Attachment_A-SOW-N3131A19PR011NV-YAP.pdf
PDF 37 KB Posted
- Attached to
- Logistics Support Services Federal contract opportunity
- Solicitation number
- N3131A19PR011NV
About this file
Statement of work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTACHMENT_C-PRICING_SCHEDULE-N3131A19PR011NV-FST_YAP_SURVEY_.xlsx | XLSX spreadsheet | |
| Attachment_B_Terms_and_Conditions_N3131A19PR011NV.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 2019 CONDEPTSOP 4200.03
STATEMENT (SOW)
FOR
YAP, FSM Survey and
Fleet Survey Team
06/12/2019
STATEMENT OF WORK
TABLE OF CONTENTS
SECTION PAGE
1 DESCRIPTION OF SERVICES 3/6
2 GENERAL INFORMATION 7
3 APPENDICES 8
1. DESCRIPTION OF SERVICES. The contractor shall provide all management, tools, supplies, equipment, and labor necessary to operate and maintain logistical support services for U.S. Navy Forces.
1.1. BASIC SERVICES. To obtain logistics support services for U.S. Navy Forces, and other designated personnel, operating on Yap, Federated States of Micronesia (FSM). It is essential that all required services be coordinated with Team Lead and in place prior to arrival of Fleet Survey Team (FST) personnel in country unless otherwise specified.
Location: Yap, FSM
Date(s): 10 JUL 2019 to 03 AUG 2019
1.2. SPECIAL REQUIREMENTS. The contractor may proceed, if necessary, one week prior to Period of Performance date for mobilization purposes only. All Airline tickets must be purchased as refundable tickets.
1.3. TOW VEHICLE WITH ENGLISH SPEAKING DRIVER – YAP
Provide tow vehicle with a capacity of at least 10 tons and ability to safely and securely transport survey vessel / 3-axle vessel trailer configuration with length approximately 13m and width 2.67m, with qualified English-speaking operator / driver. This platform will be used to transport the vessel / vessel trailer between Yap International Airport and Yap Sea Port Authority. Expeditionary Services Contractor (ESC) will provide means of loading, unloading, and securing survey vessel / vessel trailer for transit. The means of towing may be accomplished by truck (capable of towing at least 18,000 lbs.) with the proper receiving hitch (pintle-type tow hitch able to connect to lunette ring with a diameter of 7.6cm), a forklift (no less than 10K capacity) for which FST will provide the adapter. Cost should include driver/operator, fuel, loading/unloading vessel/boat trailer, repair/maintenance during transit, tolls and insurance. This platform will:
1) Tow the survey vessel/equipment on or about 10 JUL 2019 from Yap International airport to Yap Sea Port.
An FST field representative will provide ESC 24-hour advance notice of the exact date and time equipment is expected to be required. Some variance is expected with flight arrival times.
2) Truck will transport vessel/trailer from Yap Sea Port to Yap International Airport and/or on to flight line for loading onto C-130 on or about 02 AUG 2019.
An FST field representative will provide ESC 24-hour advance notice of the exact date and time equipment is expected to be required. Some variance is expected with flight arrival times.
Quantity – One (1) Tow Vehicle for transporting boat with English-speaking driver, including loading/unloading equipment such as crane, telehandler or truck.
Period of Performance –10 JUL 2019, 02 AUG 2019 (2 days)
Location –Yap, FSM
1.4. CARGO TRUCK WITH ENGLISH SPEAKING DRIVER – YAP
Provide a covered and lockable cargo truck, box truck, or equivalent with English-speaking driver.
Platform should be able to transport up to four (4) pallets (approximately 40” x 48”) weighing up to 350 lbs. (160kg) each and up to 20 pieces of luggage. The palletized equipment can be broken down into smaller sized component pieces for fitting into the truck if necessary. Cost should include driver, fuel, tolls and insurance. This platform will:
1) Receive on-load of palletized equipment and luggage via 10K telehandler and FST personnel at Yap International Airport and transport equipment and luggage to designated storage area and/or Yap Sea Port Facility on or about 10 JUL 2019.
2) Transport equipment and luggage from Yap Sea Port to Yap International Airport on or about
02 AUG 2019.
An FST field representative will provide ESC 24-hour advance notice of the exact date and time equipment is expected to be required. Some variance is expected with flight arrival times.
