Updated_Specifications.PDF

PDF 81 KB Posted

Attached to
Fort Meade Fences Federal contract opportunity
Solicitation number
L15PS00411
Issued by
Department of the Interior Bureau of Land Management Montana-Dakotas

About this file

Updated Statement of Work (replaces original)

View the file

Other files for this federal contract opportunity

Other files attached to Fort Meade Fences, newest first.
File Type Posted
Sol_L15PS00411_Amd_000004.pdf PDF
Sol_L15PS00411_Amd_000003.pdf PDF
Sol_L15PS00411_Amd_000002.pdf PDF
SD9.txt TXT text file
Sol_L15PS00411_Amd_000001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART VI

SPECIFICATIONS

FT. MEADE FENCE 2015

MILES CITY DISTRICT OFFICE

MILES CITY, MONTANA

INDEX

DIVISION 1 - GENERAL REQUIREMENTS

01009 - GENERAL INFORMATION & REQUIREMENTS

01019 – GOVERNMENT FURNISHED PROPERTY

01505 - MOBILIZATION

DIVISION 2 - SITE WORK

02834 - WIRE FENCES & GATES

WORK DATA SHEET

SECTION 01009 - GENERAL INFORMATION AND REQUIREMENTS

PART 1: GENERAL

1.01 SUMMARY:

A. Description of Work: Furnishing labor, equipment, supplies, and materials, except for Government furnished items as designated in the specifications and Work Data Sheet to reconstruct a 4-wire fence (bottom smooth wire). Construction shall consist of 870 rods of new 4-wire (bottom smooth wire) with 3 steel posts to 1 wood post ratio, with removal and replacement of partial areas of fence and utilization of designated items existing on the lines.

Approximately 870 rods of 4-wire fence of the existing fence line shall be removed. Designated rods of fence, corners, panels, gates, wood posts along the fence route unless indicated otherwise on the location maps and Work Data shall be replaced and installed. *Note: The fence route shown on the location maps is the line and items to be constructed, installed or utilized. Not all the existing fence alignment, corners, and panels to be removed along the construction route are shown to eliminate any construction confusion. Tie into existing structures, panels, including fences as designated. The Contracting Officer will designate what items are to remain, to be removed, and to be replaced as shown on the work location maps, the work reference map, and Work Data Sheet.

B. Location: Work under this Contract is located in Meade County South Dakota. The Work locations are shown on the drawings.

C. Work Data Sheet: Designates the type and quantity of work required at each project location, and dimensions required for structures as shown on typical drawings.

1.02 QUALITY ASSURANCE:

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

1.03 DELIVERY, STORAGE, AND HANDLING:

A. Delivery: The Contractor shall protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.

B. Storage: The Contractor shall provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling. No material shall be stored with direct contact to the ground.

C. Handling: The Contractor shall load and unload products in such a manner that protects them from damage.

1.04 PROJECT/SITE CONDITIONS:

A. Access to the Work: Public roads damaged by the Contractor shall be restored at

Contractor's expense to the same condition they were in at the commencement of work.

Survey monuments or markers disturbed or removed during construction shall be reset at the Contractors Expense.

B. Environmental Considerations: Operations of the Contractor upon government premises including storage of materials, camping areas and equipment parking shall be confined to approved areas.

1.05 SEQUENCING AND SCHEDULING:

A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, the Contractor shall submit an updated schedule within 3 calendar days.

PART 2: PRODUCTS

(There are no applicable requirements.)

PART 3: EXECUTION

3.01 PROJECT MEETINGS:

A. Pre-Work Conference:

1. Notification: A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. Attendance: The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.

3. Presentation: The Contractor shall be prepared to summarize and explain procedures planned for the project.

B. Progress Meetings:

1. Location: Meetings shall be held at the project site, or as determined by the

Contracting Officer.

2. Notification: Meetings may be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda.

C. Final Inspection:

1. Location: Meeting shall be held at the project site, or as determined by the Contracting Officer.

2. Notification: The Contractor shall notify the Project Inspector (PI) or Contracting

Officers Representative (COR) at least 3 working days before the completion date so a final inspection can be scheduled.

3. Superintendent shall be present during this inspection.

3.02 PREPARATION:

A. Work Layout: The Government will set stakes or posts to give the Contractor measurements, lines and grades necessary for the work executed under the Contract.

B. Installation Changes: Records shall be maintained of actual installations where at variance with the work shown, where changed, or where not otherwise located by dimension, elevation or other reference on the Contract drawings.

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment.

4.02 BASIS OF PAYMENT:

A. Payment: No direct payment for the work described under this section will be made. The

Contractor shall include consideration for this item in the schedule of items price (SOI) for other items of the Contract.

END OF SECTION

SECTION 01019-GOVERNMENT-FURNISHED PROPERTY

1.01 SUMMARY:

A. Section Includes: Materials to be furnished by the Government and their locations.

1.02 DELIVERY, STORAGE, AND HANDLING:

A. Location: The Government-furnished property will be provided by the Bureau of Land Management at the BLM storage facility area located at Fort Meade in Sturgis, South Dakota at the site to be fenced. .

B. Time: Property will be available for delivery Monday through Friday, between the hours of 8:00 A.M. and 4:00 P.M., except on holidays with a lead time of at least a week.

D. Loading, Offloading and Transporting Property: The Contractor shall be responsible for providing the necessary material-handling equipment to load and offload materials. The Contractor shall return all unused property upon completion of the project.

PART 2: PRODUCTS

2.01 MATERIALS:

A. Materials to be Furnished by the Government:

Specification Materials Estimated Section Description Quantity Unit

02834 5 ft. Metal Walk Through Gate 2 Each 02834 Wood Bike Ramp (3’W x 10’L) 2 Each 02834 16 Ft. Wide Steel Livestock Gate 9 Each

2.02 EQUIPMENT:

A. There are no applicable requirements.

PART 3: EXECUTION

Two walk through metal gates and bike ramps are attached to a panel or wood posts as shown on the reference map drawing. Relocate, realign and install as designated by the Contracting Officer.

Install a contractor furnished railroad tie for the single brace post installed adjacent to the walk through gates. Place the railroad tie 3 ft. in the ground and secure in place with 2 ft. of cement and surrounded with 1 ft. of a combination of rock and earth backfill. Gates shall be adjusted to properly open and close. Refer to the photo for reference and installation to the brace posts.

The existing 16 ft. wide steel cattleguard/bases plus wings shall be tied into as shown on the work map and as directed by the Contracting Officer.

The bike ramp will involve clearing, excavating, and sloping approximately a slightly larger area to install the government provided wooden drive through ramp with a length just over 10 ft. from the entrance to the exit and slightly over 3 ft. in width with the triangular ramp wings for attachment. Refer to the ramp photo for reference, installation, or readjustment as necessary. Lay the ramp in an excavated area approximately 3 to 4 inches in depth and slope to ground conditions to allow ground stability, provide a flush approach and exit to avoid any entrance or exit ground or ramp hazards. Attach the ramp wings to a single installed wood brace post or a brace post of an installed adjacent panel as indicated on the drawing, photo, and maps. Refer to the photo for reference and installation to the brace posts.

The 16 ft. wide government furnished metal livestock gate shall be attached to an installed single brace post or the brace post of an adjacent panel to be installed to properly open and close. Refer to the photo for reference and attachment.

*Note: Installation of the walk through gate, bike ramp, and livestock gate shall include only the labor, costs, and accessories not provided to attach or hang the government provided items to a single wood brace, brace post or railroad tie of an installed adjacent panel to properly function.

The cost of any required single wood brace posts or railroad tie shall be paid for as a single wood line post or railroad tie installation. The Contracting Officer shall designate if an existing brace or panel post can be utilized or if a new brace post or railroad tie shall be installed and utilized

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment.

4.02 BASIS OF PAYMENT:

A. Payment: No direct payment for the work described under this section will be made. The Contractor shall include consideration for this item in the bid price for other items of the Contract.

SECTION 01505 – MOBILIZATION

1.01 SUMMARY:

A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site. This specification does not include moves between project sites.

PART 2: PRODUCTS

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: Progress payments will be made as follows:

1. When 5 percent of the original contract amount is earned from other bid items, 50 percent of the amount bid for mobilization or 5 percent of the original contract amount, whichever is lesser, will be paid.

2. When 10 percent of the original contract amount is earned from other bid items, 100 percent of the amount bid for mobilization or 10 percent of the original contract amount, whichever is lesser, will be paid.

3. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10 percent of the original contract amount, will be paid.

4. The total sum of all payments shall not exceed the original contract amount bid for mobilization, regardless of the fact that the contractor may have shut down the work on the project or moved equipment away from the project and then back again.

4.02 BASIS OF PAYMENT:

A. Payment: No direct payment for moves between project sites will be made. The Contractor shall include consideration for moves between project sites in the schedule of items price for other items of the Contract. Prices and payment will be full compensation for the work described in this section. No modification and adjustments shall be allowed for costs and changes to mobilization despite changes in fuel or transportation costs. Payment will be made under:

Pay Item Pay Unit

01505 (1) Mobilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lump Sum

SECTION 02834 - WIRE FENCES AND GATES

1.01 SUMMARY:

A. Section Includes: Installing with Contractor and Government furnished property, wire fences, gates and various panels.

1.02 REFERENCES:

A. American Society for Testing and Materials

ASTM A 121-86 Zinc-Coated (Galvanized) Steel Barbed Wire ASTM A 641-82 Zinc-Coated (Galvanized) Carbon Steel Wire ASTM A 702-87 Steel Fence, Posts, and Assemblies, Hot-Wrought

B. American Wood Preserver's Association

AWPA C 1-86 All Timber Products - Preservative Treatment by Pressure Process AWPA C 5-84 Fence Posts - Preservative Treatment by Pressure Processes AWPA P 10-73 Lodgepole Pine Poles - Preservative Treatment by the Full-Length Thermal Process AWPA P 2-85 Standard Creosote and Creosote Solutions AWPA P 5-86 Waterborne Preservatives AWPA P 8-77 Oil-Borne Preservatives AWPA P 9-84 Solvents and Formulations for Organic Preservatives Systems

1.03 SUBMITTALS:

A. Certification: The Contractor shall furnish written certification from the treating plant stating that chemicals and methods used, for wood preservation and net amount of preservative retained are in conformance with applicable standards. Contractor-furnished gates and accessories will be approved by the Contracting Officer prior to installation. Furnish written certification from the manufacturer that the Contractor-Furnished fence posts and wire conform to the requirement of this section. Submittals shall be according to Section 01009 - General Information and Requirements.

PART 2: PRODUCTS

2.01 CONTRACTOR - FURNISHED MATERIALS:

A. Heavy Duty Barbed Wire: (Redbrand or Equal) Two 12-1/2 ga. galvanized wires twisted together with 2-point barbs of 14-ga. wire spaced 4 inches apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.3 oz/ft2 of coated surface area and a minimum breaking strength of 950 lb-force. The barbed wire shall be a heavy duty wire conforming to ASTM A 121 requirements. Failure to meet any of these requirements shall result in the rejection of the material at the time of inspection.

B. Heavy Duty Barbless Wire: (Redbrand or Equal) Two 12-1/2 ga. galvanized wires twisted together. Wire shall be zinc-coated steel wire of at least 0.3 oz/ft2 of coated surface area and a minimum breaking strength of 950 lb-force. The wire shall be heavy duty with a high tensile strength, low stretch, tight brading per rod, conform to all ASTM A 121 requirements and must be tagged accordingly. Failure to meet any of these requirements shall result in the rejection of the material at the time of inspection.

C. Brace Wires: Shall be 4, 9-ga. galvanized wires or 2, galvanized, 12 1/2 ga. barbless-wires twisted tight (total of 4 strands). The minimum weight of zinc coating for 9-ga. wire shall be at least 0.4 0z of zinc per sq. ft. of coated surface area and 0.3 oz for 12-1/2 ga. wire.

D. Miscellaneous Wire: Wire for gate loops, and fastening wood stays, shall be 9 or 12-1/2 ga.

galvanized wire.

