Draft Performance Work Statement
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pipe Fitter Trade – FY 2015
PNS PERFORMANCE WORK STATEMENT (PWS)
1. INTRODUCTION
1.1. Background - Portsmouth Naval Shipyard (PNS), a field activity of Naval Sea Systems Command (NAVSEA), has a requirement for Pipe Fitter tasks and Management to support 688 Class Submarines. PNS is the Navy's center of excellence for fast-attack submarine maintenance, modernization, and repair. The Shipyard’s skilled and dedicated workforce safely delivers first-time quality on one of the most sophisticated warfighting platforms in existence – the nuclear-powered submarine.
1.2. Scope – Contractor shall provide pipe fitters and management services as defined in paragraph
2 of the PWS and in accordance with the manning table provided as attachment (A).
1.3. Place of Performance – Shipboard and back-shop work areas at Portsmouth Naval Shipyard, Kittery (i.e., Seavey Island), Maine.
1.4. Period of Performance and Level of Effort - services shall be provided in accordance with below schedule:
1.4.1. Base Period: Starting contract award and lasting for 11 weeks. The Base level of effort is
6,784 straight time labor-hours and no more than 704 overtime hours (total hours – 7,488 hours). Overtime hours will be authorized as deemed necessary by PNS.
1.4.1.1. 11 weeks from contract award, 5 days per week, Monday through Friday, excluding federal holidays, at 8 hours per day.
1.4.1.2. 4,240 Total Straight time Day Shift Hours -- (10) Pipe Fitters
1.4.1.3. 2,544 Total Straight time Afternoon Shift Hours -- (6) Pipe Fitters
1.4.1.4. 440 day shift overtime hours and 264 night shift overtime hours for 704 Total
Overtime Hours.
1.4.1.5. Necessary Supervision as determined by the contractor.
1.4.2. Option 1: Starting the day after the end of the Base Period and lasting for 13 weeks. The level of effort for Option 1 is 7,936 straight time labor-hours and no more than 832 overtime hours (total hours – 8,768 hours). Overtime hours will be authorized as deemed necessary by PNS.
1.4.2.1. 13 weeks from contract award, 5 days per week, Monday through Friday, excluding federal holidays, at 8 hours per day.
1.4.2.2. 4,960 Total Straight time Day Shift Hours -- (10) Pipe Fitters
1.4.2.3. 2,976 Total Straight time Afternoon Shift Hours -- (6) Pipe Fitters
1.4.2.4. 520 day shift overtime hours and 312 night shift overtime hours for 832 Total
Overtime Hours.
1.4.2.5. Necessary Supervision as determined by the contractor.
1.4.3. Option 2: This option authorizes an additional 400 hours of overtime throughout the contract periods of performance.
1.4.4. The work schedule is Monday through Friday.
1.4.4.1. Day shift hours of work are 0700-1530.
1.4.4.2. Afternoon shift hours of work are 1500-2330.
1.4.4.3. Hours of work outside these windows may be required to support specific tasking. PNS will provide as much advanced notice as possible of the need to support work outside the above hours.
2. CONTRACTOR REQUIREMENTS
2.1. PIPE FITTERS
2.1.1. Tasks - The contractor shall provide Pipe Fitters (Trade Skill PF, Designator P1) capable of performing pipe fitting tasks identified below in support of various submarine overhauls.
2.1.1.1. Fabricate, install, remove, modify and repair piping/hoses in the shop and aboard ship.
2.1.1.2. Remove, fabricate, assemble, or reinstall various Submarine non-nuclear piping systems including pressure joints.
2.1.1.3. Fit-up and prepare various system piping for cutting, welding, or brazing (e.g.
sanitary, potable water, cooling piping systems).
2.1.1.4. Template, fabricate and install plumbing and high-pressure air systems piping.
2.1.1.5. Work from templates, manufacturing and installing parts and assemblies with reference to base lines, centerlines, frame lines, and other reference points.
2.1.2. General Qualifications –
2.1.2.1. Contractor shall maintain:
2.1.2.1.1. A Personal Fall Arrest System (PFAS) program in accordance with 29 CFR 1915 – Subpart I.
2.1.2.1.2. A confined/enclosed space entry program in accordance with 29 CFR 1915 – Subpart B.
2.1.2.1.3. The contractor shall provide copies of the training curriculums for PFAS and Confined/Enclosed space with their proposal.
