Sol_L15PS00332.pdf

PDF 814 KB Posted

Attached to
Feagle and Tobe Creek Culverts Federal contract opportunity
Solicitation number
L15PS00332
Issued by
Department of the Interior Bureau of Land Management Oregon-Washington

About this file

L15PS00332

View the file

Other files for this federal contract opportunity

Other files attached to Feagle and Tobe Creek Culverts, newest first.
File Type Posted
Attachment_4_Maps.zip ZIP file
Attachment_3_Geologic_Reports.zip ZIP file
Attachment_2_BLM_Permits_and_Agreements.zip ZIP file
Section_C_Attachments_-_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040206427

BLM OR-ST OFC PROC MGMT BR(OR952)

1220 SW 3rd Avenue, 12th Floor

PORTLAND OR 97204

LHA

SEE SOLICITATION SECTION L

Richard Dandasan 503-808-6220

1x 05/08/2015

L15PS00332

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

FEAGLES AND TOBE CREEK CULVERTS, SALEM DISTRICT AREA OF RESPONSIBILITY, BENTON,

COUNTY, OREGON

MAGNITUDE OF THIS CONSTRUCTION PROJECT IS BETWEEN $250,000.00 AND $500,000.00

DUNS NO: ___________________________

E-MAIL: ____________________________

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

5 90 calendar days and complete it within ________________ ________________ calendar days after receiving

Clause 52.211-10

06/10/2015

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

BLM OR STATE OFC PROC MGMT-OR952

1220 SW 3rd Avenue, 12th Floor

PORTLAND OR 97204

LHA

Constance B Hampton

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 69

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

L15PS00332

FOB: Destination

Period of Performance: 06/15/2015 to 09/15/2015

00010 Feagles and Tobe Creek Culverts. See Section B for additional details.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

FEAGLES AND TOBE CREEK CULVERTS, SALEM, OREGON SOLICITATION NO. L15PS00332

BLM SALEM DISTRICT OFFICE Page 4 of 69

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

BASE

Item

no. Item Description Quantity

Unit of Measure Unit Price Total

1. 151(01) Mobilization 1 LS $ $

2. 204(01) Excavation and

Embankment – Feagles

1 LS $ $

3. 204(02) Excavation and Embankment

1 LS $ $

4. 204(03) Select Borrow – Tobe 350* CY $ $

5. 251(01) Class Riprap 300* TN $ $

6. 251(02) Vein Rock – Feagles 1 LS $ $

7. 251(03) Vein Rock – Tobe 1 LS $ $

8. 251(04) Streambed Materials –

Feagles

490* TN $ $

9. 251(05) Streambed Materials – Tobe

320* TN $ $

10. 301(01) Surface Course Aggregate

– Feagles

310* TN $ $

11. 301(02) Surface Course Aggregate - Tobe

310* TN $ $

12. 301(03) Subbase- Feagles 370* TN $ $

13. 301(04) Subbase-Tobe 550* TN $ $

14. 601(01) Concrete Footings- Feagles 75* CY $ $

15. 601(02) Concrete Footings- Tobe 90* CY $ $

16. 602(01) 24-Inch Culvert 1 LS $ $

17. 603(01) Structural Plate Structures

-Feagles

1 LS $ $

18. 603(02) Structural Plate Structures -Tobe

1 LS $ $

GRAND TOTAL $

* Estimated Quantity LS = Lump Sum CY = Cubic Yard TN = Ton

PERFORMANCE PERIOD: See clause 52.211-10 in Section I.

THIS SOLICITATION IS TOTAL SMALL BUSINESS SET-ASIDE.

(End of Section B)

BLM SALEM DISTRICT OFFICE Page 5 of 69

SECTION C –SPECIFICATIONS

SUPPLEMENTAL SPECIFICATIONS FOR THE CONSTRUCTION OF FEAGLES AND TOBE CREEK

CROSSING

Description of Work

The work to be done under this contract includes all labor, supervision, transportation, equipment, tools, supplies, and materials (not furnished by BLM) necessary to remove and dispose of existing metal culvert pipes at two sites and construct two new structural steel arch bottomless culvert pipes, and other work as necessary for a complete project. The work includes de-watering the site; excavation and construction of road prisms; structure excavation and backfill; removal and disposal of existing culvert; concrete footings, furnishing and installing structural steel arch culverts, shaping and grading streambed materials, construction of riprap slope protection, and other related site work. The Salem District Site is located on BLM Rd# 14-7-19 in Benton County, approximately 3 miles (4 road miles) south of the town of Alsea, Oregon, and on BLM Rd# 12-8-19 in Lincoln County, approximately 10 miles (23 road miles) north of the town of Alsea, Oregon.