Quantity – One (1) cargo truck with English-speaking driver
Period of Performance – 10 JUL 2019, 02 AUG 2019 (2 days)
Location – Yap, FSM
1.5. 10K TELEHANDLER OR FORKLIFT AND QUALIFIED OPERATOR – YAP
Provide no less than an 10K telehandler, forklift, or similar equipment and qualified English-speaking operator to offload / load the boat/trailer and equipment pallets from/to rear of military C-130 aircraft, which is anticipated to land at the Yap International Airport on or about 10 JUL 2019 (arrival/offload) and on or about 02 AUG 2019 (departure/load). The forks should be a minimum of 5 ft (1.5m) long and fork extensions are allowed. The mast must not exceed 10 ft (3.0m) in height when the forks are 6 ft (2.0m) off the ground to avoid contact with the aircraft tail. Offloading and loading of the boat/trailer will be accomplished by using a forklift hitch adapter (supplied by FST) to connect the trailer to the forklift and then pushing and pulling the boat/trailer from the C-130. Cost should include operator, fuel, and insurance. The forklift will:
1) Offload the palletized equipment from C-130 and load onto equipment transport truck, then offload the boat/trailer from C-130 and tow to Yap Sea Port on or about 10 JUL 2019.
2) Load boat/trailer into C-130, then load the palletized equipment onto C-130 on or about 02
AUG 2019.
An FST field representative will provide ESC 24-hour advance notice of the exact date and time equipment is expected to be required. Some variance is expected with flight arrival times.
Quantity – 10K Telehandler or Forklift and Qualified Operator
Period of Performance – 10 JUL 2019, 02 AUG 2019 (2 days)
Location – Yap, FSM
1.6. PORT SERVICES – HULL CLEANING – YAP
Provide hull cleaning service for survey vessel while out of the water at the Yap Sea Port facility on or about 01 AUG 2019. FST will communicate with ESC at least 48 hours prior to date required if needed before 01 AUG 2019. Hull cleaning service should remove barnacles and sea life growth from hull via hand scrapers and/or brushes or pressure washer.
Quantity – One (1) hull cleaning for survey vessel
Period of Performance – 01 AUG 2019 (one day)
Location – Yap, FSM
1.7. UNLEADED FUEL (87 OR HIGHER AUGANE / NO ETHANOL) FOR BOAT – YAP
Provide approximately 1,200 gallons (4,542 liters) of unleaded gasoline delivered to Yap Sea Port facility during survey project. The price should include delivery costs, fuel containers, and spill containment pads. Fuel will need to be delivered in approximately 200 gallons increments every four (4) days from 11 JUL 2019 through 01 AUG 2019. Survey will require an estimated 6 replenishments. FST's team leader will inform ESC 24 hours in advance of fuel amount needed and delivery time. Survey vessel will be in the water at Yap Sea Port 11 JUL 2019 through 01
AUG 2019.
ESC will provide a delivery system to pump fuel from fuel delivery container to FST’s survey vessel and portable fuel containers for portable generators. Delivery system will include a pump, meter to measure quantity, hose with sufficient length to reach from delivery container to survey vessel (approx.15-20 meters long), method to determine if fuel contains contaminants (i.e. water), and fuel dispensing nozzle that fits inside a ¾ inch fuel tank opening.
Fuel will be tested for the presence of water. If water is present, fuel will be rejected and FST will not be charged for fuel, its delivery, nor disposal. Delivery charges, access fees, and other related costs to deliver and dispense fuel will be the ESC's responsibility. Fuel should be ethanol free.
Coordination with Yap Sea Port security personnel is required. ESC is responsible for any permits or permission required to conduct fueling operations at the Yap Sea Port area.
This is an estimate of the fuel to be used on this survey. FST will not be responsible for payment of fuel not used.
