFFICER (JAN 1992)
(a) Except as specified in paragraph (b) below, no order, statement, or conduct of Government personnel who visit the Contractor's facilities or in any other manner communicate with Contractor personnel during the periormance of this contract shall constitute a change under the "Changes" clause of this contract.
(b) The Contractor shall not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this contract.
(c) The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and notwithstanding provisions contained elsewhere in this contract, the said authority remains solely with the Contracting Officer. In the event the Contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in charges incurred as a result thereof. The address and telephone number of the Contracting Officer is:
Name: Contracting Officer Address: 110 Yorktown Avenue, NAS Jacksonville, FL 32212 Phone: (904) 542-1103
PART 6
CONTRACTOR UNCLASSIFIED ACCESS TO FEDERALLY CONTROLLED FACILITIES, SENSITIVE
INFORMATION, INFORMATION TECHNOLOGY SYSTEMS OR PROTECTED HEALTH INFORMATION
The following shall be inserted in full text in all solicitations and contracts (including commercial acquisitions) which require contractor unclassified access to federally controlled facilities, sensitive information, Information Technology (IT) systems or protected health information. For commercial acquisitions, this text shall be incorporated into either the SOW or PWS.
The security text does not apply in cases where the contractor/vendor does not have access to Navy Marine Corps Intranet (NMCI) computers, is not issued a Common Access Card (CAC) and is involved in training or other short term duties of less than 30 days duration that allow for the use of a visitor request. In these cases, the government employee must submit a Visitor Access Request (VAR) to the main gate or applicable processing entity for your facility and assume responsibility to escort those without CAC Credentials.
This local text does not apply to non-United States (U.S.) Nationals (foreign nationals) who are contactor employees performing work overseas. The local text is applicable to the U.S. Nationals living in the U.S. or overseas who are performing work on a Navy contract.
The investigation of a non-U.S. national at a foreign location must be consistent with a National Agency Check with Written Inquiries (NACI), to the extent possible and include a fingerprint check against the Federal Bureau of Investigation (FBI) criminal history database, an FBI investigations file (name check) search and a name check against the terrorist screening database. Also, the above cited reference notes that Foreign Nationals may not be granted CAC credentials until completion of their investigation and not in the interim.
Per Department of Defense Memorandum (DoDM) 5200.2, Department of Defense (DoD) components must initiate and ensure completion of a background investigation before applying the credentialing standards to a non-U.S.
national at a foreign location. The background investigation must be favorably adjudicated before a CAC can be issued to a non-U.S. national at a foreign location. The type of background investigation may vary based on standing reciprocity treaties concerning identity assurance and information exchanges that exist between the U.S. and its allies or agency agreements with the host country.
CONTRACTOR UNCLASSIFIED ACCESS TO FEDERALLY CONTROLLED FACILITIES, SENSITIVE
INFORMATION, IT SYSTEMS OR PROTECTED HEALTH INFORMATION
Executive Order 13467, Reforming Processes Related to Suitability for Government Employee, Fitness for Contractor Employees and Eligibility for Access to Classified National Security Information, Homeland Security Presidential Directive (HSPD)-12, requires government agencies to develop and implement Federal security standards for Federal employees and contractors. The 5 CFR 32 Part 157 in concert with DoD Manual 1000.13, Vol 1, implements the Federal Standards.
APPLICABILITY
This text applies to all DoD sponsored individuals who require CAC eligibility (or login and P/W if acceptable per contract) for: Physical access to DoD facilities or non-DoD facilities on behalf of DoD; Logical access to information systems (whether on site or remotely); or remote access to DoD networks that use only the CAC logon for user authentication, or access to sensitive and protected information. This applies to the Office of the Secretary of Defense (OSD), the Military Departments, the Office of the Chairman of the Joint Chiefs of Staff and the Joint Staff, the Combatant Commands, the Office of the Inspector General of the DoD, the Defense Agencies, the DoD Field Activities and all other organizational entities within the DoD (hereinafter referred to collectively as the "DoD Components").
Each contractor employee providing services at a Navy command under this contract is required to obtain a DoD CAC. Additionally, depending on the level of computer/network access, the contract employee will require a successful investigation as detailed below.