Applicable Standard Specifications

The General Requirements (Division 100) and applicable sections of Division 150 through 700 of the Federal Highway Administration's “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects -- FP-03, U.S. Customary Units" of the U.S. Department of Transportation, Federal Highway Administration apply to this project as modified by these Supplemental Specifications and by the Special Contract Requirements and Contract Clauses contained in the contract. Unless otherwise noted, all reference headings in these supplemental specifications refer to divisions, sections, articles or paragraphs of the Standard Specifications, FP-03, and bear like headings.

Federal Highway Administration Standard Specifications are available electronically at:

http://flh.fhwa.dot.gov/resources/pse/specs/fp-03/fp-03usc.pdf http://flh.fhwa.dot.gov/resources/pse/specs/fp-03/fp-03usc.pdf

BLM SALEM DISTRICT OFFICE Page 6 of 69

INCLUDED DRAWINGS

(SEPARATELY ATTACHED – SECTION C)

01 TITLE SHEET

02 GENERAL NOTES AND DETAILS

03 FEAGLES TYPICAL SECTIONS

04 FEAGLES EXISTING SITE PLAN

05 FEAGLES EROSION CONTROL AND DISPOSAL SITE PLAN

06 FEAGLES PROPOSED STREAM PLAN AND PROFILE

07 FEAGLES FOOTING AND STREAM DETAILS

08 FEAGLES PROPOSED ROAD PLAN AND PROFILE

09 TOBE TYPICAL SECTIONS

10 TOBE EXISTING SITE PLAN

11 TOBE EROSION CONTROL AND DISPOSAL SITE PLAN

12 TOBE DE-WATERING PLAN

13 TOBE PROPOSED STREAM PLAN AND PROFILE

14 TOBE FOOTING AND STREAM DETAILS

15 TOBE ROAD PLAN AND PROFILE

BLM SALEM DISTRICT OFFICE Page 7 of 69

Supplemental Specifications include the following divisions:

DIVISION 100 GENERAL REQUIREMENTS

Section 101 TERMS, FORMAT, AND DEFINITIONS

Section 102 BID, AWARD, AND EXECUTION OF CONTRACT

Section 103 SCOPE OF WORK

Section 104 CONTROL OF WORK

Section 105 CONTROL OF MATERIAL

Section 106 ACCEPTANCES OF WORK

Section 107 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

Section 108 PROSECUTION AND PROGRESS

Section 109 MEASUREMENTS AND PAYMENT

DIVISION 150 PROJECT REQUIREMENTS

Section 151 MOBILIZATION

Section 152 CONSTRUCTION SURVEY AND STAKING

Section 154 CONTRACTOR SAMPLING AND TESTING

Section 156 PUBLIC TRAFFIC

Section 157 SOIL EROSION CONTROL

DIVISION 200 ASPHALT PAVEMENTS AND SURFACE TREATMENTS

Section 201 CLEARING AND GRUBBING

Section 203 REMOVAL OF STRUCTURES AND OBSTUCTIONS

Section 204 EXCAVATION AND EMBANKMENT

Section 209 STRUCTURE EXCAVATION AND BACKFILL

DIVISION 250 SLOPE REINFORCEMENT AND RETAINING WALLS

Section 251 RIPRAP

DIVISION 300 AGGREGATE COURSES

Section 301 UNTREATED AGGREGATE COURSES

BLM SALEM DISTRICT OFFICE Page 8 of 69

DIVISION 600 INCIDENTAL CONSTRUCTION

Section 601 MINOR CONCRETE STRUCTURES

Section 602 CULVERTS AND DRAINS

Section 603 STRUCTURAL PLATE STRUCTURES

Section 625 TURF ESTABLISHMENT

Section 635 TEMPORARY TRAFFIC CONTROL

DIVISION 100

GENERAL REQUIREMENTS

Section 101. - TERMS, FORMAT, DEFINITIONS

101.02 Specification Format. Delete the first sentence of the third paragraph.

101.04 Definitions. Delete the definitions for the following terms:

Award Contractor Plans Bid Contract Time Right-of-Way Bidder Day Solicitation Bid Form Drawings Subcontract Bid Guarantee Government Subcontractor Bid Schedule Notice to Proceed Substantial Completion Contract Pay Item Surety Contracting Officer Payment Bond Contract Modification Performance Bond

Modify the following definition as follows:

Special Contract Requirements -- Delete this definition and replace with the following:

Supplemental Specifications -- Modifications to the standard specifications applicable to an individual project.

Section 102. -- BID, AWARD, AND EXECUTION OF CONTRACT

Delete this section in its entirety.

