Statement_of_Work_MARMC_Facility_Planning_Follow_On.pdf

PDF 15 KB Posted

Attached to
MARMC Facility Planning Follow On Federal contract opportunity
Solicitation number
N50054-17-P-0040
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to MARMC Facility Planning Follow On, newest first.
File Type Posted
Sole_Source_Justification.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Provide a concept study that evaluates MARMCs mission requirements, funding projections, and planning constraints. Analyze existing conditions, define goals, and evaluate technical, economic, environmental, energy, and safety impacts. Furnish the necessary management, technical services, labor, material, and equipment for the development effort for a MARMC future facility design. Provide MARMC with tangible results that will be used to deliver pertinent information in preparation for the NAVSEA Fiscal Year 2021 Program Objective Memorandum (POM-21) MILCON review cycle.

1. REQUIREMENTS

1.1 Milestone Schedule

1.1.1 Establish a schedule for project deliverables and milestones, based on completion percentage of the tasks below.

1.2 Project Phasing and Scope Modification

1.2.1 Develop options for separating the MILCON project P768 into multiple phases (between $30M and $50M each) and modify scope based on funding and options for relocation.

1.2.2 Provide liaison support with NAVFAC and DLA to determine long-term space usage, environmental remediation requirements, and, costs for the proposed project site.

1.2.3 Provide preliminary scoping details, cost estimates, square footages, and footprint calculations for up to three projects phases.

1.2.4 Collaborate with MARMC leadership, CNRMC, NAVFAC, NAVSEA, DLA, and other project stakeholders during project rescoping phases.

1.3 Update the DD Form 1391 and Supporting Documentation

1.3.1 Create new DD Form 1391 project in Electronic Project Generator (EPG) for either (a) up to three project phases in preparation for the NAVSEA Fiscal Year 20121 Program Objective Memorandum (POM 21) MILCON review cycle or (b) one project phase for the POM-21 MILCON review cycle and one project for congressional consideration.

1.3.2 Revise supporting documentation (e.g., economics analysis, basic facility requirements, business case analysis) for either (a) up to three project phases in preparation for the NAVSEA Fiscal Year 20121 Program Objective Memorandum (POM-21) review cycle or (b) one project phase for the POM-21 MILCON review cycle and one project for congressional consideration.

1.4 Annual MILCON Review Cycle

1.4.1 Develop briefs and supporting materials for the annual POM MILCON project review cycles for NAVSEA and NAVFAC.

1.4.2 If requested, attend and provide technical support MILCON briefings and associated meetings.

1.4.3 Based on the briefing and scoring results, provide a prioritized list of recommendations and strategies to improve project scoring for the subsequent POM year review cycle.

Delivery Address:

9727 Avionics Loop

Norfolk, VA 23511

Delivery Date:

31 March 2018