II. A. Solicitation 70LGLY26RSSB00004 Modular Classroom Roof Repairs Various.pdf

PDF 967 KB Posted

Attached to
Modular Classroom Roof Repairs Various Federal contract opportunity
Solicitation number
70LGLY26RSSB00004
Issued by
Department of Homeland Security Federal Law Enforcement Training Center

About this file

This is a Request for Proposal (RFP) for modular classroom roof repairs at the Federal Law Enforcement Training Center (FLETC) in Glynco, Georgia. The procurement is a 100% small business set-aside for SBA Region IV (Georgia, Alabama, South Carolina, Florida, Mississippi, Kentucky, North Carolina, and Tennessee). The contract will be awarded as a Single Firm Fixed Price contract with a construction magnitude between $1,000,000 and $5,000,000. The work involves repairing or replacing EPDM roofing systems on 14 modular classroom buildings (numbered 702, 709, 711, 712, 713, 714, 743, 744, 747, 759, 768, 774, 797, and 902) and releveling one modular unit that has settled. The performance period is 365 calendar days following issuance of the Notice to Proceed, with a mandatory completion requirement of 120 calendar days after notice to proceed. Proposals are due by 11:00 A.M. Eastern Time on March 3, 2026, and must be submitted electronically to Shannon.Anthony@fletc.dhs.gov. The contracting officer is Shannon Anthony. A mandatory site visit is scheduled for February 11, 2026, at 10:00 A.M. at Building 200, FLETC.

Proposals will be evaluated on three factors of equal importance: Past Performance (Superior, Satisfactory, Neutral, or Unsatisfactory ratings based on PPIRS/CPARS records), Corporate Relevant Experience (Superior, Good, Acceptable, Marginal, or Unsatisfactory ratings based on submission of two to four past performance questionnaires for projects over $1,000,000 involving similar roofing materials completed within five years, plus copies of licenses and certifications specific to roofing installation), and Price. Award will be made using the "Best Suited Then Negotiate" methodology. To be eligible for award, offerors must obtain a minimum satisfactory rating for Past Performance and an Acceptable rating for Corporate Relevant Experience. Performance and payment bonds equal to 100% of the contract price are required within 10 calendar days of award. The appropriate wage determination is GA20260315 dated January 23, 2025. The NAICS code is 238160 (Roofing Contractors) with a small business size standard of $19 million.

View the file

Other files for this federal contract opportunity

Other files attached to Modular Classroom Roof Repairs Various, newest first.
File Type Posted
Att 011 DHS 11000-6 Non-Disclosure Agreement - Copy.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

26GVARIC02

DEPARTMENT OF HOMELAND SECURITY

FEDERAL LAW ENFORCEMENT TRAINING CENTERS

1131 CHAPEL CROSSING RD

GLYNCO GA 31524

70LGLY

Federal Law Enforcement Training Center

Building 681 Attn: S. Anthony

1131 Chapel Crossing Glynco GA 31524

Shannon Anthony 912-261-3630

1x 02/02/2026

70LGLY26RSSB00004

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This Request for Proposal will result in a Single Firm Fixed Price Contract Award for Modular Classroom Roof Repairs - Various at Federal Law Enforcement

Training Center, Glynco GA.

The contract will be procured as a 100% total small business set-aside to SBA Region

IV (Georgia, Alabama, South Carolina, Florida, Mississippi, Kentucky, North

Carolina, and Tennessee).

The Government will utilize the acquisition strategy Best Suited Then Negotiate when analyzing proposals. The Government will also utilize Federal Acquisition Regulation procedures (FAR) 15.404, Price Negotiation when evaluating Offeror’s proposal.

The construction magnitude for this requirement is between $1,000,000 and

$5,000,000.00.

The contract duration will be for a period not to exceed 365 calendar days after issuance of Notice to Proceed.

The North American Industry Classification System (NAICS) Code for this solicitation

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

1 365 calendar days and complete it within ________________ ________________ calendar days after receiving

03/03/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

DEPARTMENT OF HOMELAND SECURITY

FEDERAL LAW ENFORCEMENT TRAINING CENTERS

1131 CHAPEL CROSSING RD

PRO BLDG 681

70LGLY

GLYNCO GA 31524

Shannon Anthony

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 82

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

70LGLY26RSSB00004

shall be 238160 Roofing Contractors.

A site visit is scheduled for February 11,2026, at

11:00am at FLETC Building 200. Upon arrival, attendees should report to the commercial gate a minimum of 30 minutes prior to the application screening process, then proceed to Building 200.

All personnel who are not currently badged will need to complete and return Day Pass applications for all attendees no later than

February 10,2026, at 10:00am to the attention of

Project Manager, Emerson Floyd at

Emerson.Floyd@fletc.dhs.gov Please coordinate receipt of badge applications and submission with

Mr. Floyd.

Delivery: 365 Days After Award

Delivery Location Code: FLETC GL

DEPARTMENT OF HOMELAND SECURITY

FEDERAL LAW ENFORCEMENT TRNG CTR

1131 CHAPEL CROSSING RD

ATTN: BLDG:

GLYNCO GA 31524

Period of Performance: 03/20/2026 to 03/19/2027

0001 This is a Firm-Fixed Price CLIN Building 904 The 1 EA

Contractor shall level modular due to settling and replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0002 This is Firm-Fixed Price CLIN. Building 709 The 1 EA

Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0003 This is a Firm Fixed Price CLIN. Building 711 1 EA

The Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

4 82

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

70LGLY26RSSB00004

0004 This is a Firm Fixed Price CLIN. Building 743, 1 EA

The Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0005 This is a Firm Fixed Price CLIN. Building 744, 1 EA

The Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0006 This is a Firm-Fixed Price CLIN. Building 747, 1 EA

The Contractor shall replace the roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0007 This is a Firm-Fixed Price CLIN. Building 768, 1 EA the Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0008 This is a Firm Fixed Price CLIN. Building 774 1 EA

The contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0009 This is a Firm-Fixed Price CLIN. Building 797 The 1 EA

Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0010 This is a Firm Fixed Price CLIN. Building 902, 1 EA

The Contractor shall replace roof due to leaks.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

5 82

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

70LGLY26RSSB00004

OF OFFICE BUILDINGS

0011 This is a Firm Fixed Price CLIN. Building 759, 1 EA the Contractor shall replace roof due to leaks

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0012 This is a Firm Fixed Price CLIN. Bui8lding 712, 1 EA

The Contractor shall remove existing sealant on seams, prep and re-coat seams.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0013 This is a Firm Fixed Price CLIN. Building 713, 1 EA

The contractor shall remove existing sealant on seams, prep and re-coat seams.

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

0014 This is a Firm Fixed Price CLIN. Building 714, 1 EA

The Contractor shall

Product/Service Code: Z2AA

Product/Service Description: REPAIR OR ALTERATION

OF OFFICE BUILDINGS

Submission of your invoice certifies that all employees and subcontractors have been notified of the United States Government's zero tolerance policy regarding trafficking in persons, and the actions that will be taken for violations of this policy.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

B - Supplies or Services/Prices

Clauses

See Continuation Sheet, Standard Form 1442. Also, please refer to Exhibit A for completion of the Bid Schedule and proposal breakdown

C - Description/Specifications

The contractor will furnish all labor, materials, equipment, and supervision necessary to accomplish the work detailed herein. The contractor will also verify all quantities, dimensions, and site conditions in the field. The contractor will supply all supplemental and related miscellaneous work to comply with the scope of work as indicated in the Specifications, Statement of Work, and/or Contract.

The contractor shall provide all labor, materials, tools, equipment, and supervision necessary to repair or replace EPDM (Ethylene Propylene Diene Monomer) roofing systems and relevel a modular classroom utilized for agency training. The work includes removing damaged roofing materials, inspecting and repairing underlying structures, installing new EPDM membranes, and releveling a modular classroom to ensure structural stability and proper alignment. Modular roofs 904, 902, 709, 743, 744, 747, 759, 768, 774, 711, 797, 712, 713, and 714. Prepare the site described herein for the repair and installation of roofs on various modular classrooms. Please refer to SOW Attachment 1 for a detailed project description.

See Section J, Attachment 1 for the complete technical requirements associated with this action.

D - Packaging and Marking

D.1 Packing and Marking

(a) All shipments of materials, equipment and/or supplies to the project site shall be addressed to the Contractor and not the U. S. Government. Preservation, packaging and packing shall be in accordance with standard practices for commercial packaging.

(b) Government personnel are not authorized to accept deliveries for the contractor, nor are they responsible for off-loading shipments. A contractor representative must be present to accept deliveries.

D.2 Payment and Postage and Fees

a) The Contractor shall pay all postage and fees related to submitting information (including forms, reports, etc.) to the Contracting Officer.