Section 103. -- SCOPE OF WORK

103.02 Disputes. Delete in its entirety.

103.03 Value Engineering. Delete in its entirety.

103.04 Contract Records. Delete in its entirety.

103.05 Partnering. Delete in its entirety.

BLM SALEM DISTRICT OFFICE Page 9 of 69

Section 104. -- CONTROL OF WORK

104.01 Authority of the Contracting Officer (CO). Delete in its entirety.

104.02 Authority of Government Inspectors. Delete in its entirety.

104.03 Specifications and Drawings.

(a) General. Delete the text and replace with the following:

Shop drawings for any part of the permanent work shall include, but not be limited to, stress sheets, anchor bolt layouts, shop detail drawings, erection plans, equipment lists, material certifications, manufacturer’s literature, and any other information specifically required elsewhere in the specifications that shall be reviewed and approved by the Contracting Officer before any work involving these plans is performed. Submittals shall be made sufficiently in advance of the start of the affected work to allow a minimum of seven (7) days for review by the Government. Additional time will be required for revisions, rejections and resubmittals.

Shop drawings shall be submitted through the Contracting Officer’s Representative for review by the Government for the following item:

(1) Structural Arch Culverts, including recommended footings.

(2) Spill Prevention, Control and Countermeasures Plan (SPCC)

Shop drawings shall be submitted electronically via email or other electronic means, in such a manner that clear and legible copies can be made and each drawing and calculation sheet shall include the project name, number and other identification shown on the contract plans.

104.04 Coordination of Contract Documents. Delete in its entirety.

Section 105. – CONTROL OF MATERIAL

105.02 Material Sources. Delete (a) Government-provided sources in its entirety.

105.03 Material Source Management. Delete in its entirety.

Section 106. -- ACCEPTANCE OF WORK

106.07 Partial and Final Acceptance.

(a) Partial Acceptance. Delete the first paragraph.

Section 107. -- LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

107.01 Laws to be Observed. Delete in its entirety.

107.02 Protection and Restoration of Property and Landscape. Delete the text and replace with the following:

Follow the requirements of FAR Clause 52.236-9 Protection of Existing Vegetation, Structures, Equipment, and Improvements. FAR Clause 52.236-9 is supplemented as follows:

Preserve public and private property and protect land monuments and property markers. When necessary to destroy a monument, use a licensed land surveyor to reference and reestablish the monument according to State requirements.

Do not disturb the area beyond the construction limits.

BLM SALEM DISTRICT OFFICE Page 10 of 69

107.04 Railroad Protection. Delete in its entirety.

107.05 Responsibility for Damage Claims. Delete in its entirety.

107.06 Contractor’s Responsibility for Work. Delete in its entirety.

107.08 Sanitation, Health, and Safety. Delete in its entirety.

107.09 Legal Relationship of the Parties. Delete in its entirety.

107.10 Environmental Protection. Delete in its entirety and replace with the following:

In performance of the contract, the contractor shall not operate any equipment that is leaking or that is lacking spark arrestors that meet the requirements of State of Oregon Regulations. The contractor shall follow laws and regulations related to the Endangered Species Act and other laws and regulations that may be in place that may regulate the contractors operations in order to protect the environment. (See attachment

(a) Work Schedule

The contractor shall not perform any work on the site prior to August 5 th

, 2015, at the Tobe Creek Site, in order to protect critical habitat near the work site.

(b) In- Stream Work

The Contractor shall perform all in-stream portions of work during the ODF&W In-Stream Work Period ending August 31 st , 2015. Refer to ODF&W 2008 Oregon guidelines for timing of in-water work to protect fish and wildlife resources.

The following in-stream permits apply to this project and the contractor shall incorporate the permit conditions into the project.

Department of State Lands (DSL) Permit # 42104-RF

United States Army Corps of Engineers Regional General Permit (RGP) # NWP-2007-00999

(c) Spill Prevention

The contractor shall have a Spill Prevention, Control and Countermeasures Plan (SPCC) in place before performing any operation on lands managed by the BLM. In the event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, shall immediately implement the SPCC Plan and shall immediately notify the government (typically the COR or PI). The Salem District will initiate its Hazardous Materials Contingency Plan and/or Spill Containment Plan and reporting requirements. The Contractor may be responsible for any or all costs associated with this level of effort.