2.1.2.2. All personnel reporting shall meet the following criteria:
2.1.2.2.1. Shall have attained journeyman status in the pipe fitting trade with at least three (3) years experience, a minimum two (2) years of which includes repair work on U. S. Navy vessels.
2.1.2.2.2. Shall be able to accomplish typical tasks as outlined in paragraph 2.1.1 above.
2.1.2.2.3. Shall be trained to handle trade-related hazardous substances.
2.1.2.2.4. Shall be qualified to work in confined spaces such as tanks, voids, and any other areas that require gas-free controls.
2.1.2.2.4.1. Training shall be in accordance with 29 CFR 1915 – Subpart B. See
Section (2.2) for more details on confined/enclosed space requirements and contracting options.
2.1.2.2.5. Shall be qualified to wear safety harnesses and work from scaffolds/platforms where drop off will be greater than 5 feet IAW 29 CFR 1915 (Subpart I) and be trained in fall protection regulations.
2.1.2.2.6. Shall be trained to wear required personal protection equipment (PPE) when designated or required and be trained in hearing conservation and eye safety awareness.
2.1.2.2.7. Shall be capable of performing work in accordance with written technical work documents.
2.1.3. Trade Specific Requirements - The contractors’ employees shall provide their own personal hand tools and any other work apparel typically provided by their employer (e.g.
coveralls, tyvek suits, and leather palmed gloves).
2.1.3.1. In addition, the personnel fulfilling this contract must meet the following trade specific requirements:
2.1.3.1.1. Shall be qualified in using precision measuring tools such as micrometers, depth gauges, and calipers while performing close tolerance work.
2.2. Confined/Enclosed Space Details and Options
2.2.1. For execution of this contract, the contractor’s personnel will be assisting PNS personnel executing work in confined spaces. Since PNS will already be performing competent person/gas-free services for the workspaces, PNS is willing to extend its competent persons’ services and make them available to the contractor’s employees rather than have the contractor perform duplicate monitoring. The framework for the Navy/PNS providing competent personnel/gas-free services is provided in NAVSEA S6470-AA-SAF-010, Paragraph 2-8 (Contractor Operations). ). The contractor will either (1) be required to utilize PNS employees designated as GFE competent persons in executing work in confined spaces, and entering into the appropriate MOA formalized after contract award or (2), indicate in the contractor’s bid proposal what alternative to ensure employee safety for work in confined/enclosed spaces the contractor contemplates.
2.2.2. If the contractor chooses to utilize Navy-provided competent person/gas-free services, a
Memorandum of Agreement will be formalized after contract award to ensure clear delegation of responsibilities as required by NAVSEA S6470-AA-SAF-010. PNS will provide a copy of its confined/enclosed space entry program to the contractor, and the contractor will be required to make their employees familiar with our program prior to assigning them to PNS. A sample Memorandum of Agreement will be provided by the contracting officer upon request. Some examples of responsibilities provided to the contractor by NAVSEA S6470-AA-SAF-010 are:
2.2.2.1. Ensure the Navy competent person is on a list provided by PNS.
2.2.2.2. Ensure all its employees who may enter confined spaces are trained to entry procedures in accordance with 29 CFR 1915.12(d) and the PNS confined/enclosed space program. The contractor shall maintain the training records at least 3 months beyond the completion date of the contract.
2.2.2.3. Ensure all contractor employees comply with confined space entry procedures.
2.2.3. If the contractor opts not to use Navy-provided competent person/gas-free services they then must provide their own competent person/gas-free services in accordance with Occupational Safety and Health Manual VOL 2 Part I Chapter 1, NAVSEA S6470-AA-SAF- 010, and 29 CFR 1915 – Subpart B.
2.3. MANAGEMENT REQUIREMENTS
2.3.1. Copies of the contractor’s training curriculum for confined space, respirator, and fall protection programs to be submitted as part of the contractor proposal.