C. Staples: Shall be 9-ga. Barbed bright finished or galvanized with slash-cut points 1-3/4 inches long.

D. Nails: Shall be 60 d ring shank at least 6 inches long.

E. Heavy Duty Steel Fence Posts: (Chicago Steel or Equal) Shall be a heavy duty grade steel posts painted green, green with white or silver tops, "T" bar type, with a welded or riveted anchor plate which does not easily bend or twist when an obstruction is hit during the driving process.

Posts shall be furnished with clip-type fasteners. Punched tabs for fastening wires are not acceptable. Steel posts shall be manufactured from wrought, rail, or new billet steel, and shall weigh a minimum of 1.33 lb per ft. exclusive of the anchor plate, which shall weigh a minimum of 0.67 lb., with a minimum of 18 sq. inches in area. Posts shall meet all ASTM A 702 requirements and must be tagged accordingly. Failure to meet any of these requirements shall result in the rejection of the material at the time of inspection.

F. Wood Posts and Braces: Wood posts and braces shall be sound single stem members. A slight bend in one plane is acceptable. Posts are not acceptable if a straight line drawn from the geometric center of the top to the geometric center of the butt of the post falls outside of the body of the post. Posts that are twisted, rotted, excessively bent or have checks greater than 1/2 their thickness are considered unsound and are not acceptable. Posts and brace rails may be full stem members, sawed members or square cross-section, or split members. The Work Data Sheet shall indicate the required post diameters, dimensions, and the depths to be set.

1. Minimum diameter for full stem line posts and brace rails shall be 5 inches at the small end, and 5 inches for other posts. Single wood line posts shall be 5" x 7', brace line posts 6" x 8', and brace rails 5” x 8’. Minimum cross sectional area at the small end for split members shall be 10 sq. inches for line posts and brace rails, and 20 sq. inches for other posts. Slabs and wedge-shaped members will not be acceptable. Railroad ties shall be a minimum of 5” x 8’ of good quality, grade, and be properly treated.

2. The following species will be acceptable if treated for the full length: Ponderosa pine, Lodgepole pine, and Douglas-fur. Split Western Redcedar posts will be acceptable if the butt is treated for a minimum depth in the ground plus 6 inches. The following species will be acceptable without treatment: Honey Locust, Juniper, Osage Orange, and White Oak.

G. Gates: Wire Gates: Shall have the same type wire and wire spacing as the fence as shown in the drawings and Work Data Sheet unless stated on the Work Data Sheet. Wire gates shall have wire stays between the wood end stays. Any panels installed on each side of the gates shall be paid as separate installation items.

H. Mechanical Gate Closures: Assembly shall include:

1. A rigid steel strap or 9-ga. smooth wire loop 6 inches from the ground securely connected to the gate post and shaped so that the gate stay will be securely held in place.

2. An adjustable cable or chain, or rigid steel strap fastened to a cam lever device located 6 inches from the top of the gate posts. The closer must be capable of securely holding the gate stay in place.

SECTION 2.02 - GOVERNMENT-FURNISHED PROPERTY

Refer to section 01019 Government Furnished Property. Two 5 ft. walk through metal gates shall be removed, reset, or realigned as approved and designated by the Contracting Officer at the same location or area. Nine 16 ft. metal livestock gates shall be government furnished and provided and shall be contractor installed as shown on the maps, drawings, and photo as directed by the Contracting Officer.

*Note: Installation of a walk through gate, bike ramp or livestock gate shall include the labor, costs, and any accessories not provided to attach, install, or hang the government provided items to a single wood brace or brace post of an installed adjacent panel. The cost of any required single wood brace posts shall be paid for as a single wood line post or railroad tie installation. The Contracting Officer shall determine and designate if an existing brace or panel post can be utilized or if a new brace post shall be installed and utilized and shall be paid accordingly.

2.02 WOOD TREATMENT PRACTICES:

A. General: The following treatments may be used. Minimum net retentions and penetrations shall be according to AWPA C 5. Treatment method shall be according to AWPA C 1, except as otherwise noted. When a treated member must be bored or cut during construction, thoroughly swab untreated surfaces with an approved preservative.