The Contractor’s SPCC Plan shall be developed as defined under 40 CFR, Part 112. The SPCC Plan shall be reviewed and approved by the Contracting Officer. The SPCC Plan shall contain the following information:

1. Response Priorities

2. Contractor Representative in Charge

3. Duties of Contractor Personnel

4. Contractor Emergency Response Procedures

5. Contents of Spill Containment Kit (SCK)

6. Spill Response Diagram

The Contractor shall have a Spill Containment Kit (SCK), as described in the SPCC, on-site during any operation and provide training to employees on how components of the SCK are used. The SCK must be designed for use with petroleum products, and must contain, as a minimum, the following items:

BLM SALEM DISTRICT OFFICE Page 11 of 69

1. Two Bales (4 Booms/Bale, of 8" dia. X 10’ length Oil-only Absorbent Booms)

2. Two Bales (100 Pads/Bale, of Oil-only Absorbent Pads, minimum of 17"x19"x1/4")

3. One Oil-only Absorbent Sweep (minimum of 18" dia. X 100' length)

4. One Floating On-Water Containment Boom (minimum 18” width x 100’ length) (only required for in-stream or riparian work within 50 feet or less of a waterway.)

5. Gloves (PVC and Latex), Goggles, and Garbage Bags sufficient to contain soiled absorbents.

The Contractor shall implement the Emergency Response Actions described in the SPCC plan. Those actions include, but are not limited to, immediate action to protect employee health and safety, immediate action to stop the flow of product from the equipment, removal of equipment from the waterway if required and/or possible, deployment of the absorbent booms and pads downstream from the equipment, and any other immediate action as specified by Federal and/or State On-Scene Coordinators or his/her representative. The Contractor shall be responsible for cleanup/removal and proper disposal of contaminated materials from the site.

(d) Endangered Species

The Government may direct the Contractor to discontinue all operations in the event that:

a) Threatened, or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, may be affected by the operation, and a determination is made that consultation or reinitiation of consultation is required concerning the species prior to continuing operation, or;

b) Federal candidate (Categories 1 and 2), sensitive or State listed species protected under BLM Manual 6840 -

Special Status Species Management, have been discovered, and a determination is made that continued operations would affect the species or its habitat, or;

c) Species have been discovered which were identified for protection through survey and manage and/or protection buffer standards and guidelines established in the April 13, 1994, Record of Decision for Amendments to Forest Service and Bureau of Land Management Planning Documents Within the Range of the Northern Spotted Owl or in a subsequently adopted resource management plan applicable to the land involved in this contract, and a determination is made that continued operations would affect the species or its habitat, or;

d) Other active raptor or owl nests have been discovered, and a determination is made that continued operations under this contract would adversely affect the present use of the discovered nesting area by the raptor or owl.

107.11 Protection of Forests, Parks, and Public Lands. Delete in its entirety.

Section 108. -- PROSECUTION AND PROGRESS

Delete this section in its entirety.

Section 109. -- MEASUREMENT AND PAYMENT

109.02 Measurement Terms and Definitions. Modify as follows:

(b) Contract quantity. Delete in its entirety.

109.05 Scope of Payment. Delete in its entirety.

BLM SALEM DISTRICT OFFICE Page 12 of 69

109.06 Pricing of Adjustments. Delete in its entirety.

109.07 Eliminated Work. Delete in its entirety.

109.08 Progress Payments. Delete in its entirety.

109.09 Final Payment. Delete in its entirety.

DIVISION 150

PROJECT REQUIREMENTS

Section 151. – MOBILIZATION

Description

Delete in its entirety and replace with the following:

151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on BLM lands, according to the requirements within.

Construction Requirements

Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the BLM will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off of BLM administered lands.

All mechanized equipment shall be steam-cleaned before being used below ordinary high water until all visible external oil, grease, mud, and other visible contaminants are removed.

Measurement

Delete in its entirety and replace with the following:

151.02 All costs associated with the initial and subsequent cleaning of equipment shall be included in the unit bid price for Mobilization. Measure Mobilization according to Subsection 109.02.

Payment

Delete in its entirety and replace with the following:

151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Progress payments for mobilization lump sum will be allowed as follows:

(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under

Fixed-Price Construction Contracts, after receipt of the evidence of payment.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.

Section 152. — CONSTRUCTION SURVEY AND STAKING

BLM SALEM DISTRICT OFFICE Page 13 of 69

152.03 Survey and Staking Requirements. Delete items (a) to (k) and substitute the following:

Perform all survey, staking, recording of data, and calculations as necessary to construct the project from the initial layout to final completion.

(a) Control Points. Relocate initial horizontal and vertical control points in conflict with construction to areas that will not be disturbed by construction operations. Furnish the coordinates and elevations for the relocated points before the initial points are disturbed.

(b) Slope Stakes and References. Establish reference markers to assure cut and fill slopes are constructed properly.

(c) Centerline Re-establishment. Re-establish road and waterway centerline from instrument control points.