2.3.2. At least 1 week prior to a personnel’s travel date, the contractor shall supply PNS with copies of training records and documented trade/work experience certifying the personnel have met the requirements under paragraph (2.1) above. These training records for each individual shall be provided to PNS Training Department, Code 900T. The POC is Randy Winsor (207) 438-2537; Fax (207) 438-1188.
2.3.3. Once contractor personnel are assigned, it is expected that change-out of personnel will not occur without prior negotiation. If the contractor switches out personnel provided as part of this contract, new personnel will not be considered as providing hours until after they have completed the initial required training.
2.3.4. The contractor’s supervisor(s) is/are the liaison between contractor personnel and PNS
Supervisors. The contractor’s supervisor will manage worker assignments to ships, shifts of work, discipline, safety, rewards, promotion, attendance, time-off (i.e. sick and/or annual leave) and work performance. The contractor shall provide adequate supervision to oversee the assigned personnel and ensure the proper execution of the typical tasks described herein. PNS shall be responsible to provide all project management, quality assurance and engineering support that may be required in the assigned tasking.
2.3.5. In the event of injuries sustained in the performance of duty, contractor employees may receive medical aid from shipyard first responders but shall, if necessary, receive secondary aid and/or evaluation from private providers. PNS Managers and the PNS Technical POC must be immediately informed of any injuries or near misses that occur by contractor management. In the event of any long-term restriction of work availability PNS will require a replacement for the injured personnel.
2.3.6. Contractor management shall:
2.3.6.1. Provide overall management, oversight and supervision (and/or lead workers) to effectively and safely manage the work of this order.
2.3.6.2. Resolve contractor personnel problems including, but not limited to conflict resolution and administrative actions affecting the contractor’s employees.
2.3.6.3. Manage assignment of contractor personnel to shifts and projects.
2.3.6.4. Ensure daily onboard counts of employees are reported to the PNS Contracting
Officer’s Representative or Contract POC at least weekly.
2.3.6.5. Maintain accurate tracking of hours worked by personnel.
2.3.6.6. Maintain total program oversight
3. CONTRACTOR FURNISHED MATERIAL
3.1. The contractor’s employees shall provide their own personal hand tools and any other work apparel typically provided by their employer (e.g. coveralls, tyvek suits, and leather palmed gloves).
3.2. The contractor’s personnel shall provide their own personal protection equipment (e.g. safety shoes, helmets and eye protection).
4. PORTSMOUTH RESPONSIBILITIES
4.1. PNS will provide specific written technical work instructions (i.e. Task Group Instructions) and shift-to-shift project assignments. Since PNS requires our government supervisors to brief government workers prior to starting each job, the contractor’s workers may be asked to be present for those discussions.
4.2. The contractor’s employees will be provided access to PNS Tool Cribs to use government tooling/equipment. Contractor employees are responsible to return tools and to have a “clean” badge prior to departing PNS. Broken, lost or missing tooling will be billed to the contractor.
5. APPLICABLE TECHNICAL WORK INSTRUCTIONS
5.1. Technical Work Documents issued by Portsmouth Naval Shipyard
5.2. 29 CFR 1915 – Occupational Safety and Health Standards for Shipyard Employment
5.3. OSHA Directive – CPL 02-00-133 Shipyard “TOOL BAG” Directive
5.4. NAVSEA S6470-AA-SAF-010 Naval Maritime Confined Space Program
5.5. NSTM S9086-VD-STM-010/Ch-631 Rev 3 –Preservation of Ships in Service
5.6. 29 CFR 1910.134 Respiratory Protection
5.7. The Contractor shall comply with all Federal, State, and Local environmental and safety laws and regulations.
6. SECURITY/BASE ACCESS
6.1. At a minimum, all personnel shall be United States citizens and shall possess a Department of Defense final-adjudicated Personal Security Clearance at the confidential level or higher, in accordance with Attachment B (DD Form 254) for performance on this contract. Failure of ability to obtain a PNS red badge will be cause to dismiss personnel from fulfilling this contract.
6.2. Contractors must have Rapid Gate credentials for access to Portsmouth Naval Shipyard.
Contractors and any subcontractors must submit contract DD-254 to Portsmouth Naval Shipyard Security Department Code 1700 for access requirement verification prior to arrival.
