N6449819Q5169.docx
DOCX document 158 KB Posted
- Attached to
- Anchor Windlass Technical Manual Update Federal contract opportunity
- Solicitation number
- N6449819Q5169
About this file
Solicitation N649819Q5169 closes 07/01/2019
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6449819Q5169SOW.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N6449819Q5169
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lite |
Anchor Windlass Tech Manual Update
FFP
LHD 1-4 CLASS ANCHOR WINDLASS TM UPDATE (S9581-BE-MMA-010)
FOB: Destination
VENDOR PART NR: 100001477902-0020
PURCHASE REQUEST NUMBER: 1300789033
PSC CD: L099
NET AMT
Section C - Descriptions and Specifications
CLAUSES INCORPORATED BY FULL TEXT
C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)
(a) Department means the Department of the Navy.
(b) Commander, Naval Sea Systems Command means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.
(c) References to The Federal Acquisition Regulation (FAR) All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.
(d) National Stock Numbers Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:
(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit nonsignificant number.
(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.
(End of text)
C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA) (OCT 2018)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
C-211-H001 ACCESS TO THE VESSEL(S) (NAVSEA) (OCT 2018)
Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.
C-211-H002 DRY-DOCK CERTIFICATION (NAVSEA) (OCT 2018)
The dry-docking of all vessels shall be accomplished in dry docks certified in accordance with MIL-STD-1625D(SH) dated 27 August 2009 as invoked by NAVSEA Standard Item 009-01 dated 18 November 2016. A copy of Standard Item (SI) 009-01 can be obtained from the internet by going to http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-01.
C-211-H004 HEAVY WEATHER PLAN (NAVSEA) (OCT 2018)
(a) In order to ensure that Naval vessel(s), material and Government property are protected during destructive weather such as gales, storms, hurricanes, high winds, heavy snow, ice and high water, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69 dated 18 November 2016. A copy of Standard Item (SI) 009-69 can be obtained from via the internet by going to: http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-69. In accordance with SI 009-69, the Contractor shall furnish to the cognizant Regional Maintenance Center (RMC), a copy of such HWP, and shall make such changes in the plan as the RMC considers necessary and reasonable to protect and care for vessel(s), material and Government property.
(b) In the event the RMC directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such Government direction.
C-211-H005 PLANT PROTECTION (NAVSEA) (OCT 2018)
(a) In accordance with NAVSEA STANDARD ITEM (SI) 009-72, ( ) the Contractor shall develop, maintain, and implement, as necessary, a Plant Protection Plan ( ) which prescribes the actions and procedures and assigns responsibilities for actions to be taken to provide adequate protection of the ship(s) and the materials and equipment to be installed therein. A copy of SI 009-72 can be obtained from the purchasing office representative listed in Section G of the contract or via the internet by going to http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-72.
(b) The Contractor shall establish and maintain, for its plant and the work in process under this contract, physical security boundaries and other security measures to provide safeguards against hazards, including unauthorized entry, malicious mischief, theft, espionage, sabotage, and terrorism to U.S. Naval Vessels and their crews, in accordance with SI 009-72 and Attachment A thereto. The Contractor shall also provide reasonable safeguards against vandalism and fire.
(c) The Contractor shall meet the requirements of Force Protection Condition NORMAL (as defined in SI 009-72) at all times. In addition, and in accordance with SI 009-72, the Contractor shall meet the requirements of increased levels of Force Protection as may be required or approved by the Contracting Officer, or when notified by the Supervisor, for the protection of its plant and the work in process under this contract against any threats including terrorism, espionage, sabotage, and enemy action.
(d) At the Supervisor’s discretion, the Contractor and the Supervisor shall negotiate a cost rate agreement applicable to each level of increased Force Protection above the NORMAL level. In addition to material costs, the labor cost rates shall be negotiated using the contractor’s and the Supervisor’s accepted common business practices. The labor and material costs to the Contractor for all safeguards so required or approved shall, to the extent allowable and allocable to this contract, be reimbursed to the Contractor in the same manner as if the Contractor has furnished such safeguards pursuant to a change order issued under the clause of this contract entitled "Changes-Fixed Price" (FAR 52.2431) or "Changes-CostReimbursement" (FAR 52.2432), as applicable. Such costs shall not include any allowance on account of overhead expense, except shop overhead charges incident to the construction or installation of such devices or equipment.
(e) Upon payment, in accordance with the Payments provision of this contract, by the Government of the cost to the Contractor for any device or equipment required or approved under paragraph (c) above, title thereto shall vest in the Government, and the Contractor shall comply with the instructions of the Contracting Officer respecting the identification and disposition thereof. No part or item of any such devices or equipment shall be or become a fixture by reason of affixation to any realty not owned by the Government.
(f) The plant protection plan and rate agreements required by this requirement shall be completed and implemented, within sixty (60) days of contract award for new construction and prior to ship arrival for conversion, repair or overhaul.
C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
C-211-H019 COMMONALITY AND STANDARDIZATION (NAVSEA) (FEB 2019)
The Contractor shall develop and implement a Commonality and Standardization Plan, reducing range and increasing depth of like equipment, to enhance supportability, minimize life cycle costs, and increase system readiness and interoperability across ships/ship classes through the selection of equipment and components which are, to the maximum extent possible, (1) common for application within the Class and (2) common with equipment/components currently installed in U.S. Navy ships. The Contractor shall utilize both Industry (e.g., the Common Parts Catalog) and Government (e.g., NAVSEA Enterprise Commonality Virtual Shelf and the Hull, Mechanical and Electrical Equipment Data Research System (HEDRS)) tools to implement its Commonality and Standardization Plan. For selecting Hull Mechanical and Electrical (HM&E) equipment/components, the Contractor shall utilize NAVSEA Enterprise Commonality Virtual Shelf before other tools, if the items meet the contract requirements. The Virtual Shelf is a web-based repository of HM&E equipment/components that meet cross-platform requirements and specifications and provide superior Total Ownership Cost (TOC). Information to gain access to the Virtual Shelf is located on the following web site: https://www.dau.mil/team/virtualshelf/SitePages/Home.aspx.
C-211-H020 PROTECTION OF THE VESSEL (NAVSEA) (MAR 2019)
(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been offloaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.
(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirtyfive degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipelines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.
(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.
(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.
(End of Text)
C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (APR 2019)
(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST 5510.2D.
(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:
(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.
(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.
(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.
(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.
(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.
(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.
(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.
(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.
(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.
(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-U.S. citizens of hostile and/or communist-controlled countries.
(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "Default (Fixed-Price Supply and Service)" (FAR 52.249-8), "Default (Fixed-Price Research and Development)" (FAR 52.249-9) or "Termination (Cost Reimbursement)" (FAR 52.249-6), as applicable.
(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.
(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.
(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.) except that, with respect to access to the vessel and worksite, the restrictions shall not apply to uniformed U.S. Navy personnel who are non-U.S. citizens and who are either assigned to the ship or require access to the ship to perform their duties.
C-223-H002 SAFETY, HEALTH AND FIRE REQUIREMENTS FOR SHIP REPAIR (NAVSEA) (JAN 2019)
(a) Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.13). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.
(b) SAFETY INSPECTOR/FIRE MARSHAL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshal who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety Representative. This Inspector or Fire Marshal shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved Safety Plan.
(c) PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:
(1) Protective hard hats that meet the following specifications:
(i) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated by the Contractor to be equally effective.
(ii) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National Standard Safety requirements for Industrial Head Protection," Z89.1-1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR 1910.135 Head Protection]
(2) Approved type Plano or prescription glasses meeting the following specifications:
(i) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.
(ii) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1-1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF 1910.133 Protective eye and face devices.]
(3) Safety toe shoes, with built-in protective toe box that meet the following specifications:
(i) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.