ACCESS TO FEDERAL FACILITIES
Per HSPD-12 and implementing guidance, all contractor employees working at a federally controlled base, facility or activity under this clause will require a DoD CAC. When access to a base, facility or activity is required contractor employees shall in-process with the Command's Security Manager (CSM) upon arrival to the command and shall out-process prior to their departure at the completion of the individual's performance under the contract.
START-UP PERIOD
All contractor resource onboarding documents must be submitted via the prime contractor. The prime contractor shall make all necessary preparations to assume full responsibility for productive performance as of the performance start date.
Definition of "productive":
a. Visit Authorization Request (VAR)
b. Contractor Information Sheet (CIS)
c. FD-258 Fingerprint Card
d. Completed Electronic Investigation (EQIP)
e. All contractor resource(s) must have an active Joint Personnel Adjudication System (JPAS) profile
f. Common Access Card(CAC)
Note (1): Invoicing by the contractor will begin as of the commencement of the performance period of services and no reimbursement will be paid by the government for efforts expended during the start-up period.
Note (2): Foreign Nationals are not allowed access to the functional/system side of Enterprise Resource Planning
(ERP).
ACCESS TO DOD INFORMATION TECHNOLOGY (IT) SYSTEM
In Accordance With (IAW) Secretary of the Navy (SECNAV) M-5510.30, contractor employees who require access to Department of the Navy (DoN) or DoD networks are categorized as IT-I, IT-II, or IT-III. The IT-II level, defined in detail in SECNAV M-5510.30, includes positions which require access to sensitive information. Sensitive information includes information protected under the Privacy Act, to include PHI. All contractor employees under this contract who require access to Privacy Act protected information are therefore categorized no lower than IT- II. IT Levels are determined by the requiring activity's Command Information System Security Manager (ISSM)/Information Assurance Manager (IAM).
Contractor employees requiring privileged or IT-I level access, (when specified by the terms of the contract) require a Single Scope Background Investigation (SSBI) or T5 or T5R equivalent investigation, which is a higher level investigation than the National Agency Check (NAC) with Law and Credit (NACLC)/T3/T3R described below. Due to the privileged system access, an investigation suitable for High Risk national security positions is required.
Individuals who have access to system control, monitoring, or administration functions (e.g. system administrator, database administrator) require training and certification to Information Assurance (IA) Technical Level 1, and must be trained and certified on the Operating System (OS) or Computing Environment (CE) they are required to maintain.
Access to sensitive IT systems is contingent upon a favorably adjudicated background investigation. When access to IT systems is required for performance of the contractor employee's duties, such employees shall in-process with the Navy CSM and ISSM/IAM manager upon arrival to the Navy command and shall out-process prior to their departure at the completion of the individual's performance under the contract. Completion and approval of a System Authorization Access Request Navy (SAAR-N) form is required for all individuals accessing Navy IT resources. The decision to authorize access to a government IT system/network is inherently governmental. The contractor supervisor is not authorized to sign the SAAR-N; therefore, the government employee with knowledge of the system/network access required or the Contracting Officers Representative (COR) shall sign the SAAR-N as the supervisor.
The SAAR-N shall be forwarded to the CSM at least thirty (30) days prior to the individual's start date. Failure to provide the required documentation at least thirty (30) days prior to the individual's start date may result in delaying the individual's start date.
When required to maintain access to required IT systems or networks, the contractor shall ensure that all employees requiring access complete annual Cyber Awareness training, and maintain a current requisite background investigation. The contractor's security representative shall contact the CSM for guidance when reinvestigations are required.
INTERIM ACCESS
The CSM may authorize issuance of a DoD CAC and interim access to a DoN or DoD unclassified computer/network upon a favorable review of the investigative questionnaire and advance favorable fingerprint results. When the results of the investigation are received and a favorable determination is not made, the contractor employee working on the contract under interim access will be denied access to the computer network and this denial will not relieve the contractor of his/her responsibility to perform.
DENIAL OR TERMINATION OF ACCESS
The potential consequences of any requirement under this clause including denial or termination of physical or system access in no way relieves the contractor from the requirement to execute performance under the contract within the timeframes specified in the contract. Contractors shall plan ahead in processing their employees and subcontractor employees. The contractor shall insert this clause in all subcontracts when the subcontractor is permitted to have unclassified access to a federally controlled facility, federally-controlled information system/network and/or to government information, meaning information not authorized for public release.
