Switching_and_Instrumentation_System_tasks_and_components.docx
DOCX document 13 KB Posted
- Attached to
- Microwave Depot Test Stand Switching and Instrumentation System Upgrade Federal contract opportunity
- Solicitation number
- Not on record
About this file
Switching and Instrumentation System tasks and components
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Switching / Instrumentation subsystem, P/N 75-0097-000, QTY 11
The following is a list of the tasks and components for the requirement:
1) Provide a fully integrated switching and instrumentation subsystem
2) Provide all material associated with the subsystem including
a. VXI chassis and Enet slot 0 controller
b. Required switching modules, based on the VTI’s SMP family of switching
c. Required instrumentation based on the VMIP family of instruments
d. The VPC interface Receiver
e. Interface cabling assemblies that connect the switching and instrumentation to the VPC receiver
3) Major subsystem components include the following:
CT400A Chassis VXI 13- slot EX2500 Slot 0 controller / ENET SMP1100/6005/6005 Coax switching module 1-slot VPC 2025 interface cable ASSY VP to 6005 coax interface SMP1200/6004 x6 Coax switching module 2-slot VPC 2025 interface cable ASSY VP to 6004 coax interface SMP1200/3001 X6 Signal switching module 2-slot VPC 2025 interface cable ASSY VP to 3001 signal interface SMP1200/3001 X2 /2001X2 Signal / Power switching module 2-slot VPC 2025 interface cable ASSY VP to 3001 signal & 2001 power interface SMP1200/5004x2 5005X2/5001 Signal General purpose switching module 2-slot VPC 2025 interface cable ASSY VP to 500x signal interface VM9000/1548X2 Instrument DIO VPC 2025 interface cable ASSY VP to VM 1548 signal interface VM9000 /3608/1548C Instrument DIO O/C and DAC VPC 2025 interface cable ASSY VP to VM1548C & VM3608 signal interface VPC 2025 TR receiver interface Sub system Receiver VPC 2015 TR
4) Provide Virginia Panel Receiver VPC 2025 TR with the rack mount kit VPC P/N 310 113 451 as part of the subsystem.
5) Provide all the interface cabling between the above listed modules and the VPC interface receiver. These cable assemblies include the VPC receiver modules and the mating connectors to the subsystem
6) Install all the above instruments and switching modules in the chassis
7) Configure the instruments in the chassis with proper address settings
8) Conduct verification tests to ensure the instruments above are operating as expected. Provide drivers or wrappers and verify existing program function calls work with new Hardware
9) Provide installation procedure and any documentation generated as part of this process.