PETREL_DS_FY16_R0_SPEC.pdf
PDF 272 KB Posted
- Attached to
- USCGC PETREL DS FY16 Federal contract opportunity
- Solicitation number
- HSCG80-16-Q-P45236
About this file
STATEMENT OF WORK
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_002_Petrel.pdf | ||
| SF30_001_Petrel.pdf | ||
| Petrel_RFQ_(Stand-Alone).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC PETREL (WPB 87350)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2016
Developed By: Tim O'Brien
(Rev-0, 13 October 2015)
USCGC PETREL (WPB-87) DOCKSIDE AVAILABILITY FY2016
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: Handrail, Modify WORK ITEM 2: Main Mast, Preserve, 100% WORK ITEM 3: Galley and Mess Deck, Preserve Bilges 100% and Renew Joiner Deck WORK ITEM 4: Install Halyard Ring Eye Bolts WORK ITEM 5: HVAC System, Ducting, Clean iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
• American Welding Society (AWS): http://www.awspubs.com/index.php
• ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
• NFPA: http://www.nfpa.org
• SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 113-001, Rev E, Platform Plating & Framing Coast Guard Drawing 87 WPB 113-002, Rev B, Galley/Messdeck Bilge Access Coast Guard Drawing 87 WPB-171-001, Rev U, Mast Details Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping System Coast Guard Drawing 87 WPB 601-001, Rev P, Outboard Profile & General Arrangements Coast Guard Drawing 87 WPB 621-001, Rev H, Joiner Work Details Coast Guard Drawing 87 WPB 634-001, Rev C, Deck Coverings & Details Coast Guard Drawing 87-WPB 612-001 (Rev L) Handrail Details
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean
Shipboard Ventilation Systems http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning vi (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
This section is not applicable to this package.
vii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
2 Main Mast, Preserve, 100%
3 Galley and Mess Deck, Preserve Bilges 100% and Renew Joiner Deck viii (Rev-0)
PRINCIPAL CHARACTERISTICS
87' WPB
PHYSICAL
Length overall 87' Length between perpendiculars 81' 7" Depth 10' 11" Maximum beam 19.4' Draft, mean to design waterline 5' 9" Height of highest projection 50.2' Full load displacement 93.5 long tons Minimum operating displacement 83.9 long tons Displacement, light ship 77.9 long tons Framing Longitudinal Bulkheads Four watertight bulkheads located below the Main Deck Anchor 40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset
HULL
Hull/main weatherdeck material ABS Grade AH 36 Superstructure 5086 Aluminum
MACHINERY
Main propulsion Two MTU 8V396TE94, sequential turbo-charged diesels Reduction gears Two ZF Type BW 255 Propulsion shaft Two AQUAMET 22, 101.6mm Shaft diameter 4" Shaft seal Two John Crane mechanical seals Shaft bearing, intermediate Thordon Elastomeric Bearing Shaft bearing, aft Thordon Elastomeric Bearing Number of propellers 2 Number of blades 5 Diameter of propeller 1040mm Pitch 1230 mm fixed Shaft RPM 828 Rudders Two 316L Stainless Steel Ship's service generators Two Man Model D08241F01 diesel with Stanford 60KW Generator
TANK CAPACITIES
3-9-1-f (fuel oil) 1402 gal 3-9-2-f (fuel oil) 1402 gal 3-12-2-f (waste oil) 86 gal 3-12-1-f (oily water) 86 gal 3-7-0-q (sewage collection) 352 gal 3-7-1-q (grey water) 52 gal 3-12-1-w (fresh water) 200 gal 3-12-2-w (fresh water) 200 gal
1 (Rev-0)
00000_0315_FLT
REC_00000_FLT_ Commercial Project @ CG Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Small Quantity.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3 (Rev-0)
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to adequately accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor shall be aware of the following:
3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
• None.