(d) Culverts. Set adequate horizontal and vertical control and reference points for all components.

(e) Clearing Limits. Clearing limits shall be staked five (5) feet beyond the catch points of all earthwork area.

152.06 Payment. Delete this Subsection in its entirety and replace with the following:

Contractor Construction Surveying and Staking is considered incidental to Pay Items 204(01), 204(02), 601(01) and 601(02), no additional payment will be made.

Section 154. — CONTRACTOR SAMPLING AND TESTING

154.02 Sampling.

Delete this Subsection in its entirety and replace with the following:

Sample material to be tested in accordance to the items required to be tested in Subsection 154.03.

154.03 Testing.

Delete the first sentence and replace with the following:

Testing to be conducted in accordance to acceptable industry procedures.

Add the following:

Testing for items associated with the culvert to be in accordance with procedures determined by the manufacture of the Structural Plate Structure to be constructed as part of this project.

Furnish test results to the CO immediately after completing the test. The requirements for furnishing test results do not include sampling aging or curing time; therefore, reporting times will be extended accordingly.

For aggregate and base materials, contractor shall submit testing of aggregates and certify that the materials meet project requirements. For compaction, the contractor shall demonstrate that the material is compacted sufficiently so that a fully loaded dump truck does not visibly displace the materials.

154.07 Payment. Delete this Subsection in its entirety and replace with the following:

Contractor Sampling and Testing is considered incidental to Pay Items 251(04), 251(05), 301(01), 301(02), 301(03), 301(04), 601(01), and 601(02), no additional payment will be made.

BLM SALEM DISTRICT OFFICE Page 14 of 69

Section 156. – PUBLIC TRAFFIC

156.03 Accommodating Traffic During Work. Supplement this section with the following:

The Contractor shall perform work in a manner that the exiting road remains open during construction of the Feagles Site.

The Contractor may close the road at the Tobe Site, but the mainline road adjacent to the project shall remain open.

156.10 Measurement and Payment. Delete this Subsection in its entirety and replace with the following:

Work required under this section will not be measured and is considered incidental to applicable Pay Items, no additional payment will be made.

Section 157. – SOIL EROSION CONTROL

157.04 Controls and Limitations on Work. Supplement this section with the following:

The Contractor shall submit an Erosion Control Plan for approval. The Erosion Control Plan shall completely detail how the contractor will control sediment and protect downstream water quality. The plan shall incorporate requirements detailed in the Plan Sheets. The plan shall be submitted no less than 7 days before any work that disturbs the site.

157.09 Diversions. Delete in its entirety and substitute the following:

The contractor shall implement the Dewatering Plan and the Re-Watering Plan as detailed in the Plans.

Measurement

157.15 Delete in its entirety and substitute the following:

Soil erosion control measures include all work required to support the Erosion Control Plan, the Dewatering Plan, the Re-watering Plan, any sediment fence, unsupported sediment fence, aggregate construction entrances, check dams, dewatering structure and associated materials for impounding and transmitting flows, or any other work required under this section.

Payment

157.16 Delete in its entirety and substitute the following:

Section 157 Temporary erosion control measures are considered incidental to Pay Items 204(01), 204(02), 251(01), 251(02), 251(03), 251(04), 251(05), 601(01), and 601(02), no additional payment will be made.

DIVISION 200

EARTHWORK

Section 201. – CLEARING AND GRUBBING

201.01 Description

Replace with the following:

This work consists of clearing and grubbing within clearing limits as shown in the plan or as determined under Section 152.

201.04 Clearing.

Supplement with the following:

(f) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.

(g) Trees shall be removed with stumps intact, as much as possible and shall be placed along the existing stream

BLM SALEM DISTRICT OFFICE Page 15 of 69 at locations designated by the COR, outside of the stream channel.

(h) Woody debris to be scattered onsite as designated by the COR.

201.06 Disposal

Replace with the following:

(a) Top Soil to be utilized as cover material for disturbed areas within the clearing limits.

(b) Trees shall be removed with stumps intact and placed on final slopes.

(c) Woody debris to be scattered onsite in an area designated by the COR.

(d) Excess material to be incorporated into designated disposal areas, fill slopes and riprap cover.

201.09 Payment. Delete in its entirety and substitute the following:

Work under this section is considered incidental to Pay Items 204(01) and 204(02), no additional payment will be made.

Section 203. – REMOVAL OF STRUCTURES AND OBSTRUCTIONS

203.01 Description. Delete in its entirety and substitute the following:

This work consists of the removal and disposal of a metal culverts.

203.05 Disposing of Material.

(a) Remove from project. Add the following: Removed culverts/pipe structures shall become the property of the Contractor and shall be removed from the project site.

