This federal solicitation requests offers for the supply of SWCS Battery Sets. Key details include a requirement for four production lots of six sets each to be delivered over 330 days from award. Offerors must meet technical specifications for design, manufacture, testing, and configuration management as defined in the procurement drawings and specifications referenced. Successful offerors will be required to pass first article testing and approval by the Government as well as subsequent production lot testing and approval. Pricing will be evaluated for reasonableness. The solicitation provides standard terms for small business subcontracting, transportation, and other standard contract clauses. The closing date for offers and additional submission instructions are included.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section L - Instructions, Conditions and Notices to Bidders
SECTION L
SUBMISSION OF OFFERS for LOWEST PRICED, TECHNICALLY ACCEPTABLE OFFERS
Proposal Preparation Instructions
1. The Offeror’s proposal shall consist of two volumes, General Information/Price and Technical.
2. Proposal Format
a. Offerors shall submit electronically one copy of the proposal.
b. Exceptions. Offerors are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors and subfactors. Failure to meet a requirement may result in an offer being ineligible for award. If the offeror finds it necessary to take exception to any of the requirements specified in this solicitation, the offeror shall clearly identify the applicable Volume and exceptions with a complete explanation of why the exception was taken, what benefit accrues to the Government (if any), and its impact, if any, on the performance, schedule, cost, and specific requirements of the solicitation. Offerors are cautioned that taking an exception may render the offer ineligible for award.
c. The proposal shall be organized into two volumes.
3. Proposal Content:
Volume I – General
1. Solicitation, Offer and Award - The SF 33 shall be submitted fully completed. The offeror is cautioned that the SF 33 must contain an original signature in block 17 of the form. The contractor shall acknowledge any amendments to the RFP in accordance with the instructions on the SF 33 and with Section L, FAR 52.215-1(b), Instruction to Offerors—Competitive Acquisition. The offeror shall provide the name, title and telephone number of the company/division point of contact regarding decisions made with respect to your proposal and who can obligate your company contractually. Also, identify those individuals authorized to negotiate with the Government.
2. Section B (Supplies or Services and Prices/Costs) - Section B shall be submitted fully completed and error free. It shall contain the offeror’s prices for the established Contract Line Items Numbers (CLINS).
3. Section K (Representation, Certifications, and Other Statements of Offerors) – The offeror shall ensure that Section K is submitted thoroughly completed with all blocks in each certification/representation completed truthfully and completely.
Volume II – Technical
Subfactor 1: First Article Testing (FAT)
· This requirement is subject to First Article Testing by the government. Offerors either must provide proof of successful FAT completion and approvals by submitting proof which can be a letter or a copy of the previous contract. If an offer is not seeking a waiver, the offer must include that in their offer and adhere to the schedule outlined in FAR 52.209-4. It provides an assessment of the offeror’s capability to satisfy the Government’s minimum requirement.
Offerors may email proposals to this solicitation electronically as follows:
To: Tiana Hammaker SUBJECT LINE: Proposal (insert name of Offeror) N00104-22-R-FB17
DOD SAFE: If a proposal exceeds 10MB, offerors may submit proposals through the DOD Secure Access File Exchange (SAFE) module at https://safe.apps.mil/. The Government will not retrieve proposals sent through proprietary or third party File Transfer Protocol sites or NECO. Offerors without PIV Certificates are required to request a drop-off no earlier than two days prior to solicitation closing and no later than the day of solicitation closing. Untimely requests for drop-off may result in later offers.
The completion and submission of the above items will constitute the offeror’s initial proposal and will indicate the offeror’s unconditional assent to the terms and conditions of this RFP and any attachments hereto.
The Government intends to award a contract without discussions, but reserves the right to conduct discussions if the contracting officer later determines them to be necessary. Since offers that take exception or object to terms of this solicitation may be rendered technically unacceptable, offerors are cautioned to address solicitation exceptions, objections, or questions to the contracting officer prior to the time set for receipt of initial proposals.
The Government reserves the right to require the submission of Other Than Certified Cost or Pricing Data as is deemed necessary to arrive at a fair and reasonable price.