B. Pentachlorophenol Method: Five percent pentachlorophenol solution conforming to AWPA P 8 in petroleum AWPA P 9 conforming to Type A.

C. Chromated Copper Arsenic: Waterborne preservative conforming to AWPA P 5, types A, B, or C.

D. Creosote: Shall be according to AWPA P 2.

E. Butt-End Treatment for Split Western Redcedar Only: When split western redcedar posts are used with treatment on butt only, treatment may be by either the cold soaking or hot bath process.

Either pentachlorophenol or Creosote (Coal tar) solution may be used. Minimum net retention of preservative shall be 6 lb/ft3 for creosote solutions and 0.3 lb/ft3 for pentachlorophenol.

F. Thermal Process: Lodgepole pine may be treated by the thermal process according to AWPA C 10.

3.01 PREPARATION:

A. Clearing: Maximum mowed/clearing width is 6 ft on each side of the fence line, except where restricted on designated areas of Ft. Meade. Many areas of the existing line have been cleared by the BLM to allow the use of equipment for installation, however some areas will require the installation of the wire only on the BLM side as directed by the Contracting Officer. This may require some hand work due to the ground cover or terrain. Long eared bats are in the area, therefore no pine trees shall be cut down, but may be trimmed with approval from the Contracting Officer. It is acceptable to clear oak trees that fall within the clearing limits and with authorization of the Contracting Officer. Provide minimum disturbance to existing grass and sod.

Any blade work or other surface disturbance shall require prior approval.

3.02 INSTALLATION:

A. General: Set wood posts in dug or drilled holes. Drive steel posts. All line posts shall be steel and wood configuration as designated on the Work Data Sheet.

B. Setting Posts: Dig holes for setting wood posts to the depth as shown on the Work Data Sheet.

Set posts plumb and to the spacing and grades as shown on the drawings, unless staked otherwise.

Space within 6 inches of that dimension shown on the drawings or in the Work Data Sheet. Holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Backfill gradually and uniformly with soil around each post. Do not exceed 6 inch lifts during backfill. Compact backfill firmly from the bottom of the hole to the ground surface.

*Note: Milled wood posts shall be allowed to have an anchor plate or block attached to the bottom or a wood block attached to the side of the post base area to anchor the post in place since it has no taper to properly hold it in place.

C. Driving Posts:

1. Wood Posts: Drive only when approved by the Contracting Officer to the depth shown on the Work Data Sheet. Predrill a 2 or 3 inch diameter hole as necessary if wood posts are to be driven. Wood posts shall be machine pointed if driven into the ground. Posts shall be driven plumb. Posts that are split, bent or broomed, will not be accepted.

2. Steel Posts: Drive into the ground to the depth shown on the drawings, work data sheet, or until the anchor plate is slightly below the ground surface. Posts shall be driven plumb. When rock formations prevent driving remove anchor plate and excavate or drill holes a minimum of 18 inches deep and slightly larger than the diameter of the post. Place posts in the holes and grout the post solidly in position with cement grout or mortar.

D. Corner Panel and Stress Panel Assemblies: Set posts as specified, fabricate panels as shown on the drawings and indicated on the Work Data Sheet.

E. Figure Fours and Rock Jacks: May be used in rock. Figure fours shall be used in lieu of steel posts, and rock jacks in lieu of wood line posts, except that where a series of figure fours are required, a rock jack shall be substituted for every fifth figure four. Figure fours and rock jacks shall be constructed as shown on the drawings.

F. Wire: Stretch tightly and staple to wood posts or securely attach to steel posts with standard wire clips. Wire is properly stretched when it is springy to the touch. Drive staples into wood until the staple comes in contact with the wire against the post, but not so tight as to crimp the wire or prevent movement of the wire. Do not drive staples parallel to the grain of the wood.

Terminate wire at each end post, gate post, corner post, or stress panel. Wrap wire around the post two times and tie off by wrapping around the incoming wire a minimum of four times.

G. Brace Wire: Shall be double-looped and twisted tight with a stick or post. Leave one end long enough to fasten behind the horizontal brace to prevent wire from unwinding.

