STATEMENT OF WORK
Hauser CNC Grinder Repair, Model# S55-400, SN# 0569 & 0572
Fleet Readiness Center Southeast (FRCSE)
1.0 SCOPE
The contractor shall provide all materials, labor, supervision, tools, equipment, and any other items necessary to perform the onsite repair and certification of 2 Hauser CNC Grinders with the following discrepancy: “Fine adjustment does not repeat in X and Y axis.”
All work will be performed on site Fleet Readiness Center Southeast(FRCSE), Building 101, Naval Air
Station, Jacksonville, FL 32212. All travel and any other associated costs shall be included in the price to perform services and shall not be billed separately.
2.0 BACKGROUND
FRCSE utilizes the Hauser CNC Grinders in the final finishing process of replacement aircraft structural assemblies that require extremely tight tolerances. As the Grinders have aged, bearings, ball screws and races have worn and accuracy has lessened to the point where they need to be refurbished. FRCSE had the grinders diagnosed through testing and evaluation.
3.0 REQUIREMENT
3.1 The contractor shall perform the following:
1. Supply the material, tooling, and labor required to rework the two Grinders by performing the following functions to return the machines back to an operational state.
- Completely rebuild the U Axis including way covers
- Replace Y Axis Ball Screw and Bearings
- Replace X Axis Ball Screw and Bearings
- Replace X Axis Rollers
- On Grinder, Serial# 0572, Install a new Collector with Brushes and Cover
2. Perform laser certification/calibration to certify both grinders after completion of rebuild and repair.
3. FRCSE will supply access to electrical, shop air, overhead crane(2,000lbs.), minimal rigging support, and an onsite representative to assist in any other requirements when needed.
3.1.1. FRCSE will also provide all the required parts for servicing the Hauser CNC
Grinder Model# S55-400, SN# 0569 & 0572.
3.2 Services shall be performed between the hours of 6:00 A.M. and 2:30 P.M. (Eastern Time), Monday through Friday, excluding federal holidays.
1. Government observed holidays: New Year’s Day, Martin Luther King, Jr., President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
4.0 GOVERNMENT FURNISHED REPAIR PARTS
1. The Government will provide the parts listed below to aid in the repair of the two
Hauser Grinders.
PART NO. / DESCRIPTION / SPECIFICATIONS QUANTITY
ORDERED
HTT2141589 PROTECTION BELLOWS-U AXIS LEFT 2
HTT2141590 PROTECTION BELLOWS-U AXIS RT 2
HTT2141996 SET OF GUIDEWAYS 2
HTT2141997 SET OF GUIDEWAYS 2
HTT2141579 ROLLER, DIA. 6x5,8 64
HTT2134616 COVER 14
HTT2232900 BALL BEARING EN 265-J877 8
HTT2104773 BALL BEARING 626-2Z 2
HTT2210427 ROLLER 4
HTT2210428 PIVOT 4
HTT211060 BALL SCREW X-AXIS REPLACEMENT 2
HTT2211050 BALL SCREW 2
HTT211058 STOP RING 2
HTT211059 LIMIT STOP 2
HTT2211054 END STOP 2
HTT2211055 COVER 2
HTT2204629 BLOCK WITH BEARINGS 2
HTT2106120 GREASE FITTING 4
HTT104997 BALL BEARING 6008 2
HTT132413 ROLLER BEARING D-91074 INA 2
HTT104964 BALL BEARING 6206-Z 2
HTT2233372 SET OF AXIAL BEARINGS MM40BS72QUH 2
HTT2135675 BALL BEARING 6005-2Z 2
HTT2104943 BALL BEARING 6205-Z 2
HTT2100244 CAP SCREW M4 X 16 4
HTT2100340 CAP SCREW M X 30 12
PAK6000000LIST LOAD RELIEVING ELEMENT / HTT2140305 [ 20 WEEK LEAD TIME ] 6
HTT2206761 COLLECTOR 1
HTT2141207 ADAPTER CABLE 200 MM 1
HTT2132444 CONTROL UNIT CJD-00, B-7167 12
HTT233186 TOOTHED BELT 3MR-630X25 1
HTT2141648 FELT RING SEGMENT 2
HTT2542037 FILTER ELEMENT 1
HTT723468 FILTER ELEMENT 1
HTT2230546 FILTER ELEMENT PALL HC9801FDP4 1
HTT230972 FILTER ELEMENT B-6890 1
HTT233186 TOOTHED BELT 3MR-630X25 1
PAK6000000LIST LOAD RELIEVING ELEMENT / HTT2140305 [ 20 WEEK LEAD TIME ] 6
HTT2230383 TIN OF GREASE 250 GR. 1
HTT2132381 TIN OF 250 GREASE 1
5.0 FRCSE TECHNICAL POINT OF CONTACT (TPOC)
Information will be provided at the time of award.
6.0 PERFORMANCE PERIOD
The contractor shall coordinate with the TPOC within one (1) business day after receipt of award to arrange services start date. However, all work shall be completed with 50 business days upon award date.