4. NOTES
4 (Rev-0)
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT. SURFACE AMBIENT
ΔT
| DP -
Surface |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
8 (Rev-0)
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS CONDUCTIVITY
(microsiemens/cm)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Coating Mfg Product Name Batch # Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled) Average DFT
12 (Rev-0)
TCTO_TB3020_61200_GLT_0112_WPB87
WORK ITEM 1: Handrail, Modify
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to cut-off, modify, and re-install the port and starboard side handrails between frames 20 and 22.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87-WPB 612-001 (Rev L) Handrail Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Technical Representative.
Not applicable.
3.1.3 Protective measures.
13 (Rev-0)
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):
• Wire rope.
3.2 Stanchion renewal. The Contractor shall cut-off handrails located between frames 20 and 22 and modify as indicated in Coast Guard Drawing 87 WPB 612-001.
3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable.
This section is not applicable to this work item.
14 (Rev-0)
63150_Masts_0814_FLT REC_63150_Masts_FLT_87’ WPB (ALL) (0909)
WORK ITEM 2: Main Mast, Preserve, 100%
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve the aluminum Main Mast.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 601-001, Rev P, Outboard Profile & General
Arrangements Coast Guard Drawing 87 WPB-171-001, Rev U, Mast Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
• 3.2.2 Substrate inspection.
15 (Rev-0)
3.1.2 Tech Rep.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.1 The Contractor shall, once the equipment has been removed from the Mast, ensure it is stored in a protective environment. Areas/equipment/components to be protected include, but are not limited to the following (as applicable):
• Cable runs
• Label plates
• Connectors
• Rubber gaskets
• Yardarm blinkers
• Wind speed air vanes
• Navigation lights
• Ship's bell
• Adjacent bulkhead and deck surfaces
• Contact points
• Insulators
• Rubber shock mounts
• Safety climb.
3.1.3.2 The Contractor shall coil up electrical cabling down to associated deck/bulkhead penetrations. Mark, seal, and cover all coiled cabling. Ensure the cable is protected from abrasion and damage. Do not bend any electrical cable to a radius less than 20 times their diameter. Do not hoist a radar pedestal using its array.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed.
• Radar gear, including associated pedestals
• Navigation lights
• Electrical fittings
• Rigging
• Antennas
• Wind direction indicator
16 (Rev-0)
3.1.4.1 The Contractor shall notify the COR 72 hours in advance of beginning interference removals.
3.1.5 Personnel qualification. The Contractor shall ensure that all Contractor personnel performing removal and installation of electronics equipment shall have the training of an electronics journeyman and be knowledgeable in the areas of electrical and physical standards for equipment such as radar, waveguides and antennas.
3.1.6 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast Guard Personnel perform an initial operational test of all mast electrical and electronic equipment to demonstrate existing operational conditions. Submit a CFR.
3.2 Mast removal. The Contractor shall remove (unship) the mast. Reinstall the mast, using the attached sketch as guidance. Prepare and touch-up coat all disturbed surfaces (upon mast reinstallation) to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
3.2.1 Surface preparation optional methods. The Contractor has the option of using either high/ultrahigh pressure water jetting or abrasive blasting to achieve the required surface preparation, prior to application of the coating system specified in 3.3 (Preservation requirements). The Contractor may add abrasives to the water jet stream, for one or both of the following reasons:
• Achieving greater productivity.
• Achieving the required surface profile.
NOTE
Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.
3.2.2 Substrate inspection. After surface preparation and before the coating application, the Contractor shall perform a visual inspection of all cleaned mast surfaces, including electrical hangers, hardware, and safety rail hardware. Submit a CIR
3.3 Preservation requirements. The Contractor shall prepare and coat the mast surfaces using the system specified for “Freeboard/Superstructure/Mast (Freeboard/Superstructure)” in Appendix A (Cutter and Boat Exterior Painting Systems) of SFLC Std Spec 6310. Select the following:
• “Option I” system, for aluminum surfaces
• Spar (10371), as the top/finish color.