(ii) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]
C-223-H004 MANAGEMENT AND DISPOSAL OF HAZARDOUS WASTE (NAVSEA) (MAR 2019)
(a) General
(1) The Contractor shall comply with the Resource Conservation and Recovery Act (RCRA), the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), 10 U.S.C. 7311 and all other applicable Federal, State and local laws, codes, ordinances and regulations for the management and disposal of hazardous waste.
(2) Nothing contained in this special contract requirement shall relieve the Contractor from complying with applicable Federal, State, and local Laws, codes, ordinances, and regulations, including obtaining licenses and permits, giving notices and submitting reports, in connection with hazardous waste management and disposal in the performance of this contract. Nothing contained herein shall serve to alter either party's liability or responsibility under CERCLA.
(3) Materials contained in ship systems are not waste until after removal from the system.
(b) Identification of Hazardous Wastes of this contract identifies the types and amounts of hazardous wastes that are required to be removed by the Contractor, or that are expected to be generated, during the performance of work under this contract.
(c) Generator Identification Numbers
(1) Documentation related to hazardous waste generated solely by the physical actions of ship's force or Navy employees on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law.
(2) Documentation related to hazardous waste generated solely by the physical actions of Contractor personnel shall only bear a generator identification number issued to the Contractor pursuant to applicable law. Regardless of the presence of other materials in or on the shipboard systems or structures which may have qualified a waste stream as hazardous, where the Contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator identification number issued to the Contractor.
(3) Documentation related to hazardous waste generated by the combined physical actions of Navy and Contractor personnel shall bear a generator identification number issued to the Contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law.
(4) Notwithstanding paragraphs (c)(1) - (c)(3) above, hazardous wastes are considered to be co-generated in cases where: (a) the Contractor merely drains a system and such drainage creates hazardous waste or (b) the Contractor performs work on a system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste. Documentation related to such co-generated waste shall bear a generator identification number in accordance with the provisions of paragraph (c)(3) above.
(5) In the event of a failure by the parties to agree to the assignment of a generator identification number to any hazardous waste as set forth in paragraphs (c)(1) through (c)(4) above, the Government may direct which party or parties shall provide generator identification numbers for the waste and such number(s) shall be used on all required documentation. Any disagreement with this direction shall be a dispute within the meaning of clause of this contract entitled "Disputes" (FAR 52.233-1). However, the Contractor shall not stop any work but shall continue with performance of all work under this contract as specified in the "DISPUTES" clause.
(6) Hazardous Waste Manifests For wastes described in (c)(2), (c)(3), and (c)(4) above (and (c)(5) as applicable), the Contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the Manifest is required for disposal. The Contractor shall obtain concurrence with the categorization of wastes under paragraphs (c)(3) and (c)(4) above before completion of the manifest. Manifests prepared pursuant to paragraph (c)(1) above shall be presented to the for completion after the hazardous waste has been identified.
(7) For purposes of paragraphs (c)(2) and (3) herein, if the Contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the State in which the availability will be performed, the Contractor shall notify within 3 business days of receipt of written notification by the State. After obtaining approval, the Contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located. For purposes of paragraph (c)(1) herein, if the work is being performed at a contractor facility and the Government cannot obtain a separate generator identification number for the State, the Government shall use the Contractor site generator identification number and shall cite in the remarks block a Navy generator identification number. In both instances described above, the Contractor shall prepare the Uniform Hazardous Waste Manifest described in paragraph (c)(6) above and present it to for completion.
C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)
The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) A0001, attached hereto.
C-228-H001 INDEMNIFICATION FOR ACCESS TO VESSEL (NAVSEA) (DEC 2018)
Notwithstanding any provision in the "Access to Vessel" clause (DFARS 252.217- 7011), or any other clause of the contract, the Contractor agrees to allow officers, employees, and associates of the Government, or other prime contractors with the Government and their subcontractors, and officers, employees, and associates of offerors on other contemplated work, admission to the Contractor's facilities and access to the vessel without any further request for indemnification from any party, which has not been previously included in the contract price.
