SOW_BURLINGTON_Comm.doc
DOC document 90 KB Posted
- Attached to
- USNS BURLINGTON Comms Service Federal contract opportunity
- Solicitation number
- N3220519Q4695
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 19Q4695_SOW_BURLINGTON_Comm.doc | DOC document | |
| N3220519Q4695_Amendment_0001.pdf | ||
| Solicitation_N3220519Q4695.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS Burlington
( EPF 10 )
| COMMUNICATION AND NAVIGATION |
| CONTRACT NO. 19-008 |
| ITEM NO. 19-008 |
| CATEGORY "A" |
| 2019-01-08 |
COMMS FCT Support
1.0 ABSTRACT
1.1 This item describes technical services for Communications Systems to support FCT Mock and Final Contract Trials (FCTs).
2.0 REFERENCES:
2.1 EL-4 Internal Communications
2.2 CC-6 PBX-JHSV
2.3 CC-6A Bridge to Bridge
2.4 IS-15 LAN Drop Connectivity
3.0 ITEM LOCATION/DESCRIPTION:
3.1 Locations:
3.1.1 Wheel House
3.1.2 Various; throughout ship
3.2 Quantity:
3.2.1 Various
4.0 GOVERNMENT FURNISHED MATERIAL/EQUIPMENT/SERVICE: NONE
5.0 NOTES:
5.1 Performance Period:
5.1.1 17 - 21 June 2019, FCT walk through
5.1.2 08 - 12 July 2019, FCT Mock Trial
5.1.3 28 July - 02 August 2019, FCT Test with INSURV
5.2 Location of Work:
5.2.1 JEB-Little Creek, Virginia Beach.
5.3 Port Engineer:
5.3.1 Jonathan Twiford P.E.
Cell:
757-756-6362 Email:
jonathan.twiford1@navy.mil
5.4 Contact the Port Engineer for details and requirements concerning access to an MSC vessel.
5.5 Contractor is required to submit personnel on the EPIC spreadsheet. To gain access to MSC vessel's on the East Coast, contractors must submit an EPIC request to MSFSC(underscore)EPIC(underscore)EAST(at)navy(dot)mil MSFSC_EPIC_EAST@navy.mil.
5.6 Contractors, shall allow 3 business days (5 for NASSCO, OCONUS, & Earl NJ) for processing of all requests. EPIC will take up to 48 hrs to process, the request must be approved by EPIC before access can be sent to the facility for approval, access will not be guaranteed without approval from EPIC.
5.7 Contractor is responsible to obtain access to JEBLC Base and Pier 11.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.
7.0 STATEMENT OF WORK REQUIRED:
7.1 Provide the service of one (1) Authorized representative during the performance periods stated in 5.1. The representative shall be a Sr. Service Tech Rep Experienced with Joint Ship Computing Environment (JSCE), JETS, JWICS, JWIVCS, JRSS, and the JHSV Class. All work shall be performed by an authorized Service Representative. Representative to be onboard by 0800.
7.2 Service Representative shall be onboard for three (3) days during FCT Mock. Two (2) days when the ship is pier side and one (1) day underway with the ship from 0600 to 1800. The ship will return to the same port at JEBLC and same day.
7.3 Service Representative shall be onboard for three (3) days during FCT Test. Two (2) days when the ship is pier side and one (1) day underway with the ship from 0600 to 1800. The ship will return to the same port at JEBLC and same day.
7.4 Qualified Representative will provide support and training for the ship’s crew during pre-underway and operational assistance during underway testing for Final Contract Trials. Support will include oversight and testing of equipment required to demonstrate to MOCK and NAVY INSURV Board safe operation of equipment.
7.5 Qualified Representative will help expedite any emergent material needs to support scheduled underway operations.
7.6 Qualified Representative will provide other necessary services related to operation and troubleshooting during Final Contract Trials.
7.7 Contractor shall use References 2.0 as guidance.
7.8 Contractor shall furnish tools and test equipment.
8.0 GENERAL REQUIREMENTS: None additional.