3.4 Weather-proofing requirements. The Contractor shall weatherproof all connectors, cables and fasteners in accordance with SFLC Std Spec 3042.
3.5 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for critical-coated surfaces).
17 (Rev-0)
NOTES
1. Unless a containment system is used for surface preparation dust and debris and coating application overspray during pier side/dockside preservation, the following must be adhered to:
a. All surface preparation tools/equipment must be vacuum-shrouded.
b. Coatings must be applied by brushing or rolling.
2. Coating application by brushing or rolling may require additional coats to obtain required dry film thickness.
3. Surfaces being preserved are considered “critical-coated surfaces”.
3.6 Repair of un-intended damages. The Contractor shall repair all damages (including overspray) incurred to vessel surfaces (including those not covered by the intended scope of this work item), during surface preparation and paint application procedures.
3.7 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel, including C4IT personnel) of all mast electrical and electronic equipment, to prove satisfactory operating condition. Submit a CFR.
4. NOTES
4.1 Coast Guard Inspector. CG Inspector will ensure that antennas are mounted and weather-proofed before final operational test.
18 (Rev-0)
11305_MWS_0215_87WPB
WORK ITEM 3: Galley and Mess Deck, Preserve Bilges 100% and Renew Joiner Deck
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve the bilge surfaces and renew the joiner deck system designated in the table below.
LOCATION
APPROXIMATE
AREA
(SQFT)
Galley (2-9-1-Q) and Mess Deck (2-9-2-Q) 950 bilges;
175 deck covering
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 113-001, Rev E, Platform Plating & Framing Coast Guard Drawing 87 WPB 113-002, Rev B, Galley/Messdeck Bilge Access Coast Guard Drawing 87 WPB 601-001, Rev P, Outboard Profile & General
Arrangements Coast Guard Drawing 87 WPB 621-001, Rev H, Joiner Work Details Coast Guard Drawing 87 WPB 634-001, Rev C, Deck Coverings & Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3
(SSPC-SP 3), 2004, Power Tool Cleaning
19 (Rev-0)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
• 3.2.2 Substrate inspection.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):
• Deck grating and associated framing.
• Bilge piping.
• Electrical wiring.
• Valves.
• Control and junction boxes.
• Range.
• Sanitizer.
• Galley deck.
• Tables.
• Benches.
• Entertainment center.
3.2 Preservation particulars. The Contractor shall use Coast Guard Drawing 87 WPB 113-001, 87 WPB 113-002, and 87 WPB 601-001 as guidance to accomplish all work herein.
3.2.1 Surface preservation. The Contractor shall prepare and coat the compartment bilge surfaces (as designated in paragraph 1.1 (Intent)), including all adjacent structural members, using the system specified for “Bilges, Cofferdams, and Forepeaks, Option II”, in SFLC Std Spec 6310, Appendix B (Cutters and Boat Interior Painting Systems). Surface preparation shall be in accordance with SSPC SP-3. Select Red (20152), as the top/finish coat color.
20 (Rev-0)
NOTE
Application of the topcoat specified herein may require the use of plural-component spray equipment, or other suitable methods, to compensate for the coating system’s relatively short pot life.
3.2.2 Substrate inspection. After completion of surface preparation and before primer coat application, the Contractor shall perform a visual inspection of all prepared surfaces. Submit a
CIR.
3.3 Cosmetic polymeric epoxy resin deck renewal. The Contractor shall renew the deck covering system (i.e. remove existing covering, prepare and paint, then apply deck covering material, etc.), including the associated cove base, using Cosmetic Polymeric Epoxy Resin, Type III (One-Step Epoxy System), in accordance with appendix A of SFLC Std Spec 6341. Renew any damaged honeycomb paneling. Use Coast Guard Drawings 87 WPB 113-001, 87 WPB 621- 001, and 87 WPB 634-001 as applicable for guidance.
