Statement of Work_Updated.doc
DOC document 126 KB Posted
- Attached to
- Heat Exchanger Rental Federal contract opportunity
- Solicitation number
- N3904020Q0167
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Request for Quotation_20Q0167.docx | DOCX document | |
| Statement of Work.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Heat Exchanger (Steam)
STATEMENT OF WORK
1. SCOPE
1.1. Heat Exchanger for ships test program
2. APLLICABLE DOCUMENTS
2.1. Issues of Publications - The following documents of the issue date in effect on the date of request for proposal form a part of this specification to the extent applicable, or as specified herein. Within the specification, they shall be referred to by their basic designation only.
2.1.1. Government
2.1.1.1. N/A
2.1.2. Nongovernment
2.1.2.1. N/A
2.2. Order of precedence - In the event of conflict between the text of this specification and that of the references cited above, the text of this specification shall take precedence. Nothing in this specification, however, shall supersede applicable laws or regulations unless a specific exemption has been obtained.
3. REQUIREMENTS
3.1. Shell and Tube Heat Exchanger (Steam Shell/Freshwater Tube)
3.1.1. Heat Exchanger shall be skid mounted; fully assembled and ready for turn-key operation.
3.1.2. 1,400,000 BTU/Hr Output
3.1.3. Water Flow of 50-100 GPM Required
3.1.4. Inlet Steam Conditions: 90 PSI
3.1.5. Desired Water Outlet Temperature: 100 Deg F
3.1.6. Steam (Shell Side) requirements:
3.1.6.1. Inlet Steam Pressure Gauge
3.1.6.2. Shell Mounted Vacuum Relief Valve
3.1.6.3. Shell Mounted Pressure Relief Valve
3.1.6.4. Inlet Steam rated Valve; Throttling type; 4”
3.1.6.5. Vendor Supplied/mounted Steam Rated Isolation Valves; (2) 1-1/2”
3.1.7. Freshwater (Tube Side) requirements:
3.1.7.1. Supply and return Flanges adapted to accept (2) 2-1/2" FW Lines
3.1.7.2. Supply Side Pressure and Temperature Gauges
3.1.7.3. Return side Pressure and Temperature Gauges
3.1.7.4. Freshwater side pressure Relief Valve Set @ 60 PSI
3.1.8. Performance similar or equal to Bell & Gusset Model #SU 165-4
4. RESPONSIBILITITES
4.1. Government
4.1.1. N/A
4.2. Contractor
4.2.1. For emission producing machinery as required by the State, the Contractor shall obtain permits for the duration of the lease and affix them onto the units.
4.2.2. ASME Pressure Vessel Name Plate Affixed and visible on Heat Exchanger.
4.3. Maintenance
4.3.1. Except for daily surveillance checks i.e. liquid levels, the Contractor is responsible for and shall perform all maintenance for the duration of the lease. Coordinate maintenance with Shipyard POC.
4.3.2. The equipment will be operating around-the-clock under a rigorous deployment performance schedule. Within twenty-four (24) hours (one-day) of initial notification of the need for repair, the Contractor shall have a knowledgeable and equipped technician on the job-site fully prepared to repair the rental equipment. The defective unit(s) shall be repaired within forty-eight (48) hours (two day) of initial notification or, if the original defective unit(s) cannot be made operational, replaced within seventy-two (72) hours (three days) of initial notification. If the equipment failure is not the fault of the Government, the Contractor shall bear all costs associated with its repair and/or replacement.
4.4. Training
4.4.1. N/A
4.5. Operator / Maintenance Manuals - Documentation will be located within a water proof case affixed to each machine. Minimally, the documentation shall consist of:
4.5.1.1. Technical Instructions (TIs) such as an Operations & Maintenance Manual, Controls Manual, and/or Electrical Manual with Schematics
4.5.1.2. Lifting & Handling the equipment with its padeye(s) Certification
4.5.1.3. Equipment Data Sheet (EDS)
4.5.1.4. Operating Instructions, if not in the TIs
4.5.1.5. Points of contact with telephone numbers for requesting emergency repair regardless of the time or type of day
4.5.1.6. Testing: Heat Exchanger Design and Testing to be In accordance with ASME Code. Pressure and Vacuum relief devices to be installed in accordance with ASME code.
5. DELIVERY / RETURN
5.1. Delivery - The machinery shall be in a fully-charged, fully-assembled, ready-to-use, and in a first-class-operating condition. Machines shall be functionally tested prior to its delivery. The machinery with its support equipment shall be delivered to the site on or prior to the request date. It is incumbent and the responsibility of the Contractor to either confirm or coordinate the date and time of delivery prior to each shipment via the Point-of-Contact (POC) as designated on the Contract and/or the Contracting Officer's Representative (COR). The Government can provide forklift services for removing machinery from Vendor’s transport during work hours. Documentation with Shipyard copies shall accompany each delivery.
5.2. Security - To be allowed onto a government Shipyard, personnel must be US citizens and in possession of appropriate personal identification. Proof of US citizenship may be necessary and can be required for access to the drydock. Allowable documentation of US citizenship is an official government issued Certificate of Birth or Naturalization (w/ raised seal & not a photocopy) or a US passport (can be expired). Vehicular access requires a non-expired personal Driver’s License and appropriate vehicle identification or registration. The transport vehicle must have the company’s name / logo prominently displayed. To gain access to the drydock environs, personnel must be escorted and possess / wear their own personal safety gear.
5.3. Inspection Criteria
5.3.1. Verifying supplied Heat Exchanger skid meets the requirements of Section 3 (Requirements) of this Statement of Work.
5.4. Packaging and Marking
5.5. Final Acceptance - Upon satisfactory completion of inspection and test of the equipment, the authorized Government Representative (Portsmouth Naval Shipyard, Code 990 Equipment Manager) will sign and forward the acceptance document(s) to Code 270.3 Production Control for completion. Unloading of equipment from Vendor’s transport does not signify acceptance.
5.6. Return - The Government will dismantle the equipment and provide a temporary storage location convenient for Contractor pick-up. The Government will notify the Contractor as well as the Contracting Office as to when the rental Item has been released and is available for pick-up. The last day of the rental period shall be the next normal workday after the Contractor has been so notified. The Contractor shall be responsible for shipping. The Government can provide forklift services during work hours for placing the equipment onto the vendor’s transport.
6. GENERAL
6.1. Response to Request - As part of the response to this request, descriptive literature shall be furnished in sufficient detail to show that the proposed design will meet these specifications. Vendor submittals shall include brochures of the model being submitted, assembly sketches with critical dimensions, sketches (with dimensions) of all tooling being provided, statements of compliance with specification, and performance statements with special instructions. Supporting information shall be organized and packaged by unit. If supporting information includes multiple models the vendor shall clearly state model number of proposed unit and redact all information not applicable to proposed unit.
6.2. Approved Models
6.2.1. Bell & Gusset Model #SU 165-4
Spec #: 2017-04 Rev: