SYNOPSIS_N32205-17-R-4206.docx
DOCX document 37 KB Posted
- Attached to
- T-AKE Class Emergency Board Bus Tie Circuit Breaker Replacement Federal contract opportunity
- Solicitation number
- N32205-17-R-4206
About this file
Synopsis N32205-17-R-4206
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N32205-17-R-4206.docx | DOCX document | |
| J&A_N32205-17-R-4206_FBO_Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Military Sealift Command Synopsis
1. Action Code: Presolicitation
2. Date: 2 February 2017
3. Year: Fiscal Year 2017
4. Contracting Office Zip Code: 23511
5. Classification Code: 1915
6. Contracting Office Address: 471 East C Street Norfolk, VA 23511
7. Subject: T-AKE Class Emergency Board Bus Tie Circuit Breaker Replacement
8. Proposed Solicitation Number: N32205-17-R-4206
9. Closing Response Date: TBD
10. Contact Point or Contracting Officer: Donnie Leger, donnie.leger@navy.mil, (757) 443-5900
11. Contract Award and Solicitation Number: Solicitation N32205-17-R-4206, Award N32205-17-C-4206
12. Contract Award Dollar Amount: TBD
13. Contract Line Item Number TBD
14. Contract Award Date: TBD
15. Contractor: TBD
16. Description: Military Sealift Command intends to award a sole source firm fixed price contract to Point Eight Power procure twenty four (24) ABS approved bus tie circuit breakers, twenty four (24) switchboard modification kits, and eight (8) spare circuit breakers to replace existing bus tie circuit breakers on T-AKE 1, and T-AKE 3 through T-AKE 9. Requirement will include one option for the USNS SACAGAWEA.
a. Unit of issue: N/A
b. Destination information: Norfolk, VA
c. Delivery schedule:
| Period |
| Deliverable |
| Shipsets |
| Quantity |
| Date of Commencement |
| Date of |
Completion
| Base Period |
| Update of Protective Device Coordination |
| N/A |
| N/A |
| Upon contract award |
| 30 days after contract award |
| Update of Switchboard Control Wiring Diagram |
| N/A |
| N/A |
| Upon contract award |
| 30 days after contract award |
| Update of Switchboard Assembly and Details Drawing |
| N/A |
| N/A |
| Upon contract award |
| 30 days after contract award |
| MSC Design Review |
| N/A |
| N/A |
| 30 days after contract award |
| 45 days after contract award |
| ABS Design Review |
| N/A |
| N/A |
| 60 days after contract award |
| 90 days after contract award |
| Circuit Breakers |
| 8 |
| 24 |
| Upon completion of MSC and ABS Design Review |
| 6 months after contract award |
| Spare Circuit Breaker |
| 8 |
| 8 |
| Upon completion of MSC and ABS Design Review |
| 6 months after contract award |
| Modification Kit |
| 8 |
| 24 |
| Upon completion of MSC and ABS Design Review |
| 6 months after contract award |
| Tech Manual Change Pages |
| 8 |
| 23 |
| Upon completion of MSC and ABS Design Review |
| 6 months after contract award |
d. Procedures: N/A
e. Anticipated Award Date: 10 March 2017
f. The solicitation will be made available on www.fbo.gov on or about 7 February 2017
g. Set-aside Status: Other Than Full and Open
V1.1 (17 June 2014)
File details come from the government source that posted it. Updated .