H. Wire Spacing: The wire spacing will be from the ground up. Bottom wire shall be smooth unless designated otherwise. Spacing for all projects is indicated on the Work Data Sheet.

I. Gates: Shall be installed according to the drawings, unless directed otherwise by the Work Data or Contracting Officer. Designated metal gates by the Contracting Officer and the maps shall be installed as directed or indicated.

J. Mechanical Gate Closures: Line up the latch with the gate. Adjust latch assembly after installation so that the latch does not bind and the gate hangs properly.

K. Spiking: For spikes larger than 40d, predrill lead holes. The hole diameter shall be three-fourths the diameter of the spike and drilled to a depth no greater than 1/2 the length of the spike.

L. Deadman: Shall be installed at all minor depressions when the spacing between the bottom wire and the ground exceed 20 inches. Deadman can be rock weighing a minimum of 50 lbs or a 5 ½’ steel post driven straight into the ground a minimum of 4 ft. and parallel with the fence attached with additional wire of the same material as the bottom wire. See drawing 02834-1.

Salvageable steel posts as approved and designated by the Contracting Officer shall be allowed as deadmen.

M. Railroad Tie: Dig holes for setting the tie to the depth as shown on the Work Data Sheet. Set posts plumb and to the spacing and grades as shown on the drawings, unless staked otherwise.

Space within 6 inches of that dimension shown on the drawings or in the Work Data Sheet.

Provide an adequate area around the post to place backfill to secure the post in place and place a minimum of 2 ft. of cement around the base. Once the cement has properly set and cured, backfill the remaining 1 ft. of cover with backfill and rock not to exceed 6 inch lifts, compacting and tamping to the ground surface.

3.03 FENCE REMOVAL:

A. Shall include removal and disposal of clips, stays, wire, wood & steel posts, various panels, plus salvage of designated steel posts, wood posts, and gates as designated and determined by the Contractor and as approved by the Contracting Officer. All removed material shall become the responsibility of the Contractor. Designated salvageable material shall be stockpiled, utilized as directed and approved by the Contracting Officer. Material not salvaged shall become the property of the Contractor. The Contractor shall be responsible to remove, dispose, and haul away all material as directed and approved by the Contracting Officer. Roll, secure wire, posts, gates, and stock pile. No woven wire shall be returned to any of the fence permittee’s or other operators unless approval is given by the Contracting Officer. Wood and steel posts shall not be cut off at the ground level. Wood or steel posts that break off at the ground level shall be pulled or the stub shall be pushed below the ground surface. Any large holes or voids in the ground from pulled posts shall be covered or filled with appropriate sod or backfill to eliminate any safety hazards.

Wood posts shall not be stockpiled and burned. Two short sections of woven wire (approximately 2000 ft total) located on the east boundary of the VA property are to be removed, rolled up, and left on site to be removed by government forces.

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: The work described in this section will be measured for by the rod as measured along the ground surface next to the completed and removed fence including distance across gate openings, end, stress, and corner panels. The quantities of stress, and corner panels, single wood posts, railroad ties, bike ramps, and gates to be paid for will be the actual number of these items installed. Note: Wire Gates do not include adjacent end or corner panels. These are separate pay items. Walk Through Gates, bike ramp, or metal gate installations do not include the adjacent single wood post utilized for brace installations or to brace panels. They are separate pay items.

These installations shall include any site preparations, costs, and accessories necessary to install the government provided items to attach the structures to the necessary braces as designated by the Contracting Officer (CO). Note* All 16 ft. wire gates refer to 16 ft. 6 inch spacing width, unless designated otherwise on the drawings, maps, or Work Data Sheet. Refer to the photo for reference and attachment of the metal gates, walk through gates, or bike ramp to the brace posts.

Deadman in the fence line are considered part of the fence construction and will not be paid as a separate item.