C-237-H001 ENTERPRISE-WIDE CONTRACTOR MANPOWER REPORTING APPLICATION (NAVSEA) (OCT 2018)
(a) The contractor shall report contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the [insert named component] via a secure data collection site. Contracted services excluded from reporting are based on Product Service Codes (PSCs). The excluded PSCs are:
(1) W, Lease/Rental of Equipment;
(2) X, Lease/Rental of Facilities;
(3) Y, Construction of Structures and Facilities; (4) D, Automatic Data Processing and Telecommunications, IT and Telecom- Telecommunications Transmission (D304) and Internet (D322) ONLY;
(5) S, Utilities ONLY;
(6) V, Freight and Shipping ONLY.
(b) The contractor is required to completely fill in all required data fields using the following web address https://www.ecmra.mil.
(c) Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://dod.ecmra.support.desk@mail.mil.
C-243-H002 NOTIFICATION OF CHANGES (NAVSEA) (MAY 2019)
(a) Definitions. As used in this requirement, the term "Contracting Officer" does not include any representative of the Contracting Officer whether or not such representative is acting within the scope of his authority nor does it include any other individuals or activities that in any way communicate with the Contractor. As used in this requirement, the term "conduct" includes both actions and failures to act, and includes the furnishing of, or the failure to furnish, any item under any provision of this contract.
(b) Notice. The primary purpose of this requirement is to obtain prompt reporting of any conduct which the Contractor considers would constitute or would require a change to this contract. The parties acknowledge that proper administration of this contract requires that potential changes be identified and resolved as they arise. Therefore, except for changes identified as such in writing and signed by the Contracting Officer, the Contractor shall notify the Contracting Officer of any conduct which the Contractor considers would constitute or would require a change to this contract. Such notice shall be provided promptly, and in any event within thirty (30) calendar days from the date the Contractor identifies any such conduct. The Notice shall be written and shall state, on the basis of the most accurate information available to the Contractor:
(1) The date, nature, and circumstances of the conduct regarded as a change;
(2) The name, function, and activity of the individuals directly involved in or knowledgeable about such conduct;
(3) The identification of any documents and the substance of any oral communication involved in such conduct;
(4) The particular elements of contract performance for which the Contractor might seek an equitable adjustment under this requirement, including:
(i) What ship(s) have been or might be affected by the alleged change;
(ii) To the extent practicable, labor or materials or both which have been or might be added, deleted, or wasted by the alleged change;
(iii) To the extent practicable, the Contractor's preliminary order of magnitude estimate of cost and schedule impact, including what delay and disruption in the manner and sequence of performance and effect on continued performance have been or may be caused by the alleged change; and
(iv) What and in what manner are the particular technical requirements or contract requirements regarded as changed; and
(v) The Contractor’s estimate of the time by which the Government must respond to the Contractor’s notice to minimize cost, delay or disruption of performance.
(c) Continued Performance. Except as provided in paragraph (f) below, following submission of notice, the Contractor shall take no action to implement an alleged change until advised by the Contracting Officer in writing as provided in (d) below, unless the alleged change was previously directed by the Contracting Officer, in which case the Contractor shall conform therewith. Nothing in this paragraph (c) shall excuse the Contractor from proceeding with contract work other than implementation of the alleged change or from proceeding in accordance with directions issued by the Contracting Officer.
(d) Government Response. The Contracting Officer shall promptly, and in any event within twentyone (21) calendar days after receipt of Notice, respond thereto in writing. In such response, the Contracting Officer shall either:
(1) Confirm that the conduct of which the Contractor gave notice would constitute a change, and when necessary, direct the mode of further performance, or;
(2) Countermand any conduct regarded by the Contractor as a change, or;
(3) Deny that the conduct of which the Contractor gave notice would constitute a change and, when necessary, direct the mode of further performance, or;
(4 In the event the Contractor's notice information is inadequate to make a decision under (i), (ii) or (iii) above, advise the Contractor what additional information is required. Failure of the Government to respond within the time required above shall be deemed a countermand under (d)(ii).
(e) Equitable Adjustments. Equitable adjustments for changes confirmed or countermanded by the Contracting Officer shall be made in accordance with the clause of this contract entitled "CHANGES", or any other requirement of this contract which provides for an equitable adjustment.
