The file's text, extracted by GovTribe without its formatting.
12 February 2018
MEMORANDUM
From:
NAVAIR Fleet Readiness Center Mid-Atlantic (FRCMA) Voyage Repair Team (VRT), Product Support Section To:
NAWC AD/LKE Contracts Section Subj:
CONTRACTUAL PROCUREMENT OF A 62 INCH CLAUSING CNC FAGOR 8055I MILLING MACHINE AND RELATED ACCESORIES
| Qty |
| Manufacturer PN |
| ALRE Part # |
| Description |
| 1 |
| 8055i |
| N/A |
| 62 Inch Clausing Milling CNC FAGOR W/ Accessories |
| 1 |
| IUID (OM) |
| N/A |
| UID Tag and Name plate affixed to the Machine |
| 1 |
| INST |
| N/A |
| Installation and Setup |
| 1 |
| TRAIN |
| N/A |
| 3 Days Operator Training Onsite |
| 1 |
| 8VS205 |
| N/A |
| Coolant Oil Skimmer |
| 1 |
| 8VSCNC10 |
| N/A |
| CNC Fagor Scale Option(Factory Install) |
| 1 |
| 2VS010 |
| N/A |
| 52 Piece Clamping Kit |
| 1 |
| 2VS022 |
| N/A |
| NMTB40 Milling Chuck Kit w/7 Collets |
| 1 |
| FV-9010G |
| N/A |
| Kurt 6” Vise |
| 1 |
| FV-9011G |
| N/A |
| Swivel Base for FV-9010G |
| 1 |
| FV-9012G |
| N/A |
| Vise Step Key Kit 11/16 x 5/8 |
| 3 |
| Man Set (OM) |
| N/A |
| 3 Sets of Manuals |
| 1 |
| Voltage Requirements |
| N/A |
| 460V/3Phase 60 Hz |
Shipping to Norfolk, VA 23511
2. Due to the aggressive maintenance schedule, urgency in the tasking, inability to locate capable procurement vendors and delivery date there is insufficient opportunity and or lead-time to properly synopsize this contract. In addition, it has been determined that this Purchase Request falls under an exception clause for synopsis. Due to the unusual and compelling urgency, the synopsis cannot be conducted IAW NAVSUPINST 4200.85D PG 4-5, PARA 4E (1), FAR 5.202(2) AND FAR 6.302-2. Based upon this determination, request a waiver of synopsis be authorized for the subject contract.