E - Inspection and Acceptance

52.246-12 Inspection of Construction. (AUG 1996)

52.246-21 Warranty of Construction. (MAR 1994)

F - Deliveries or Performance

F.1 Existing Furniture, Equipment, and Materials

The Contractor shall move all furniture, equipment, and materials for access to work.

Upon completion of work, such items shall be repositioned to their original location.

Personal items, computers, telephones, audio-visual equipment, and facsimile machines will be removed by the Government. All other items will be removed and replaced by the Contractor. Some offices are fully furnished and others are less congested. It will be the Contractor's responsibility to remove and replace, or if unable to remove the furniture, to cover and protect, all furniture for the duration of the task order.

Additional compensation may be negotiated for rooms that are considered “libraries’ or “volume storage areas.”

F.2 Occupancy of Premises

The premises may be occupied during the performance of the work.

F.3 Submittals & Preconstruction Conference

Submittals are due no later than 14 calendar days after award. For more information regarding submittals, please see Attachment 1, Scope of Work and Submittal Specifications.

Clauses

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after the date the Contractor receives the notice to proceed.

The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-13 Time Extensions. (SEP 2000)

52.242-17 Government Delay of Work. (APR 1984)

G - Contract Administration Data

G.1 Accounting and Appropriation Data

Funds have been reserved for this acquisition. The accounting appropriation data applicable for this acquisition will be provided in any resulting contract.

G.2 Identification of Correspondence

All correspondence and data submitted by the Contractor under this contract will reference the contract number and title.

G.3 Contracting Officer

The Contracting Officer (CO) for award of the contract will be Shannon Anthony from the office listed below:

FLETC, Procurement Division Specialized Services Branch (SSB) Bldg 681, 1131 Chapel Crossing Road Brunswick, GA 31524

The Contracting Officer (CO) for administration of the contract will be Shannon Anthony.

G.4 Payment Office Address

Department of Homeland Security FLETC Finance Division/Contract Payments Building 681 (BFD) Glynco, Georgia 31524 (See G.8, Invoices)

G.5 Contracting Officer

The Contracting Officer has the overall responsibility for the administration of this contract. All communication pertaining to contractual or administrative matters under the contract shall be addressed to the Contracting Officer. The Contracting Officer alone, without delegation, is authorized to take actions on behalf of the Government to amend, modify or deviate from the contract terms, conditions, requirements, specifications, details and/or schedules. However, he may delegate certain other responsibilities to his authorized representatives.

G.6 Designation of Contracting Officer’s Representative

As indicated in Homeland Security Acquisition Regulation (HSAR) clause 3052.242-72, Contracting Officer’s Representative, the Contracting Officer will designate a Contracting Officer's Representative (COR) to perform functions under the contract such as review or inspection and acceptance of services, and other functions of a technical nature. The Contracting Officer will provide a written notice of such designation to the Contractor within five working days after contract award. The designation letter will set forth the authorities and limitations of the COR under the action. The Contracting Officer cannot authorize the COR or any other representative to sign documents, such as contracts, contract modifications, etc., that require the signature of the Contracting Officer. In no event, will any matter deviating from the terms of this contract be effective or binding unless formalized by contractual documents executed by the Contracting Officer.

The Contracting Officer for this contract should be informed as soon as possible of any actions or inaction by the Contractor or the Government which could change any of the terms, conditions, or completion times stated in the contract. On all matters pertaining to contract terms, the Contractor must communicate with the Contracting Officer.

Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If a disagreement exists as to contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without contractual coverage could result in nonpayment.

G.7 Bonds – 52.228-1 Bid Guarantee (SEP 1996) (Not required for subject requirement)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds-

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be [20%] percent of the bid price or $3,000,000.00 the amount of the proposed price, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee. 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)

(a) Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.

(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.

(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.

G.8 Payment & Performance Bond (REQUIRED for subject requirement)

a. Performance and Payment bonds. The Contractor shall be required to provide both payment and performance bonds.

b. Penal sums. The penal sums of the performance and payment bonds shall equal one hundred percent (100%) of the contract price.

c. The Contractor shall furnish all bonds or alternative payment protection no later than ten (10) calendar days after receipt of the notice of award. The furnishing of bonds is a part of contract performance and failure to provide bonds within the time specified shall be grounds for default.