Quantity – 1,200 Gallons (4,252 liters) total; provided in 6 deliveries x 200 gallons
Period of Performance – 11 JUL 2019 to 01 AUG 2019 (22 days)
Location –Yap, FSM
1.8. SURVEY SERVICES - VESSEL / ENGINE / BOAT REPAIR AND MATERIALS
ESC shall provide qualified technicians to inspect and repair vessel outboard engines (250HP Honda), vessel generator (Westerbeke) and procure miscellaneous materials to effect repairs if required. Materials to be procured could include but is not limited to: boat and engine parts, labor, and consumables. Total price of materials and services will not exceed $5000.00. ESC shall provide detailed receipts for all authorized procurements to the FST OIC, and in writing prior to procurement. All fabricated material remains property of the US Government.
1.9. HYDROGRAPHIC SURVEY SUPPORT REQUIREMENTS MATERIALS:
ESC shall procure miscellaneous materials to assist in survey tasking as directed by FST OIC, including but not limited to: hardware, metal piping, and lumber. Total price of materials will not exceed $1000.00. ESC shall provide detailed receipts for all authorized procurements to the FST OIC, and in writing prior to procurement. All fabricated material remains property of the US Government (Not to exceed $1,000.00).
1.10. CONTINGENCY SITUATIONS/MISSION OPERATIONS
Contingency situations (natural disasters, military peacetime and wartime contingency operations/exercises, serious accidents, civil disturbances, major mobilization or repatriation of non-combatants) may necessitate that the ESC be flexible in arranging different levels of support and service operational hours. The ESC shall respond to contingency situations and revise priorities as directed by the COR. Un-avoidable, and oftentimes last-minute delays and changes in the arrival dates and times of the NALO C-130 flights which transport the boat, equipment, and some personnel may necessitate that the ESC be flexible in arranging different days and/or operational hours of service. Hurricanes and other natural disasters can occur in this location. If the ESC cannot accomplish normal activities due to activation or exercise of any contingency plan, the ESC shall not be held liable for non-support of lower priorities. The COR will determine the lower priorities that can be temporarily relaxed in contingency situations. If appropriate, the ESC shall be reimbursed for contingency operations requiring a higher level of response and resources.
The ESC shall submit a Request for Equitable Adjustment detailing the impact resulting from the incorporation and operation of such contingency actions prior to the beginning of the contingency operations. In the event that operations are curtailed as a result of weather emergencies or other unplanned mission-related events, ESC personnel may be considered non-essential personnel and thus, not required to be at the work site. They may, however, be required to be on call, to work at a designated evacuation site, or to be part of a crisis response team at a nearby site.
2.1. QUALITY CONTROL.
2.1.1. Quality Control Program. In compliance with the clause entitled “Inspection of Services”, 52.246-4, the contractor shall establish a complete Quality Control Program to ensure the requirements of this contract are provided as specified. The contracting officer will notify the contractor of acceptance or required modifications to the plan before the contract start date. The contractor shall make appropriate modifications (at no additional costs to the government) and obtain acceptance of the plan by the contracting officer before the start of the first operational performance period.
2.2. GOVERNMENT OBSERVATIONS. Government personnel, other than contracting officers (COs), may from time-to-time, with CO coordination, observe contractor operations.
However, these personnel may not interfere with contractor performance or make any changes to the contract.
2.3. SAFETY REQUIREMENTS. In performing work under this contract, the contractor shall:
2.3.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.
2.3.2. Take such additional immediate precautions as the contracting officer may reasonably require for safety and mishap prevention purposes.
2.3.3. Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.
2.3.4. Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.
2.3.5. Record and report promptly (within one hour) to the contracting officer or designated government representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.
2.3.6. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.
2.3.7. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.
2.4. PHASE OUT:
2.4.1. If there is a change in contractor or if the operation reverts to in-house, the incumbent contractor will provide familiarization, to the government or the follow-on contractor, whichever the case may be. During the phase-out familiarization period, the incumbent will be fully responsible for the operation.
3. APPENDICES
A. Acronyms & Abbreviations List
APPENDIX A
ACRONYMS AND ABBREVIATIONS LIST
Acronym/Abbreviation Definition
CO Contracting Officer
ESC Expeditionary Services Contractor
FST Fleet Survey Team
GR Government Representative
POC Point of Comtact
QCP Quality Control Program
SOW Statement of Work
| 1 DESCRIPTION OF SERVICES 3/6 |
| 2 GENERAL INFORMATION 7 |
File details come from the government source that posted it.