(f) Special Procedures. Paragraph (c) provides that the Contractor is to take no action to implement an alleged change pending the Contracting Officer's response to the Contractor's notice of the change, except where specifically directed by the Contracting Officer. In special situations, however, such as where:
(1) The circumstances do not allow sufficient time to notify the Contracting Officer of the facts prior to the need to proceed with the work, and;
(2) The work must proceed to avoid hazards to personnel or property or to avoid additional cost to the Government, the Contractor may proceed with work in accordance with the alleged change. In such special situations, the Contractor shall advise the Contracting Officer in writing within ten (10) days of the conduct giving rise to the alleged change that the Contractor has proceeded with work and shall describe the nature of the special situation which required proceeding prior to notification. Within thirty (30) calendar days of the conduct giving rise to the alleged change, the Contractor shall provide notice as required in (b) above. The Contracting Officer shall respond as set forth in (d) above. If the Contracting Officer determines that the conduct constitutes a change and countermands it, the Contractor shall be entitled to an equitable adjustment for performance of work in accordance with that change prior to the countermand including any additional performance resulting from the countermand.
(g) When the Contractor identifies any conduct which may result in delay to delivery of the ship(s), the Contractor shall promptly so inform the Contracting Officer thereof prior to providing the notice required by paragraph (b) above.
(h) Despite good faith best efforts, occasions may arise in which the Contractor does not provide notice within the time periods specified in paragraphs (b) and (f) above. Accordingly, prior to the end of the first and third quarters of each calendar year through the period of performance of this contract, beginning with the quarter of , the Contractor shall deliver to the Government an executed release, in the format set forth in Exhibit "A" to this requirement, covering the six-month period of time ending with the second and fourth quarters, respectively, of the preceding year, with such specific exceptions, if any, as are identified by the Contractor. If the Contractor cites specific exceptions to the release, the Contractor shall concurrently provide the Contracting Officer with notice, containing the information set forth in paragraph (b) of this requirement, for each item excepted from the release. However, the release required by this requirement shall not make unallowable any costs which are otherwise allowable under any other requirement of this contract. Within sixty (60) days of receipt of the release, the Contracting Officer shall sign and return a copy of the release to the Contractor. If the Contracting Officer fails to execute and return the release within the required time, then the release shall be deemed to be void and of no effect for the period involved.
(End of text)
EXHIBIT A TO C-243-H002, NOTIFICATION OF CHANGES
This modification reflects the agreement of the parties to the mutual full and final releases for the consequences of that conduct (as conduct is defined in the requirement entitled "NOTIFICATION OF CHANGES"), described below, except the conduct identified in Attachment A hereto is excluded and not covered by the terms of this release.
1. Except for the conduct listed in Attachment A by either party, neither the Contractor nor the Government shall be entitled to any equitable adjustment or to money damages and/or other relief for any conduct, as specified below.
2. In consideration of the foregoing the parties hereby agree to the following release:
a. The Government, for itself, its assigns, vendors, suppliers, and contractors, hereby remises, releases, and forever discharges the Contractor, its officers, agents and employees from any and all entitlement of the Government to equitable adjustment of the contract price and delivery schedule due to conduct under this contract, which occurred on or before .
b. The Contractor, for itself, its successors, assigns, vendors, suppliers, and subcontractors, hereby remises, releases and forever discharges the Government, its officers, agents and employees from (i) any and all entitlement of the Contractor to equitable adjustment of the contract cost and profit/fee and/or delivery schedule of this contract or of any other Government contract (with this or any other Contractor) or any contract between the Contractor and any third party by reason of any conduct which increases the Contractor's cost or time of performance of work under this contract and meets the following conditions (1) known to the Contractor, (2) occurred on or before and (3) the Contractor failed to give notice prior to date of this release, and (ii) any and all liabilities to the Contractor for money damages and/or other relief for the impact of any such conduct, upon this contract or any other Government contract (with this or any other Contractor) or any contract between the Contractor and any third party.