G.9 Individual Surety

a. As prescribed in FAR 28.200, individual sureties are acceptable for all types of bonds except position schedule bonds. In order for the Contracting Officer to determine the acceptability of individuals proposed as sureties, all bidders/offerors who submit bonds which are executed by individual sureties are required to furnish the following information in support of SF 28, Affidavit of Individual Surety, with the bond(s):

1. A complete description of real property offered, supported by proof of title, such as by title opinion or abstract of title, and a certified appraisal or tax assessment;

2. C.P.A. certified balance sheet(s) and income statement(s) with a signed opinion for each individual surety;

3. Independent certified appraisal of net value of property offered;

4. Independent Certification by licensed attorney or Title Company of liens or other encumbrances which exist against all property listed;

5. A current list of all other bonds on which the individual is a surety and bonds for which the individual is requesting to be a surety, together with a statement as to the percent completion of these bonded jobs.

6. Copy of latest Federal and State Income Tax returns including all schedules.

b. This information is necessary to enable the Government to evaluate the sufficiency of the surety. Failure to furnish this information may result in non-approval of the surety and a determination of non-responsibility.

G.10 Irrevocable Letter of Credit

As prescribed in FAR 28.204-3, an Irrevocable Letter of Credit is acceptable for all types of bonds, if all provisions of FAR 28.204-3 and FAR -14 are met. FAR -14 requires a specific format for the Irrevocable Letter of Credit and the letter from the Financial Institution confirming an Irrevocable Letter of Credit.

G.11 Invoices

a. All payments under this contract will be made by electronic funds transfer (EFT) in accordance with FAR 52.232.33, Payment by Electronic Funds Transfer—System for Award Management (See Section I). An invoice is a written request for payment under the contract for supplies delivered or for service rendered. Invoices shall cite the contract number, quantity, price, and total amount of invoice. The sample invoice forms will be given to the successful offeror at the Pre-Construction meeting after contract award. In accordance with FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts (Section I), the Contractor shall furnish proper certification required by paragraph (d) on progress payments.

b. Invoices shall be prepared by the Contractor and submitted and distributed as follows:

Email to the attention of the Contracting Officer at Shannon.Anthony@fletc.dhs.gov

c. The Government will pay all proper invoices per the provisions of FAR 52.232-5, Payments Under Fixed Price Construction Contracts, and FAR 52.232-27 Prompt Payment for Construction Contracts (see Section I).

d. Payment will be based on invoices submitted by the Contractor for satisfactorily completed work. Upon verification of work actually performed and receipt of a proper invoice and any required contractor submittals, invoices will be processed for payment.

e. Submission of the invoice certifies that all employees and subcontractors have been notified of the United State Government’s zero tolerance policy regarding trafficking in persons, and the actions that will be taken for violations of this policy.

G.12 Payment to Contractor

a. The Provisions of the clause entitled "Payment Under Fixed-Price Construction Contracts" prescribed in FAR 52.232-5 are supplemented as follows:

1. In preparation of estimates, the Contracting Officer (CO) may authorize materials delivered to the site and preparatory work done to be taken in to consideration if these items are specifically identified in the accepted Schedule of Values (SOV) (if applicable) for the contract. The CO will only authorize payment for stored materials in the SOV that are considered high value; long lead or difficult to obtain; or are specialty items specifically manufactured for this project. Standard construction materials such as CMU block, conduit, wire, paint, etc. will be paid for upon satisfactory installation of the material. Payment requests for authorized stored materials in the SOV must be accompanied by an invoice showing a detailed description, quantity, cost of the materials, and evidence of contractor payment for the materials. If payment is authorized, the Contractor will be paid the lesser of the material invoice amount, or the SOV line item amount. Any remaining SOV line item balance shall be redistributed to the material installation activity, or another activity as acceptable to the Contracting mailto:Shannon.Anthony@fletc.dhs.gov

Officer. The Contractor remains responsible at all times for the proper storage and protection of all materials. Retention will be withheld from future payment applications for improperly stored materials for which the Contractor has been previously paid.

2. The FLETC will not normally authorize payment for material stored off-site. In the event the FLETC and the Contractor both agree that it is in interest of the project to consider payment for off-site material, the following conditions at minimum must be met:

a) Material properly stored in a bonded warehouse;

b) Submission of a paid invoice indicating the contractor has title to the material

c) Arrangements made for government representative to inventory the material

d) A defined material delivery date to the project

3. In accordance with FAR 52.232-5, Payments under Fixed-Price Construction Contracts, if the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.

b. No payment request (invoice) will be processed by the Contracting Officer when the Contractor's payroll submittals and/or those of any subcontractor are not current. This means the Contracting Officer must have in hand payroll submittals for the prime Contractor and all subcontractors up through and including the week immediately prior to the date on the invoice. Any invoice received wherein the Contractor has not adhered to this policy will be promptly returned to the Contractor and will not be processed until payroll submittals are brought up to date by the Contractor.

G.13 Final Payment

Final payment will not be made until all work is completed and accepted, all submittals have been received and approved, warranties received, and final cleanup of the premises is accomplished.

G.14 Daily Report to Inspector

The Contractor’s Superintendent shall complete for each day and submit electronically daily, prior to 10 AM of the following day, Form FTC-FMD-42 (12/09), Daily Report to Inspector to the Government Project Manager, Building 200, FLETC, Glynco GA. The Daily Report should contain a clear accounting of the time, location, type and quantity of work that took place. All sections shall be filled out or a comment made indicating that “this does not apply at this time”. If the proper procedure is not followed, a “Contract Construction Compliance Notice” will accompany the returned document or in the case of no report, the “CCCN” will be your notification.

G.15 Special Note

Sections K, L and M of this solicitation will be physically removed from any resultant award; however; Section K will be deemed to be incorporated by reference.

Special Contract Requirements Clauses

SECTION H- SPECIAL CONTRACT REQUIREMENTS

H.1 Directives, Regulations, And Instructions (Jul 2013) The Contractor, its personnel, subcontractors, their personnel, and representatives shall become acquainted with and fully comply at all times with the Federal Law Enforcement Training Centers (FLETC) Regulations, Directives, and Instructions. Any individual shall be subject to removal from the Center for noncompliance.

In the event of a conflict between this contract and FLETC directives, regulations, or instructions the contract shall take precedence.

H.2 Operation On The Facility Safety (Jul 2013) H.2.1 Safety The Contractor shall conduct the operation(s) under this contract in strict conformance with all FLETC safety directives and Federal, State, and local requirements and with all applicable provisions of 29 CFR Part 1910 and 1926 of the Occupational Safety and Health Act (OSHA) and USACE EM-385-1-1.

The Contractor shall conform to all safety rules and requirements in effect on the award date of this contract and shall take such additional precautions as the Contracting Officer (CO) may reasonably require for safety and accident prevention purposes while performing any work under this contract. The Contractor agrees to take all reasonable steps and precautions to prevent accidents and preserve the life and health of Contractor and Government personnel performing in any way under this contract.

The Contractor shall make contract personnel available for government-furnished safety and occupational training, estimated at two (2) to four (4) hours annually per individual.

Government-furnished training may include Quality, Safety, and Occupational requirements.

H.2.2 Accident Reports Within 24-hours of occurrence, the Contractor shall prepare a report of all job-related accidents and injuries occurring on FLETC property. The Contractor shall deliver the report to the Contracting Officer Representative (COR) and if COR is unavailable the CO. The Contractor shall maintain an accurate record of all accidents resulting in personal injury, death, trauma, or occupational illness or disease; exposure to hazardous materials (asbestos, lead, etc.); and all injuries reported on the Occupational Safety and Health Administration (OSHA) Form 300, Log of Work-Related Injuries and Illnesses.

H.2.3 Occupational Hazards The Contractor shall comply with all elements of OSHA Safety and Health Standards, FLETC Safety & Health Directives and all other Federal, State and Local regulatory requirements.

H.2.4 Physical Security The Contractor shall be responsible for safeguarding all Government property provided for https://www.osha.gov/recordkeeping/forms contractor use. At the end of each work period, all Government facilities, equipment and materials must be secured. Locked rooms must not be left unattended during the cleaning process and shall be re-locked by contractor personnel after completion of cleaning duties. The Contractor is responsible, through the CO/COR, for obtaining access to buildings and arranging for each room/area to be opened and closed as necessary in the performance of contract requirements.

In the event of an Emergency or Fire

1. Glynco Security

a. Dispatch x2911

b. (912) 267-2911

2. Artesia Security

a. Dispatch x8136

b. (575) 748-8136

3. Charleston Security

a. Dispatch x911

b. (843) 974-6305

4. Cheltenham Security

a. Dispatch x911

b. (301) 877-8400

The Contractor shall observe all OSHA, FLETC, and National Fire Prevention Association (NFPA) requirements for handling and storage of combustible supplies, materials, waste, and trash. If combustible materials are to be stored on the premises, the Contractor shall obtain Government approval, label the containers with the materials' fire hazard potential, and store the containers in fire-rated locking metal cabinets.

H.2.5 Traffic Regulations Contractor and subcontractor personnel operating motor vehicles on FLETC shall observe traffic regulations and posted speed limits except as defined elsewhere in this contract. The only exception to posted speed limits is passing jogging formations, when speed shall be reduced to 15 mph. Traffic laws are enforced on the Center, and violations shall be assessed penalty points, which can result in the revocation of driving privileges on the Center.

H.2.6 Prohibited items - See Interagency Security Committee Executive Order 14111, U.S.

DHS, Cybersecurity and Infrastructure Security Agency, Interagency Security Committee Document (2022 edition) for the list of prohibited items on federal facilities.

Substances Contractor personnel are not permitted to bring any substance that is illegal under Federal or State law or statute.

Weapons Contractor personnel are not permitted to bring privately owned firearms, weapons, or ammunition on FLETC facilities. This restriction includes handguns, rifles, shotguns, hunting bows, arrows, etc. All privately owned firearms, weapons, and ammunition must be surrendered/checked in at the Security Visitor Control Center (VCC) Weapons Storage area upon https://www.cisa.gov/sites/default/files/2022-11/052622_Items_Prohibited_in_Federal_Facilities_508c_FINAL.pdf https://www.cisa.gov/sites/default/files/2022-11/052622_Items_Prohibited_in_Federal_Facilities_508c_FINAL.pdf entry to FLETC.

H.2.7 Supervision of Contractor Personnel The Contractor's personnel shall always remain under the Contractor's direct supervision.

Although the Government will coordinate direction within the scope of the contract, detailed instructions for the Contractor's personnel's performance and supervision shall remain the sole responsibility of the Contractor.

H.3 Medical Treatment Only emergency medical care is available in Government facilities to Contractor personnel who suffer on-the-job injury. The Government will NOT perform physical examinations on Contractor personnel except as specified elsewhere in this contract. Government emergency vehicles and medical personnel may be used as the first point of treatment in emergency situations affecting Contractor personnel suffering pain or whose life or limb may be in danger.

Transfer to other than Government medical treatment facilities shall be affected by the Local Rescue Squad or Security Vehicle as determined necessary by attending medical authorities. The Contractor shall render payment for care at the rates established by the CO as equitable with like services rendered in the local community. Upon receipt of a statement of charges, reimbursement will be made by the Contractor as a credit to the next billing invoice. Cost of these emergency services shall be incurred and borne by the Contractor as non-reimbursable by the Government.

H.4 Subcontracting The Government reserves the right to approve or disapprove subcontractors for any work required by this contract. The Contractor shall obtain the CO's written approval of all subcontractors and provide copies of approved subcontracts.

H.5 Other Contracts The Government may award third party contracts for additional work at or near the site of work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the CO. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.

H.6 Rights Of The Government To Perform Functions With Its Own Personnel The Government reserves the right to perform or supplement performance of contract functions with Government personnel during periods of disaster, war emergencies, police actions, or acts of God. Such performance shall not constitute a breach of contract by the Government within the meaning of the contract clause FAR 52.212-4 entitled "Termination for Cause".

The Contractor agrees under such circumstances to permit the Government to use any essential Contractor-furnished property. The Government will equitably compensate the Contractor for use of such property.

H.7 Government Performance Of Services During Labor Strikes Because the services called for under this contract are of critical importance to FLETC, the Government reserves the right to take over or supplement performance of this contract in the event of a labor strike by the Contractor's personnel which impairs the Contractor's ability to satisfactorily perform the contract. Under such circumstances and at the direction of the CO, the Contractor agrees not to interfere in any way with Government performance. The Contractor further agrees under such circumstances to permit the Government to use any essential contractor-furnished property. The Government will equitably compensate the Contractor for use of such property.

The Contractor will not be entitled to payment for any performance period, in part or in total, during which the Government assumes performance under this clause. This clause does not limit the Government's rights under any other clause of this contract, including but not limited to, "Termination for Cause”; “Termination for Convenience”, and "Inspection/Acceptance” in accordance with FAR 52.212-4(a).

H.8 Conservation Contractor and subcontractor personnel shall actively participate in all energy conservation efforts and programs applicable to work performed under this contract. The Contractor shall instruct its personnel and subcontractors in utilities conservation policies.

H.9 Labor Relations The Contractor shall maintain satisfactory labor relations with its personnel. Representatives of the Contracting Office will not participate in labor relation matters unless disputes develop that interfere with the proper performance of the contract, at which time the representative may endeavor to assist in settling the difficulty.

The Contractor shall provide the CO with a copy of any collective bargaining agreement applicable to personnel performing on this contract.

H.10 Affirmative Procurement Of Biobased Products Under Service And Construction Contracts The Contractor shall provide a complete list of biobased products purchased to carry out the contract requirements. Provided to those listed in FAR 52.223-2, Reporting of Biobased Products Under Service and Construction Contracts (May 2024), product types and dollar value of any biobased products in USDA-designated product categories purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30. The products list shall be organized into the following three categories: Biobased products, Sustainable Products and Services and all other products. The Contractor shall list volume to be used and total cost for each individual product in each category.

H.11 Photography No photography, of any nature, is allowed while on FLETC without the written authorization of the COR or CO. Submit photography requests to the CO at least two (2) business days prior to the anticipated photo session.

H.12 Conduct Of Personnel The CO may require the Contractor to remove from the job site any individual under this contract for reasons of misconduct, security, suspected or found to be under the influence of alcohol, drugs, or other incapacitating agents. Contractor and subcontractor personnel shall be subject to dismissal from the premises upon determination by the CO that such action is in the best interests of the Government. The CO has the authority to bar individuals from the installation. Such removal from the job site or dismissal from the premises shall not relieve the Contractor of the requirement to provide sufficient personnel to perform the services as required by this performance work statement.

H.13 Contractor Vehicles, Driver’s license and Vehicle Passes All Contractor vehicles operated on Government property shall be in operable condition, maintained in good repair, and meet all local, State and Federal safety requirements. Vehicles found to be unsafe or unable to function as designed shall be removed from the job site immediately. Each vehicle operated by the Contractor under this contract shall, at all times, display a valid state license plate and safety inspection sticker, if applicable.

Vehicles must be registered with FLETC. Contractors wishing to drive on FLETC will need to provide proof of insurance, valid registration and tag number of the vehicle. Contractor cannot park in restricted parking areas unless authorized by FLETC. These authorizations will receive a parking pass that must be displayed when parked in the restricted areas. Failure to register a vehicle with FLETC will result in the loss of driving privileges on FLETC for a minimum of 30 days.

Traffic laws are enforced on the Center and violations shall be assessed penalty points, which can result in revocation of driving privileges on Center. Contractor personnel operating motor vehicles on FLETC shall observe traffic regulations and posted speed limits. Drivers will reduce speed to no more than 15mph when passing jogging formations.

H.13.1 Vehicle Inspections The Contractor shall be liable for any resultant delays (including jeopardizing their performance report rating on contract schedules) should a vehicle fail to meet the standards.

The Contractor's name and telephone number shall be conspicuously legible on both sides of all Contractor vehicles and over-the-road equipment.

The Contractor shall ensure that all Contractor personnel who will be driving a vehicle in support of this contract possess the required license prior to driving that vehicle. This specifically includes personnel operating FLETC government-owned vehicles in the performance of their roles.

H.14 Permits The Contractor shall, without additional expense to the Government, obtain all appointments, licenses, and permits required for the prosecution of the work and for compliance with all applicable Federal, State, and local laws, regulations, and codes. Evidence of such shall be provided to the CO upon request.

The Contractor shall ensure that all Contractor personnel who will be driving a vehicle in support of this contract possess a required license prior to driving that vehicle. This specifically includes personnel operating FLETC government-owned vehicles in the performance of their roles.

H.15 Environmental Protection The Contractor shall comply with all applicable environmental protection requirements, including all Federal, State, and local laws and regulations. All environmental protection matters shall be coordinated with the CO or designated representative. In the event that a regulatory agency assesses a monetary fine against the Government for violations caused by the Contractor, or contractor equipment, personnel, etc., the Contractor shall reimburse the Government for that portion of the fine and associated costs for which the Contractor is responsible.

H.16 Access To Buildings It shall be the Contractor's responsibility, through the COR, to obtain access to buildings and to arrange for each room/area to be opened and closed as necessary in performance of contract requirements. The Contractor shall be responsible for safeguarding all Government property and securing facilities, equipment, and materials at the end of each work period.

H.17 Key Control and Access Control Devices Keys to include keyless entry cards or other similar access control devices will be issued to the Contractor as appropriate. The Contractor shall receive, service, and account for all keys issued for use in the performance of this contract. The Contractor shall develop a system of key control and submit the written plan for the CO's approval five (5) days prior to contract start. This plan shall become a part of the quality control plan. The Contractor's plan shall ensure that all keys and lock combinations issued to the Contractor by the Government are not lost, misplaced, or used by unauthorized persons.

Neither the Contractor, nor any Contractor personnel, shall duplicate or fabricate any Government key or access control device in its custody. The Contractor shall report loss or unauthorized duplication of Government issued keys to the CO and/or the COR, along with his/her designated representative within 48 hours of learning of the loss or duplication by Contractor personnel. Should replacement keys be required, the Contractor shall submit a WRITTEN REQUEST to the COR and/or the CO, before any action is taken to replace any key.

The Contractor shall control access to all Government provided lock combinations to preclude unauthorized entry. The Contractor shall immediately notify the COR when lock combinations have been compromised.

Should the security of a facility become compromised by the loss of a key by Contractor personnel, the Contractor shall be responsible for replacement cost for rekeying of locks or lock replacements as determined appropriate by the CO. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced and replacement cost borne by the Contractor.

Contractor personnel shall not allow anyone the use of any Government key in their possession.

They shall not open locked rooms or areas to permit entrance by persons other than Contractor personnel performing assigned duties. Any room unlocked by Contractor at the start of work shall not be left unattended during the service process and shall be re-locked by Contractor personnel after completion of their service duties.

H.18 Disclosure Of Information

DISCLOSURE OF INFORMATION

a. The Contractor is reminded that information furnished under this contract may be subject to disclosure under the Freedom of Information Act (FOIA). Therefore, all items that are confidential to business, or contain trade secrets, proprietary, or personnel information must be clearly marked. Marking of items will not necessarily preclude disclosure when FLETC or the Government determines disclosure is warranted by the FOIA. However, if such items are not marked, all information contained within the submitted documents will be deemed releasable.

b. Any information made available to the Contractor by the Government must be used only for carrying out the provisions of this Contract and must not be divulged or made known in any manner to any person except as may be necessary in the performance of the contract.

c. In performance of this contract, the Contractor assumes responsibility for protection of the confidentiality of Government records and must ensure that all work performed by its subcontractors shall be under the supervision of the Contractor or the Contractor’s responsible employees.

d. Each officer or employee of the Contractor or any of its subcontractors to whom any

Government record may be made available or disclosed must be notified in writing by the Contractor that information disclosed to such officer or employee can be used only for the purpose and to the extent authorized herein, and that further disclosure of any such information, by any means, for a purpose or to an extent unauthorized herein, may subject the offender to criminal sanctions imposed by 19 U.S.C. 641.19 U.S.C. 641. This section provides, in pertinent part, that whoever knowingly converts to their use or the use of another, or without authority, sells, conveys, or disposes of any record of the United States or whoever receives the same with intent to convert it to their use or gain, knowing it to have been converted, shall be guilty of a crime punishable by a fine of up to $10,000, or imprisoned up to ten years, or both.

H.19 Implementation Of Executive Order (E.O.) 13224-Blocking Property and Prohibiting Transactions With Persons Who Commit, Threaten to Commit, or Support Terrorism The Contractor is reminded that U.S. Executive Orders and U.S. law prohibits transactions with, and the provision of resources and support to, individuals and organizations associated with terrorism. It is the legal responsibility of the Contractor to ensure compliance with the United States Executive Orders and laws.

H.20 Advertising of Award The Contractor shall not refer to awards in commercial advertising in such a manner as to state or imply that the product or service provided is endorsed or preferred by the Federal Government or is considered by the Government to be superior to other products or services.

H.21 Damage Reports In all instances where Government property or equipment is damaged by Contractor personnel, the Contractor shall submit a full written report of the facts and extent of such to the COR within 24 hours.

H.22 Property Damage And Personal Injuries The Contractor shall assume full responsibility for any and all damages or claims for damage for injury to persons, property, or equipment which results from any service performed under this contract. The contractor shall repair or replace to the satisfaction of the Contracting Officer (CO) or his representative any surfaces, fixtures, furnishings, structures, equipment, material, or supplies which were damaged by Contractor personnel. The Contractor shall abide by the decision of the CO whether to repair or to replace items, property, or structures when damage is caused by any of the above. The Contractor shall accomplish such repair or replacement at no cost to the Government within five (5) business days following occurrence of the damage unless otherwise agreed upon by the CO.

H.23 Indemnity And Liability The Contractor shall exercise reasonable care and use the Contractor's best efforts to prevent accidents, injury, or damage to all persons and property in and about the work and to the facility or part(s) thereof upon which work is done.

The Contractor shall indemnify and hold harmless the Government against any and all…