CLAUSES INCORPORATED BY FULL TEXT
52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)
(a) Definitions. As used in this provision--
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, or revision, of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government's interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of provision)
FAR 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
FAR 52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Counsel for the Naval Supply Weapon Systems Support - Mechanicsburg, Code N0GC, 5450 Carlisle Pike Mechanicsburg, PA 17050-2411; or BID ROOM Naval Supply Weapon Systems Support – Philadelphia, Building 1, 700 Robbins Avenue, Philadelphia, PA 19111-05.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
DFARS 252.215-7008 ONLY ONE OFFER (JUL 2019)
(a) Cost or pricing data requirements. After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was received, the Offeror agrees to--
(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 2306a and FAR 15.403-3); and
(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.
(b) Canadian Commercial Corporation. If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:
(1) Profit rate or fee (as applicable).
(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).
(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable [U.S. Contracting Officer to provide description of the data required in accordance with FAR 15.403-3(a)(1) with the notification].
(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.
(c) Subcontracts. Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.
Section M - Evaluation Factors for Award
SECTION M
Evaluation of Award
EVALUATION FOR AWARD (LOWEST PRICED TECHNICALLY ACCEPTABLE
· Basis for Contract Award- This is a best value negotiated acquisition conducted in accordance with Federal Acquisition Regulation (FAR) 15.3, Source Selection, as supplemented by the Defense Federal Acquisition Regulation Supplement (DFARS). Award will be made to a single offeror who is deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to the solicitation requirements, and whose proposal, judged by an overall assessment of the evaluation criteria and other considerations specified in this solicitation, represents the Lowest Priced Technically Acceptable offer.
Evaluation criteria consist of factors and sub factors as follows:
FACTOR 1: Technical
Sub factor 1- First Article Testing (FAT) Evaluation
EVALUATION OF FIRST ARTICLE TESTING
(a) Offerors are advised that the contract awarded as a result of this solicitation will require first article testing. This requirement may be waived by the Contracting Officer when supplies identical or similar to those called for have previously been delivered by the offeror and accepted by the government. Therefore, offerors can submit alternative offers, one including testing and approval and the other excluding testing and approval. If the government waives the requirement for first article unit(s), test plans, testing and test report(s) for eligible offerors, the prices set forth in paragraph (g) will be used in evaluating offers. In addition, all provisions relating to first article testing will be deleted from the resulting contract.
(b) Offerors shall identify these identical or similar supplies by the contract number, agency, national stock number, contract award date, and contract delivery date.
| CONTRACT AGENCY |
| NSN CONTRACT |
| CONTRACT NUMBER |
| AWARD DATE |
| Delivery Date |
(c)The Government is responsible for first article testing under this contract. The contractor is required to submit an additional unit for government destructive testing per FAR 52.209-4.
(d) The approved first article serves as a manufacturing standard.
(e) Earlier delivery, if required in case of waiver of first article, shall not be a factor in the evaluation for award.
(f) The prices for first articles and first article tests in relation to production quantities shall not be materially unbalanced, if first article test items or tests are to be separately priced.
(g) Unit price offered if First Article is waived: $___________
The Technical Factor evaluation provides an assessment of the offeror’s capability to satisfy the Government’s minimum require
The Technical Factor will receive one of the adjectival ratings defined below. The sub factor ratings will be used to determine an overall rating for the factor.
Table A-1. Technical Acceptable/Unacceptable Ratings
| Rating |
| Description |
| Acceptable |
| Proposal clearly meets the minimum requirements of the solicitation. |
| Unacceptable |
| Proposal does not clearly meet the minimum requirements of the solicitation. |
Factor 2– Price. Price will not be scored or rated. Evaluation of price will be performed using one or more of the price analysis techniques in FAR 15.404-1(b). Through these techniques the Government will determine whether prices are reasonable, complete and balanced.
Definitions:
Reasonableness. A price is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business.
An award will only be made to an offeror that satisfies the general responsibility standards of Federal Acquisition Regulation (FAR) 9.104-1. The Contracting Officer may either make a responsibility determination without requesting any information from an offeror or require the offeror provide information to substantiate that it satisfies the general responsibility standards of FAR 9.104-1. The particular information requested from an offeror will be specific to that offeror. For example, an offeror that the Contracting Officer is less familiar with may be required to provide information not required from another offeror. The Contracting Officer may consider an offeror's inability to promptly respond to a request for information as an indication the offeror is nonresponsible since FAR 9.103(c) obligates prospective contractors to affirmatively demonstrate their responsibility.
When the Contracting Officer requests responsibility information, the Contracting Officers request, the offeror's response, and all related communications between the Government and offeror are solely for the purpose of determining whether the offeror is responsible. These communications will not constitute discussions within the meaning of FAR 15.306 since the offeror will not be given an opportunity to revise its proposal.