CONTRACTOR'S SECURITY REPRESENTATIVE
The contractor shall designate an employee to serve as the contractor's security representative. Within three (3) work days after contract award, the contractor shall provide to the requiring activity's Security Manager and the Contracting Officer, in writing, the name, title, address and phone number for the contractor's security representative. The contractor's security representative shall be the primary point of contact on any security matter.
The contractor's security representative shall not be replaced or removed without prior notice to the Contracting Officer and CSM.
BACKGROUND INVESTIGATION REQUIREMENTS AND SECURITY APPROVAL PROCESS FOR
CONTRACTORS ASSIGNED TO NATIONAL SECURITY POSITIONS OR PERFORMING SENSITIVE
DUTIES
Navy security policy requires that all positions be given a sensitivity value based on level of risk factors to ensure appropriate protective measures are applied. Contractor employees under this contract are recognized as Non- Critical Sensitive [ADP/IT-II] positions when the contract scope of work require physical access to a federally controlled base, facility or activity and/or requiring access to a DoD computer/network, to perform unclassified sensitive duties. This designation is also applied to contractor employees who access Privacy Act and PHI, provide support associated with fiduciary duties, or perform duties that have been identified as National Security Positions.
At a minimum, each contractor employee must be a US citizen and have a favorably completed NACLC or T3 or T3R equivalent investigation to obtain a favorable determination for assignment to a non-critical sensitive or IT-II position. The investigation consists of a standard NAC and a FBI fingerprint check plus law enforcement checks and credit check. Each contractor employee filling a non-critical sensitive or IT-II position is required to complete:
- SF-86 Questionnaire for National Security Positions (or equivalent Office of Personnel Management (OPM) investigative product)
- Two FD-258 Applicant Fingerprint Cards (or an electronic fingerprint submission
- Original Signed Release Statements
Failure to provide the required documentation at least thirty (30) days prior to the individual's start date shall result in delaying the individual's start date. Background investigations shall be reinitiated as required to ensure investigations remain current (not older than ten (10) years) throughout the contract performance period. The contractor's security representative shall contact the CSM for guidance when reinvestigations are required.
Regardless of their duties or IT access requirements ALL contractor employees shall in-process with the CSM upon arrival to the command and shall out-process prior to their departure at the completion of the individual's performance under the contract. Employees requiring IT access shall also check-in and check-out with the Navy command's ISSM/IAM. Completion and approval of a SAAR-N form is required for all individuals accessing Navy IT resources. The SAAR-N shall be forwarded to the Navy CSM at least thirty (30) days prior to the individual's start date. Failure to provide the required documentation at least thirty (30) days prior to the individual's start date shall result in delaying the individual's start date.
The contractor shall ensure that each contract employee requiring access to IT systems or networks complete annual Cyber Awareness training, and maintain a current requisite background investigation. Contractor employees shall accurately complete the required investigative forms prior to submission to the CSM. The CSM will review the submitted documentation for completeness prior to submitting it to the OPM; Potential suitability or security issues identified may render the contractor employee ineligible for the assignment. An unfavorable determination is final (subject to SF-86 appeal procedures) and such a determination does not relieve the contractor from meeting any contractual obligation under the contract. The CSM will forward the required forms to OPM for processing. Once the investigation is complete, the results will be forwarded by OPM to the DoD Central Adjudication Facility (CAF) for a determination.
If the contractor employee already possesses a current favorably adjudicated investigation, the contractor shall submit a VAR via the JPAS or a hard copy VAR directly from the contractor's security representative. Although the contractor will take JPAS owning role over the contractor employee, the Navy command will take JPAS "Servicing" role over the contractor employee during the hiring process and for the duration of assignment under that contract.
The contractor shall include the IT position category per SECNAV M-5510.30 for each employee designated on a VAR. The VAR requires annual renewal for the duration of the employee's performance under the contract.
BACKGROUND INVESTIGATION REQUIREMENTS AND SECURITY APPROVAL PROCESS FOR
CONTRACTORS ASSIGNED TO OR PERFORMING NON-SENSITIVE DUTIES
Contractor employee whose work is unclassified and non-sensitive (e.g., performing certain duties such as lawn maintenance, vendor services, etc...) and who require physical access to publicly accessible areas to perform those duties shall meet the following minimum requirements:
- Must be either a U.S. citizen or a U.S. permanent resident with a minimum of 3 years of legal residency in the U.S. (as required by the Deputy Secretary of Defense DTM 08-006 or its subsequent DoD Instruction (INST)) and
- Must have a favorably completed NACI or T1 investigation equivalent including a FBI fingerprint check prior to installation access.