4.02 BASIS OF PAYMENT:

A. Payment: Payment will be based on the following pay items:

Pay Item Pay Unit

02834(1B) Barbed Wire Fence 3 Steel/1 Wood (4-Wire) . . . . . . . . . . . . . . Rods 02834(1C) Fence Removal (Wire). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rods 02834(1E) Railroad Tie Installation . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . Each 02834(6) Barbed Wire Stress Panel. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Each 02834(7) Three-Post Barbed Wire Corner Panel . . . . . . . . . . . . . . . . . . . Each 02834(7A) Four-Post Barbed Wire Corner Panel . . . . . . . . . . . . . . . . . . . Each 02834(8) Five-Post Barbed Wire Corner Panel. . . . . . . . . . . . . . . . . . . . Each 02834(22B)Walk Through Gate (5 Ft.) . . . . . . . . . . . . . . . . . . . . . . . . . . . Each 02834(23) Barbed Wire Gate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Each 02834(23A)Bike Ramp. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Each 02834(23B)Metal Gate (16 ft.) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Each 02834(25) Single Wood Post (Line) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Each

Work Data Sheet

Install Bike Barbed Barbed Barbed Barbed Barbed Install Install Install Ramp or Wire Wire 3- Post 4-Post 5-Post Single 5 Ft. 3/1 Steel

16 ' wide Gates Stress Corner Corner Corner Fence Wood Walk T Fence Project Project Steel Gate 4-Wire Panels Panels Panels Panels Removal 5" Post Gate 4-wire

Project No. Location (Each) (Each) (Each) (Each) (Each) (Each) (Rods) (Each) (Each) (Rods) Notes Salvageable steel posts as approved can be used for deadman, drive within at least 1.5' of the top.

Ft. Meade T 5 N R 5 E, 2-B Ramp 1-16.5' 32 6 4 2 870 10 Reg. 2 870 *3:1 steel/wood ratio, remove woven and barbed wire, install one wire gate with wire stays. Bottom Fence Sec. 11 & 12 9-Steel W-gate 8' Post 8' Post 8' Post 8' Post 4-Wire Wood (Provided) wire (smooth), no wire fence stays required on main line. Contractor is responsible to haul/dispose all

Gates 8' Post Barbed 4 RailR . unsalvageable materials. *Note: No removed materials shall be given to the permittee/operators without (Provided) Ties approval from the Contracting Officer (CO). Install (9) government furnished 16 ft. steel gates, 2 bike

8' Tie ramps, and 2 walk through gates. Tie into designated structures, cattleguards, and fences.

Single wood line posts installed as brace posts for any metal & walk through gates, and bike ramps shall be paid as a separate bid pay item and not as part of the installation. The Contracting Officer shall determine if a single wood brace shall be installed or tied into an adjacent brace post panel. Railroad ties shall be set 3' in the ground and secured in place with 2 ft. of concerete/1 ft. of soil and rock to keep the gate post in proper alignment and place. BLM crews have cleared many areas of the fence to allow the installation of the material and use of equipment, however Ft. Meade has restricted areas and the wire can only be placed on the BLM side as designated/directed by the Contracting Officer. This may require some hand clearing and installation due to the ground cover or terrain. Long eared bat restrictions apply, therefore no pine trees shall be cut down, but may be trimmed with approval from the Contracting Officer. Oak trees can be cleared with authorization from the Contracting Officer

2 - B. Ramp Wire 10 Reg 2 Totals 9-S Gates 1 32 6 4 2 870' Wood (Provided) 870'

Provided W Gate 4 RR Tie Drawing Dimensions

1. All Steel post spacing (L) 16'6"

2. Length of wood posts (H1): 7' *Singles *Panels 8'0" Verticle 8'0" Cross

3. Depth of wood posts in ground (h1): 3' *Singles *Panels 3'6"

4. Diameter of wood posts 5" Dia. *Singles *Panels 6" Dia. Verticle *Panels 5" Dia. Cross

5. Length of steel line posts (H2): 5'6"

6. Depth of steel line posts in ground (h2): 1'6"

7. Gate post spacing: 16'6" unless stated otherwise.

7. Wire Spacing 4-wire w/ bottom smooth

D 40" C 28" B 22' A 16"

Note: Bottom wire shall be smooth.

FT. MEADE FENCE 2015

SPECIFICATIONS_INDEX
MeadeSpecUpdatedGLS6-22
WkData Meade15