(b) Burn. Delete in its entirety.

(c) Bury. Delete in its entirety.

203.08 Payment. Delete in its entirety and substitute the following:

Work under this section is considered incidental to Pay Items 204(01) and 204(02), no additional payment will be made.

Section 204. – EXCAVATION AND EMBANKMENT

204.01 Description Replace with the following:

This work shall consist of excavating material, reserving the most suitable material for embankment construction, embankment construction, reshaping the existing streambed materials, placing conserved topsoil. This includes hauling, stockpiling, placing, sloping, shaping, compacting, and finishing earthen and rocky materials. The work shall also include disposing of waste material at the disposal site shown in the plans.

204.05 Conserved Topsoil Add the following:

Contractor shall reserve organic soils with woody debris to be utilized as cover material for disturbed areas within the clearing limits.

The contractor shall place reserved topsoil on the top 4-feet of slope, including over any riprap. The thickness over the riprap shall be at least one foot.

204.10 Embankment Construction.

BLM SALEM DISTRICT OFFICE Page 16 of 69

(b) Embankment within the roadway prism. Delete in its entirety and substitute the following:

Place embankment material in horizontal layers not exceeding 12 inches in compacted thickness. Remove boulders and rock fragments exceeding 12 inches in diameter and stockpile for use as riprap or stream features.

(c) Individual rock fragments and boulders. Delete in its entirety.

Measurement

204.16 Delete in its entirety and substitute the following:

All Excavation and Embankment under this section is measured by lump sum. The measurement shall include all work in the roadway prism, all work to contour the existing streambed materials as shown in the plans, and all work to haul, dispose of, and shape excess materials at the disposal site.

All work to supply, haul, place and compact Select Borrow material shall be measured by the Cubic Yard in the hauling vehicle.

204.17 Payment. Delete in its entirety and substitute the following:

Requirements under this section shall be paid at the contract price.

Section 209. – STRUCTURE EXCAVATION AND BACKFILL

209.13 Measurement. Delete in its entirety and substitute the following:

Work under this section will not be measured.

209.14 Payment. Delete in its entirety and substitute the following:

Structure Excavation and Backfill is incidental to Pay Items 204(01) and 204(02), no additional payment will be

DIVISION 250

SLOPE REINFORCEMENT AND RETAINING WALLS

Section 251. — Riprap

251.01 Description.

Supplement the first paragraph with the following:

This section also includes Vein Rock and Streambed Materials.

Replace the second paragraph with the following:

A) Riprap Class 400 is designated in the following table:

Class Percent of Rock by Mass Mass (Pounds) Approximate

Dimensions (Inches) 400 20.0 290 - 400 18 - 20

30.0 130 - 290 14 - 18

40.0 15 - 130 7 - 14

10.0 – 0.0 0 - 15 0 - 7

B) Vein Rock consists of large steam boulders ranging in size of 2-feet to 2.5-feet diameter. Select boulders

BLM SALEM DISTRICT OFFICE Page 17 of 69 that have minimal fractured surfaces and are generally rounded without sharp edges.

C) Streambed Materials Streambed Materials shall be a mixture of coarse river rock and finer silt/sand materials.

1. Coarse material shall be clean, uncrushed river rock from a commercial supplier meeting the following gradation:

Gradation – Streambed Mix for Upper Site

Sieve Size (Inches) Percent Passing (by weight)

12” 90-100% 6” 79-89% 3” 45-55% 2” 29-39% #4 4-14%

2. Fine material shall be clean durable sand and river gravel. The material shall be free from overburden, spoil, shale and organic material.

Gradation – Streambed Mix for Upper Site

Sieve Size (Inches) Percent Passing (by weight)

3/4” 100% #40 51%

When placing the streambed mix, the contractor shall reserve 1/3 of the fine materials for placement in the channel when reintroducing the diversion, in order to fill voids and seal water from flowing subsurface.

251.08 Measurement.

Delete the reference to riprap measurement and replace with the following:

Measure Riprap Class 400 by the Ton, provide tickets from certified scale.

Measure Vein Rock by lump sum.

Measure Streambed Materials by the Ton, provide tickets from certified scale.

251.09 Payment.

DIVISION 300

AGGREGATE COURSES

Section 301. – UNTREATED AGGREGATE COURSES

301.01 Description. Supplement with the following:

This work consists of constructing courses of surface course aggregate and courses of sub-base aggregate.

301.02 Material. Supplement with the following:

Surface Course Aggregate shall be a dense graded 1-1/2” aggregate from a commercial source that is a

BLM SALEM DISTRICT OFFICE Page 18 of 69 supplier for forest road construction.

Subbase shall be a 6” graded base rock from a commercially available source that is a supplier for forest road construction.

Construction Requirements

301.04 Mixing and Spreading. Delete in its entirety and substitute the following:

(a) Preparation: The Contractor shall prepare the subgrade for aggregate subbase placement by blading out any surface irregularities before the aggregate subbase and surface courses are placed. The subgrade shall be roller compacted until visible displacement ceases.

(b) Placement: Place compacted depth of aggregate subbase course in lifts of four (4) inches each and the surface course in four (4) inch lifts. See 301.05 for compaction requirements.

(c) Grading: The aggregate shall be graded uniformly over the entire width of the surface to the required thickness as shown in the plans.

301.08 Acceptance. Delete the first sentence.

301.08(a) Aggregate gradation. Delete in its entirety.

301.09 Measurement. Add the following:

Surface Course Aggregate (1-1/2”) shall be measured by the Ton. The contractor shall submit weight tickets from a certified scale.

Base Rock (6”) shall be measured by the Ton. The contractor shall submit weight tickets from a certified scale.

301.10 Payment. Add the following:

DIVISION 600

INCIDENTAL CONSTRUCTION

Section 601. – MINOR CONCRETE STRUCTURES

601.01 General. Supplement with the following:

This work consists of constructing culvert footings meeting the Structural Plate Structure Manufacturer’s requirements.

601.08 Measurement. Supplement with the following:

Work under this section shall be measured by Cubic Yards in the Structure.

601.9 Payment. Supplement with the following:

Section 602. – CULVERTS AND DRAINS

602.03 General. Supplement with the following:

BLM SALEM DISTRICT OFFICE Page 19 of 69

Culvert locations will be field staked by the government.

Furnish a 16 Gauge, 24-inch dia. Galvanized CMP crossover drain pipe, approximately thirty four feet (34) length.

To be placed with minimal 18” cover under the road surface, at a 10% drain slope.

Drain pipe shall be bedded with surface aggregate.

Refer to Subsection 707.02, Metallic-coated corrugated steel pipe

602.09 Measurement. Supplement with the following:

Work under this section shall be measured lump sum.

602.10 Payment. Supplement with the following:

Section 603. – STRUCTURAL PLATE STRUCTURES

603.06 Measurement. Supplement with the following:

Work under this section shall be measured lump sum.

603.07 Payment. Supplement with the following:

Section 625. – TURF ESTABLISHMENT

625.01 Description. Delete in its entirety and replace with the following:

Government shall provide and the contractor shall apply seed and mulch to all disturbed areas within the clearing limits. Contractor shall be liable for covering excessive disturbed areas outside of the clearing limits.

625.12 Payment. Add the following:

Requirements under this section are considered incidental to Pay Item 204(01) and 204(02), no additional payment will be made.

Section 635. – TEMPORARY TRAFFIC CONTROL

635.01 Description. Supplement with the following:

Road closure signs and Type III Barricades shall be placed at the Tobe Site.

635.27 Payment. Delete and replace with the following:

Requirements under this section are considered incidental to Pay Item 151(01) and no additional payment will be

CONSTRUCTION SPILL PROVISIONS:

PART 2: PRODUCTS

A. Spark Arresters: Shall meet the requirements of the State of Oregon’s regulations.

PART 3: EXECUTION

3.01 HAZARDOUS MATERIAL CONTAINMENT/CLEANUP

A. During contractor operations on lands managed by the BLM, in event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, the Contractor shall immediately implement the SPCC plan as referenced herein and notify the on-site Government Contract Representative (COR or PI). The Government Representative will initiate the District’s

BLM SALEM DISTRICT OFFICE Page 20 of 69

Hazardous Materials Contingency Plan and/or Spill Containment Plan reporting requirements. The Government Representative will remain on scene until relieved by the District Hazardous Materials Management Coordinator (HMMC) or his/her representative.

B. Spill Prevention, Control, and Countermeasure Plan (SPCC): The Contractor shall develop an SPCC Plan as defined under 40 CFR Part 112. The SPCC Plan will be reviewed and accepted by the Contracting Officer prior to initiating project work. The SPCC Plan shall, as a minimum, contain the following information:

1. Response Priorities

2. Contractor Representative in Charge

3. Duties of Contractor Personnel

4. Contractor Emergency Response Procedures

5. Contents of Spill Containment Kit (SCK)

6. Spill Response Diagram

Upon request, an example of a SPCC may be obtained from theSalem District Environmental Protection Specialist for Hazardous Materials.