6.3. Contractors/subcontractors shall submit Visit Requests via the Joint Personnel Adjudication
System (JPAS) to SMO 39040 for visitor clearance verification. Visit requests submitted by other means will not be accepted without Facility Security Officer signed verification as to the level of security clearance granted to each employee on the visit request. Additionally, the contractor must provide a copy of Visit Request to Bruce Thorner or Richard Rogers – Code 900R (Fax 207-438-1298) at least 2 weeks prior to personnel traveling for inclusion into other PNS IT systems.
7. DELIVERABLES
7.1. Copies of training records for each individual as identified in paragraph (2) above shall be provided to PNS Training Department at least 1 week prior to personnel traveling. Training POC is Randy Winsor (207) 438-1592; Fax (207) 438-1188.
7.2. Copies of training curriculum for confined space, respirator, and fall protection programs to be submitted as part of the contractor proposal.
7.3. The contractor shall provide clearance validation (i.e. copy of clearance message) to Bruce Thorner or Richard Rogers (Fax 207-438-1298) prior to personnel traveling.
7.4. Contractor shall attend weekly status meetings with Code 900R TPOC and PNS Contracting
Officer’s Representative (COR) to discuss contract execution and performance
7.4.1. The contractor shall prepare weekly status updates in accordance with Attachment C for review at these meetings and submitted electronically to the Code 900R TPOC, PNS Business Office Representative, and COR.
7.4.2. The weekly status meetings may be reduced to a biweekly cadence if mutually agreed upon by the contractor, Code 900, and COR.
8. CLASSIFIED MATERIAL
8.1. None
9. PLACES OF PERFORMANCE
9.1. The place of performance will be Portsmouth Naval Shipyard, Kittery, Maine (i.e. Seavey Island).
10. CONTRACTING OFFICER REPRESENTATIVE (COR)
10.1. The COR for this delivery order is TBD.
11. TECHNICAL POINT OF CONTACT (TPOC)
11.1. The TPOC for this Delivery Order is Mr. Richard Rogers, PNSY Code 900R, Kittery, ME
(207) 438-2258.
12. ATTACHMENTS
12.1. Attachment A – Manning Table
12.2. Attachment B – DD254
12.3. Attachment C – Status Report Requirements
Manning Table
PNS
TS
TSD Title # Shift
Est.
Start
Est.
Complete
Total # Work Days
Straight Time Hours
Over time
Hours
Base Period of Performance
PF P1 Pipe Fitter 10 AM 17 Aug 2015 30 Oct 2015 55 4,240 440
PF P1 Pipe Fitter 6 PM 17 Aug 2015 30 Oct 2015 55 2,544 264
Supervision As determined by contractor requirements
Base Straight Time Hours = 6,784 Base Overtime Hours = 704 Base All Hours = 7,488
Option #1 Period of Performance
PF P1 Pipe Fitter 10 AM 31 Oct 2015 29 Jan 2016 65 4,960 520
PF P1 Pipe Fitter 6 PM 31 Oct 2015 29 Jan 2016 65 2,976 312
Supervision As determined by contractor requirements
Option 1 Straight Time Hours= 7,936 Option 1 Overtime Hours=832 Option 1 All Hours=8,768
Option 2 Overtime Hours = 400
Total Straight Time Hours=14,720 Total Overtime Hours = 1,936 Total All Hours = 16,656
Attachment A
STATUS REPORT REQUIREMENTS
1. The monthly status report shall include the listed items:
* Project/Task number
* Task status
* Man-hour information (Include Labor Category, Hours expended for the period, and the cumulative total
* Funded Amount/Total estimated Cost
* Funds Expended To-Date
* Percentage of Funded Amount Spent To-Date
* Percentage of Completion To-Date
* Scheduled Completion Date
* Estimated Completion Date
* Remarks, including any disconnects between scheduled completion date, estimated completion date, and funds expended to date.
2. The format of the report shall be to the contractor’s discretion but shall include a graphical representation of the contractor’s progress. An X-Y graph shall be used with the X axis representing time and the Y axis representing manhours. The contractor shall plot the estimated/projected values and the actual values on one graph. Ensure that there is a date, title, and Project/Task number on the graph.