To be considered for a favorable trustworthiness determination, the CSR must submit for all employees each of the following:
- SF-85 Questionnaire for Non-Sensitive Positions
- Two FD-258 Applicant Fingerprint Cards (or an electronic fingerprint submission)
- Original Signed Release Statements
The contractor shall ensure each individual employee has a current favorably completed NACI or T1 equivalent investigation, or ensure successful FBI fingerprint results have been gained and investigation has been processed with OPM.
Failure to provide the required documentation at least thirty (30) days prior to the individual's start date may result in delaying the individual's start date.
* Consult with your CSM and ISSM/IAM for local policy when IT-III (non-sensitive) access is required for non- U.S. citizens outside the U.S..*
**Alternative language which may be included as appropriate:
Contractor and all Contractor personnel with access to or responsibility for XXXXXX of this contract shall comply with DoD Directive 8500.1E IA, DoDI 8510.01 Risk Management Framework (RMF) for DoD IT, DoD Directive
5400.11 DoD Privacy Program, DoD 5200.2-R Personnel Security Program and HSPD 12.
X.1 Be CAC ready at the IT Level II prior to reporting for work.
X.2 At minimum, all contractor personnel must possess/maintain a favorable Tier 3 investigation; formerly a NAC with Local Agency Check and Credit Check (NACLC). This requirement is critical in order to access the data base systems within NAVSUP. It is Contracting Companies; responsibility to ensure that 100% of the contractors have the Tier 3 investigation/IT Level II. In addition, interim approval of clearances is not authorized.
X.3 Be citizens of the U.S.
X.4 If at any time, any contractor person requiring a CAC is unable to possess/maintain an adjudicated Tier 3 investigation, the contractor shall immediately notify the NAVSUP COR to coordinate removal of such a person from work under this contract.
X.5 Contractor personnel with access to or responsibility for nonpublic government data under this contract must comply with HSPD-12 Personal Identity Verification (PIV) issuance requirements, known as the CAC for
NAVSUP.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 11-JUL-2024 TO
02-AUG-2024
N/A NAVAL CONSTRUCTION TRAINING
CENTER
PAMELA SIMMONS
5510 CBC 8TH STREET
BUILDING 443
GULFPORT MS 39501-5003
228-871-2977 FOB: Destination
N65971
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-17 Ownership or Control of Offeror AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-22 Alternative Line Item Proposal JAN 2017 52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment
NOV 2021
52.209-2 Prohibition on Contracting with Inverted Domestic Corporations--Representation
NOV 2015
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
SEP 2023
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
NOV 2023
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-5 Alt I Pollution Prevention and Right-to-Know Information (May
2011) Alternate I
MAY 2011
52.223-5 Alt II Pollution Prevention and Right-to-Know Information (May 2011) Alt II
MAY 2011
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
JUN 2020
52.237-2 Protection Of Government Buildings, Equipment, And Vegetation
APR 1984
252.203-7000 Requirements Relating to Compensation of Former DoD Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
JAN 2023
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
JAN 2023
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.211-7003 Item Unique Identification and Valuation JAN 2023 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.225-7048 Export-Controlled Items JUN 2013 252.225-7055 Representation Regarding Business Operations with the
Maduro Regime
MAY 2022
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime
JAN 2023
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Products or Commercial
Services
NOV 2023
252.246-7003 Notification of Potential Safety Issues JAN 2023 252.247-7023 Transportation of Supplies by Sea JAN 2023
ADDENDUM 52.212-1
ADDENDUM 52.212-1, Instructions to Offerors—Commercial Products and Commercial Services.
The following provisions are incorporated into 52.212-1 as an addendum to this solicitation:
The Government intends to post solicitation N6883624Q0095 and all amendments to the Government Point of Entry via SAM.gov.
QUESTIONS
All questions and clarifications regarding this solicitation must be submitted via email to Contract Specialist, Mr.