CAUTION
The “honeycomb” paneling is very difficult to prevent from damaging when removing the deck.
3.4 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph
3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
NOTE
Surfaces being preserved are considered “critical-coated surfaces”.
21 (Rev-0)
EC_TB5000_17110_RJL_0415_087_WPB
WORK ITEM 4: Install Halyard Ring Eye Bolts
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to install eight bimetallic bosses and stainless steel eyebolts on the mast.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB-171-001, Rev U, Mast Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship’s Structures
OTHER REFERENCES
None.
22 (Rev-0)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Coast Guard Drawing 87 WPB-171-001 shall be referenced to aid in identifying any additional interference. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):
• Halyard Staples
• Electrical cable
3.2 Removal and installation. The Contractor shall remove and dispose of all eight existing halyard staples and install eight new bimetallic bosses and stainless steel eyebolts in accordance with Coast Guard Drawing 87 WPB-171-001. All welding shall be in accordance with Surface Forces Logistics Center Standard Specification 0740, Welding and Allied Processes.
3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310.
None.
23 (Rev-0)
SYY_NNN_51400_MWS_1015_873xx
WORK ITEM 5: HVAC System, Ducting, Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to the shipboard HVAC system ducting.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping System
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
24 (Rev-0)
3.1.3 Protective measures.
3.1.3.1 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.2 Additional protective measures. In addition to providing protective covering as specified in SFLC Std Spec 5100, subsection 3.1.2 (Protective measures), provide additional protective covering for all food preparation and serving surfaces that may be affected by cleaning work, as applicable, to prevent contamination.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
• Ducting screens.
• Electric preheaters.
• Overhead sheathing and panels.
• Ventilation covers.
3.1.5 Operational tests - general.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.1.5.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the ventilation systems included in this work item, to demonstrate existing operational condition. Submit a CFR.
3.1.5.2 Operational test – post repairs. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the disturbed ventilation systems to be in satisfactory operating condition (see 4.1 (Equipment operation)). Repair all leaks. Submit a CFR.
3.2 Cleaning particulars. Using Coast Guard Drawing 87 WPB 514-001 as guidance, the Contractor shall accomplish the following:
NOTE
Provide COR written notification 48 hours prior to start of work.
3.2.1 Clean all supply and exhaust portions of the HVAC system (all ducting leading to and from the air handler unit) in accordance with SFLC Std Spec 5100.
3.2.2 Mark the positions of all diverting, balance, and splitter dampers prior to disassembly and restore to original configuration at reassembly.
25 (Rev-0)
3.3 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs).
| Revisions Record |
| Consolidated List of References |
| Consolidated List of Government-furnished Property |
| Consolidated List of Critical Inspection Items |
| Principal Characteristics |
| General Requirements |
| QA-1 - QUALITY ASSURANCE INSPECTION FORM |
| (PRESERVATION CHECKLIST) |
| QA-3a - QUALITY ASSURANCE INSPECTION FORM |
| (SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C) |
| QA-3b - QUALITY ASSURANCE INSPECTION FORM |
| (SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B) |
| QA-4 - QUALITY ASSURANCE INSPECTION FORM |
| (SURFACE SOLUBLE SALT CONDUCTIVITY LOG) |
| SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15 |
| QA-5 - QUALITY ASSURANCE DATA FORM |
| (COATING THICKNESS) |
| (Use one sheet for each sequence) |
| Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2 |
| Location (Frame Reference): ___________________ |
| WORK ITEM 1: Handrail, Modify |
| WORK ITEM 2: Main Mast, Preserve, 100% |
| WORK ITEM 3: Galley and Mess Deck, Preserve Bilges 100% and Renew Joiner Deck |
| WORK ITEM 4: Install Halyard Ring Eye Bolts |
| WORK ITEM 5: HVAC System, Ducting, Clean |
File details come from the government source that posted it. Updated .