This document is a Memorandum that explains the justification for using other than full and open competition for an acquisition under the simplified acquisition threshold for the procurement of replacement security floodlights for the USNS Fall River EPF 4 vessel.

The memorandum states that the required item is critical ship equipment, the failure of which poses a hazard to the ship, the crew, or the environment. It also indicates that per the Military Sealift Command's standardization initiative, only the specified Phoenix Lighting floodlight model will satisfy the government's needs for additional units or replacement parts. The required delivery date is September 29, 2024. The anticipated dollar value of the procurement is not provided. The related federal contract opportunity is a solicitation issued by the Department of the Navy Military Sealift Command for the USNS Fall River floodlights.

View the file

Other files for this federal contract opportunity

Other files attached to USNS FALL RIVER - FLOODLIGHTS, newest first.
File Type Posted
Combined_Synopsis_Solicitation.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Ver 2.0 (01 July 2018)

Date: Aug 27, 2024

MEMORANDUM

Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION UNDER

THE SIMPLIFIED ACQUISITION THRESHOLD

Ref: (a) USNS FALL RIVER EPF 4 PR Number(s): __________________________________

I. BACKGROUND:

1. In considering the references, FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contacting Officers may solicit from one source if the Contracting Officer determines that, under the circumstances of the contract action, only one source is reasonably available (e.g., urgency, exclusive licensing, brand-name, or industrial mobilization).

2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition because only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.

II. DESCRIPTION OF ITEM OR SERVICE:

1. Provide a description of the item or service required, to include

a) The name of the required source or brand name

PHOENIX LIGHTING PRODUCTS INC______________________________

b) The required delivery date/period of performance and

RDD: 9-29-2024_ __________________________

c) Its intended use.

Replacement of existing deteriorated security floodlights.

2. List the source(s) or known vendor(s) who are able to provide the above described item or service.

Phoenix Lighting Products Inc. Jo-Kell Inc. Beck Electric.

III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION IS BASED

ON THE FOLLOWING (select all that apply):

A. _____ Only one responsible source (select all that apply):

1. _____ RESTRICTIVE RIGHTS: the source has established proprietary rights, limited rights in data, patent rights, copyrights, or secret processes in the item or service.

a. Explain what is subject to the restrictive rights.

2 Ver 2.0 (01 July 2018)

b. If drawings are included, who is identified as “owning” the drawings.

2. _____ EXCLUSIVE LICENSING AGREEMENTS: The item or service is only available from the Original Equipment Manufacturer (OEM), or there is ONLY ONE authorized distributor or technical representative for the OEM.

a. Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.

b. Identify the distributor / authorized technical representative for the item or service.

Provide evidence of the exclusive licensing agreement as an attachment to this document.

(NOTE: If there is more than one distributor / authorized technical representative, then use Part B – Brand Name.)

3. __XX___ OTHER REASON:

a. _XX____ CRITICAL SHIP EQUIPMENT: The required item is critical ship equipment, the failure of which poses a hazard to the ship, the crew or the environment.

i. SMS Procedure Number: ___________________________

b. _XX____ STANDARDIZATION / BRAND NAME: Per MSCs standardization initiative, only the specified make/model of the equipment/parts will satisfy the Government’s needs for additional units or replacement items.

i. Identify Make / Model Number(s): _ Phoenix Lighting, Floodlight EM3-HI-WF-

120-277-50K-B2-316SS

ii. Identify other vessels with this Make / Model:

_All EPF’s______________________________________________

c. _XX____ FORM, FIT, AND FUNCTION: Item is direct replacement parts / components for existing equipment and must be compatible in terms of form, fit, and function with existing equipment / configurations.

i. Identify Make / Model of existing equipment:

3 Ver 2.0 (01 July 2018)

____Phoenix Lighting, Floodlight EM3-HI-WF-120-277-50K-B2-316SS

ii. Describe how the equipment must be compatible with the existing configuration.

These are direct replacements for existing units which have exceeded life expectancy and deteriorated to inoperable state.

d. _____ OTHER:

4. _____ UNUSUAL AND COMPELLING URGENCY: The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits. Urgent requirements are supplies or services that will result in work stoppage, or are mission critical and the routine processing time would injure the Government. The determination that the procurement for the above is an urgent and compelling requirement is based on the following:

a. Date on which the requirement was identified: ______________________________

b. Required delivery date / Period of Performance: _____________________________

c. If the difference between a. and b. is more than one week, explain the delay in submitting t he requirement.

d. Estimated production lead time: ______________________________

e. Explanation of why delivery / commencement of services by the date required is needed: (explain the impact to the mission, any special circumstances or conditions, etc.)

f. CASREP Number: _________________________________________

IV. ANTICIPATED DOLLAR VALUE OF PROCURMENT: $XXX.XX______________________