Dylan Douglas at dylan.l.douglas.civ@us.navy.mil and Contracting Officer, Mr. Robert Edwards at robert.s.edwards42.civ@us.navy.mil; subject line to read: Questions/Clarifications for N6883624Q0095. Each question or comment should reference the applicable document, page number, and paragraph number. Quoters shall not include any proprietary information in a question, because the Government will provide the question and answer to all potential Quoters. All questions must be submitted no later than COB 05/30/2024.
The Government reserves the right not to respond to any questions received concerning this solicitation after the questions receipt date above. Accordingly, Quoters are encouraged to carefully review all solicitation requirements and submit questions to the Government early in the proposal timeframe.
HISTORICAL DATA
Incumbent: N/A
(a) North American Industry Classification System (NAICS) code and small business size standard. This procurement is being solicited in accordance with Federal Acquisition Regulation (FAR) Subpart 19.5 - Small Business programs. See block 10 of the SF1449 for the type of Small Business Set Aside, the North American Industry Classification Code System (NAICS), and the Small Business Size Standard.
(b) Submission of Quotes. Quoters shall submit quotes in PDF format by volume as described below. Each volume shall contain a cover sheet with #1 and #3 below.
The quote shall contain the following information:
1. Solicitation number as indicated on page one (1) of the SF1449, Block 5 and the Title of the procurement.
2. Time specified for receipt of quotes: Quoters shall ensure that quotes are received by the Government point of contact no later than the date and time indicated on page one (1) of the SF1449, Block 8.
3. Name, title, e-mail address, and telephone number of the individual(s) with authority to bind the company.
Quoter’s POC information for contractual questions/discussions. CAGE Code, Unique Entity ID (UEI), and Business Size.
4. Technical Description: See volumes below.
5. Terms of any express warranty: Not modified.
6. Provide Price and any discount terms as described in Price Volume.
7. “Remit to” address: The Quoter shall submit all volumes of its quoter electronically to dylan.l.douglas.civ@us.navy.mil
8. Representations and certifications: See Contractor Responsibility Volume.
9. Acknowledgment solicitation amendments: All amendments issued with signatures to acknowledge terms and conditions of amendments. Acknowledgement of all amendments issued to the solicitation shall be signed, and dated.
10. Past performance information , when included as an evaluation factor, to include recent and relevant contracts for the same or similar items and other references (including contract numbers, points of contact with telephone numbers and other relevant information ).
11. Quoters that fail to furnish required representations or information, or reject the terms and conditions of the solicitation may be excluded from consideration.
Quoters shall be submitted in volumes as follows (Font Times New Roman, 12 point font. Size limit for attachments to emails is 20MB):
Volume I – Price There is no page limit for Volume I submission
Quoters shall submit the following:
Standard Form (SF) 1449. Blocks 17a, 30a, 30b, and 30c of page one (1) of SF 1449 shall be completed and signed to show the Quoter has read and agrees to comply with all terms, conditions, and instructions provided in the solicitation document. By signing Block 30b of the SF1449, the Quoter has confirmed they take no exception to the solicitation and have read, understand, and agree to comply with all terms, conditions, and instructions outlined in the solicitation.
Price Quote. The Quoter shall fill in the price schedule and include unit prices. The unit price should be evenly incremented so that it adds up to the total price without rounding past the second digit right of the decimal point for total prices for all contract line items (CLINs). Pricing shall be structured in accordance with the contract line items identified in the SF 1449 bid schedule.
Volume II – Technical Capability Volume II is limited to 10 pages.
Quoters shall demonstrate an understanding of the solicitation requirements by providing the following:
Submission must have 1 inch margins, 12 point font, and single sided. If any quote is not incompliance with the page limitation, any page beyond 10 may not be evaluated. The quotes shall be evaluated against the following factors.
FACTOR 1: Proof of certification and/or licensure and bond to perform boiler technician services within the state of Mississippi as outlined in PWS Section 3.2c.
Each technical capability element must provide sufficient evidence that the Quoter has a clear understanding of the solicitation and are able to meet the minimum requirements and qualifications set forth in the PWS.
Volume III – Past Performance Volume III is limited to 20 pages The Quoter shall provide a maximum of three (3) relevant past performance evaluations of similar size, scope and complexity to services set forth in the PWS and completed within the past three (3) years prior to the solicitation closing date (See Block 8 of the SF1449). If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available which meets the requirements identified above, it shall be submitted with the quote.
If a CPARS is not available, then the Quoter shall submit a completed Past Performance…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .