Phased_Array_Q A's.pdf
PDF 58 KB Posted
- Attached to
- AMC Phased Array Federal contract opportunity
- Solicitation number
- HTC711-15-Q-D059
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch_2_-_PWS_Amendment_01.pdf | ||
| Phased_Array_Q A's.pdf | ||
| Phased_Array_Q A's.pdf | ||
| Atch_2_-_PWS.pdf | ||
| Atch_3_-_Provisions_and_Clauses.pdf | ||
| Atch_4_-_DD254.pdf | ||
| Atch_1_-_Info_Sheet.pdf | ||
| Combined_Synopis-Solicitation_Notice_Final.pdf | ||
| Atch_6_-_Past_Performance_Questionnaire.pdf | ||
| Atch_7_-_PP_Log.pdf | ||
| Atch_5_-_PP_Reference_Submission_Sheet.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 1: Are the following mandatory for this project?
6.4. Security Clearance and Special Access Requirements.
All positions on this task order require a minimum of a SECRET clearance as granted by the Personnel Security Management Office-Industry (PSMO-I).
6.5. Facilities Clearance (FCL)
The contractor must have a valid FCL at the SECRET level. Interim FCLs are acceptable provided they are not expired. FCL procedures and security guidelines for adjudicative requirements are outlined in DOD 5220.22-M FCLs and Interim FCLs must be awarded by the Defense Security Service (DSS) Facility Clearance Branch.
Answer: Yes these are mandatory due to the possibility of dealing with security clearance cargo.
Question 2: If we do not presently possess a Secret Facility Clearance will the Government sponsor us for this project?
Answer: USTRANSCOM currently does not sponsor contractors for their clearance.