(End of Exhibit A)
C-245-H006 ADDITIONAL REQUIREMENTS RELATING TO GOVERNMENT PROPERTY (NAVSEA) (OCT 2018)
(a) For purposes of paragraph (h) of the clause entitled "Government Property" (FAR 52.245-1) in addition to those items of property defined in that clause as Government Property, the following shall also be included within the definition of Government Property:
(1) the vessel;
(2) the equipment on the vessel;
(3) movable stores;
(4) cargo; and
(5) other material on the vessel
(b) For purposes of paragraph (b) of the clause entitled "Government Property", notwithstanding any other requirement of this contract, the following shall not be considered Government Property:
(1) the vessel;
(2) the equipment on the vessel;
(3) movable stores; and
(4) other material on the vessel
C-247-H001 PERMITS AND RESPONSIBILITIES (NAVSEA) (DEC 2018)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits for complying with any applicable Federal, State, and Municipal laws, codes, and regulations for shipping and transportation including, but not limited to, any movement over public highways of overweight/over dimensional materials.
(End of text)
Section D - Packaging and Marking
D-211-H001 PACKAGING OF DATA (NAVSEA) (OCT 2018)
Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.
All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.
Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), DOD 5220.22-M dated 28 February 2006 incorporating Change 2 dated 18 May 2016.
D-211-H002 MARKING OF REPORTS (NAVSEA) (OCT 2018)
All reports delivered by the Contractor to the Government under this contract shall prominently show on the cover of the report:
| (1) name and business address of the Contractor |
| (2) contract number |
| (3) sponsor: |
(Name of Individual Sponsor)
(Name of Requiring Activity)
(City and State)
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| Destination |
| Government |
| Destination |
| Government |
E-246-H013 INSPECTION AND ACCEPTANCE OF DATA (NAVSEA) (OCT 2018)
Inspection and acceptance of all data shall be as specified on the attached Contract Data Requirements List(s), DD Form 1423.
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC / CAGE |
| 0001 |
| POP 13-MAY-2019 TO |
30-SEP-2019
| N/A |
| NAVAL SURFACE WARFARE CENTER PHILA |
JAMES L. FRIES
NSWC PHILADELPHIA DIVISION
1601 LANGLEY AVENUE
BLDG 542
PHILADELPHIA PA 19112
215-897-7799 FOB: Destination N64498
F-247-H001 DELIVERY OF DATA (NAVSEA) (OCT 2018)
All data to be furnished under this contract shall be delivered prepaid to the destination(s) and at the time(s) specified on the Contract Data Requirements List(s), DD Form 1423.
Section G - Contract Administration Data
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
Invoice 2in1 for Service
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
| Field Name in WAWF |
| Data to be entered in WAWF |
| Pay Official DoDAAC |
| N64500 |
| Issue By DoDAAC |
| N64498 |
| Admin DoDAAC** |
| N64498 |
| Inspect By DoDAAC |
| N64498 |
| Ship To Code |
| N64498 |
| Ship From Code |
| ____ |
| Mark For Code |
| N64498 |
| Service Approver (DoDAAC) |
| ____ |
| Service Acceptor (DoDAAC) |
| ____ |
| Accept at Other DoDAAC |
| ____ |
| LPO DoDAAC |
| ____ |
| DCAA Auditor DoDAAC |
| ____ |
| Other DoDAAC(s) |
| ____ |
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
Kimberly Villano Kimberly.Villano@navy.mil 215-897-2433
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
G-232-H002 PAYMENT INSTRUCTIONS AND CONTRACT TYPE SUMMARY FOR PAYMENT OFFICE (NAVSEA) (JUN 2018)
(a) The following table of payment office allocation methods applies to the extent indicated.
For Government Use Only
| Contract/Order Payment Clause |
| Type of Payment Request |
| Supply |
| Service |
| Construction |
| Payment Office |
Allocation Method
52.212-4 (Alt I), Contract Terms and Conditions—Commercial Items 52.216-7, Allowable Cost and Payment…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.