C. Spill Containment Kit (SCK): The Contractor shall have a SCK, as described in the SPCC, on-site during any operation and provide training to employees on how components of the SCK are used. The SCK must be designed for use with petroleum products, and must contain, as a minimum, the following items:

1. Two Bales (4 Booms/Bale, of 8" dia. X 10’ length Oil-only Absorbent Booms)

2. Two Bales (100 Pads/Bale, of Oil-only Absorbent Pads, minimum of 17"x19"x1/4")

3. One Oil-only Absorbent Sweep (minimum of 18" dia. X 100' length)

4. One Floating On-Water Containment Boom (minimum 18” width x 100’ length) (only required for in-stream or riparian work within 50 feet or less of a waterway.)

5. Gloves (PVC and Latex), Goggles, and Garbage Bags sufficient to contain soiled absorbents.

D. The Contractor shall implement the Emergency Response Actions described in the SPCC plan. Those actions include, but are not limited to, immediate action to protect employee health and safety, immediate action to stop the flow of product from the equipment, removal of equipment from the waterway if required and/or possible, deployment of the absorbent booms and pads downstream from the equipment, and any other immediate action as specified by Federal and/or State On-Scene Coordinators or his/her representative. The Contractor shall be responsible for cleanup/removal and proper disposal of contaminated materials from the site.

E. If the HMMC determines that additional resources are needed, the HMMC will implement the District’s Hazardous Materials Contingency Plan and the District Spill Containment Plan. The Contractor may be responsible for any or all costs associated with this level of effort. The amount of actual damage will be deducted by the Government from the amount due the Contractor prior to final payment.

(End of Section C)

BLM SALEM DISTRICT OFFICE Page 21 of 69

SECTION E – INSPECTION AND ACCEPTANCE

The following clauses are incorporated by reference:

52.246-12 INSPECTION OF CONSTRUCTION AUG 1996

(End of Section E)

BLM SALEM DISTRICT OFFICE Page 22 of 69

SECTION F – DELIVERIES OR PERFORMANCE

1.0 PERIOD OF PERFORMANCE

See clause 52.211-10 in Contract Clauses section.

2.0 PROGRESS PLAN

At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details it’s proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.

(End of Section F)

BLM SALEM DISTRICT OFFICE Page 23 of 69

SECTION G – CONTRACT ADMINISTRATION DATA

G.1.0 CONTRACTING OFFICER'S REPRESENTATIVE DEFINITION

The “Contracting Officer’s Representative (COR)” is delegated expressed limited authority by the Contracting Officer to assist in the technical monitoring and administration of the contract.

G.2.0 RESPONSIBILITIES OF THE CONTRACTING OFFICER'S REPRESENTATIVE

G.2.1 The COR’s authorities and responsibilities are defined in the COR’s Designation Letter. The COR is authorized to clarify technical requirements, and to review and approve work which is clearly within the scope of work. The COR is NOT authorized to issue changes or modify the scope of work in any way.

G.2.2 The COR is responsible for verifying the Contractor’s compliance with the technical specifications, drawings, work schedule, and labor provisions at the site of the work.

The following local clauses are provided in full text:

CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (JULY 2010)

(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR42.15.

(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

(c) We request that you furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.

(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at http://www.cpars.csd.disa.milJ. The CPARS User Manual, registration for On Line Training for Contractor Representatives, and a practice application may be found at this site.

(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation, and the report will be accessible at http://www.cpars.csd.disa.mil/. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official's narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1 - 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating ''No comment" in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign http://www.cpars.csd.disa.milj/ http://www.cpars.csd.disa.mil/

BLM SALEM DISTRICT OFFICE Page 24 of 69 and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment." Your response is due within 30 calendar days after receipt of the CPAR.

(f) The following guidelines apply concerning your use of the past performance evaluation:

(1) Protect the evaluation as "source selection information." After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.

(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.

(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30- day review period.

(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of clause)

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)

(APR 2013)

Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).

“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Invoice billed according to contract line items and rates.

2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.

3. If partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.

4. If final payment is billed, the last invoice shall state “FINAL”.

5. Contractor’s Release of Claims shall be submitted with the final invoice.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contract (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

https://www.ipp.gov/ mailto:ippgroup@bos.frb.org

BLM SALEM DISTRICT OFFICE Page 25 of 69

(End of Local Clause)

(End of Section G)

BLM SALEM DISTRICT OFFICE Page 26 of 69

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1.0 WORK HOURS

Unless otherwise specified in Section C, Specifications, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be done on Saturday, Sunday, or Federal holidays unless authorized by the COR.

H.2.0 ENVIRONMENTAL INTERRUPTION OF WORK

H.2.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. An allowance has been included in the contract time for all environmental delays.

This is the start of the file's text. The full file is on GovTribe.