ASSATEAGUE_(WPB_110B)_DS_Rev-1_SPEC.pdf
PDF 1 MB Posted
- Attached to
- SOLICITATION FY15 DS ASSATEAGUE Federal contract opportunity
- Solicitation number
- HSCG80-15-Q-P45001
About this file
Specification for dock side repairs to CGC ASSATEAGUE (WPB 1337)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Assateague_Amendment_2.pdf | ||
| Questions.doc | DOC document | |
| Assateague_Amendment_1.pdf | ||
| SOLICITATION_MASTER.doc | DOC document | |
| Assa-_Blank_SoS.xlsx | XLSX spreadsheet | |
| ASSATEAGUE_(WPB_110B)_DS_Rev-1_SPEC.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC ASSATEAGUE (WPB 1337)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2015
Developed By: Michael W Howell
(Rev-1, 30 June 2014)
USCGC ASSATEAGUE (WPB-110B) DOCKSIDE AVAILABILITY FY2015
ii (Rev-1)
TABLE OF CONTENTS
Revisions Record .................................................................................................................................................... iii Consolidated List of References ............................................................................................................................ iv Consolidated List of Government-furnished Property ...................................................................................... vii Consolidated List of Critical Inspection Items .................................................................................................. viii Principal Characteristics ....................................................................................................................................... ix General Requirements WORK ITEM 1: Structural, (Aluminum Plating) Repairs, Deck Locker (1-17-1-A) (CSMP 14-002) WORK ITEM 2: Piping, Packing Gland, (P-100), Renew (CSMP 14-005) WORK ITEM 3: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) WORK ITEM 4: Superstructure, Deck Lights, Renew (CSMP 14-010) WORK ITEM 5: Deck Covering (Wet/Dry), Seal (CSMP 14-008) WORK ITEM 6: QAWTD Hinges, Renew (CSMP 14-003) WORK ITEM 7: Deck Covering, Renew (CSMP 14-006, 14-007, 14-009) WORK ITEM 8: Deck Drain, (Forward Sound Locker) Renew WORK ITEM 9: Stanchions, Life Line, Renew (CSMP 14-001) WORK ITEM 10: Main Mast, Repair & Preserve, 100% WORK ITEM 11: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 12: MDE Seawater Recirculation Valves, Install WORK ITEM 13: Fire Hose Racks, Install WORK ITEM 15: Decks - Exterior, Preserve (“MIL-Spec/Flight Deck” System) (O) iii (Rev-1)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
30 June 2014 1 15 Added Decks - Exterior, Preserve (“MIL-Spec/Flight Deck”
System) as an option item to Work Item #3.
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-1)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 110B WPB 085-012, Rev B, Booklet of General Drawings
Coast Guard Drawing 110B WPB 151-007, Rev E, Superstructure Foundations Detail Booklet
Coast Guard Drawing 110B WPB 151-008, Rev -, Superstructure Details
Coast Guard Drawing 110 WPB-151-004, Rev -, Superstructure Details
Coast Guard Drawing 110B WPB-151-007, Rev E, Superstructure Details
Coast Guard Drawing 110C WPB-151-005, Rev F, Superstructure Details
Coast Guard Drawing 110C WPB-151-006, Rev F, Superstructure FDN Layout and Location Plan
Coast Guard Drawing 110 WPB 167-003, Rev -, Flush Hatch Details
Coast Guard Drawing 110B WPB 085-001, Rev A, Tank Capacity Curves
Coast Guard Drawing 110B WPB 085-012, Rev A, Booklet of General Plans (Supersedes 110B-WPB-
085-7)
Coast Guard Drawing 110B WPB 113-001, Rev K, Inner Bottom Plating
Coast Guard Drawing 110B WPB 117-001, Rev H, Transverse Sections (Frames 0 thru 4)
Coast Guard Drawing 110B WPB 121-001, Rev D, Longitudinal Bulkheads
Coast Guard Drawing 110 WPB 171-001, Rev B, Mast Details
Coast Guard Drawing 110 WPB 171-002, Rev F, Mast Details
Coast Guard Drawing 110B WPB 256-005, Rev B, Main Engine Seawater Cooling, 3-way Valve
Installation & Ripout
Coast Guard Drawing 110B WPB 437-001, Rev G, Main Engine & Generator Instrumentation
Coast Guard Drawing 110 WPB 330-005, Rev C, Ship Service Lighting One Line Diagram http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-1)
Coast Guard Drawing 110C WPB 601-027, Rev D, Outboard Profile & Weather Deck
Coast Guard Drawing 110B WPB 612-001, Rev G, Handrail & Grabrail Details
Coast Guard Drawing 110 WPB-621-003, Rev -, Joiner Work Details
Coast Guard Drawing 110C WPB-621-004, Rev-, JNR Work Details-Superstructure (Superst BHD
Layout)
Coast Guard Drawing 110C WPB-635-001, Rev D, Linings & Insulation Plan & Details
Coast Guard Drawing 110B WPB-635-001, Rev C, Superstructure Details
Coast Guard Drawing 110B WPB 131-001, Rev J, Deck Construction Plan
Coast Guard Drawing 110 WPB 074-002, Rev -, Welding Details Handbook
Coast Guard Drawing 110 WPB 331-004, Rev C, Lighting System Deck Plan
Coast Guard Drawing 110C WPB 521-003, Rev B, P100 Pump Fixed Pipe Installation
Coast Guard Drawing 110B WPB 526-001, Rev C, Scuppers and Deck Drains Piping Arrangement
Coast Guard Drawing 110B WPB 529-001, Rev B, Bilge Piping Arrangement & Details
Coast Guard Drawing 110 WPB 601-020, Rev -, Manhole & Hatch Key Plan
Coast Guard Drawing 110 WPB 604-001, Rev -, Door & Hatch Key Plan & Lock Layout
Coast Guard Drawing 110C WPB 167-005, Rev E, Doors, Hatches & Manholes
Coast Guard Drawing 110B WPB 621-004, Rev E, Joiner Work Dets - Superstructure
Coast Guard Drawing 110C WPB 635-001, Rev C, Linings and Insulation Plan
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
Coast Guard Technical Publication (TP) 4671, Feb 2008, Manufacturer’s Instruction Book – SWBS
Group 256, MDE Salt Water Valves
OTHER REFERENCES
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
ASTM International (ASTM) F1836M, 1997, Standard Specification for Stuffing Tubes, Nylon, and
Packing Assemblies
Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
Code of Federal Regulations (CFR) Title 33 CFR, Jul 2010, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation vi (Rev-1)
DOD-STD-2003, Dec 1990, Electric Plant Installations, Standard Methods FOR surface Ships and
Submarines
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe
Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic)
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and
Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of
Reliability Is Required
MIL-DTL-24643, Aug 2002, Cable and Cord, Electrical, Low Smoke, for Shipboard Use, Specification.
MIL-DTL-15562, May 1996, Matting or Sheet, Floor Covering Insulating for High Voltage requirements vii (Rev-1)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
12 Y 4” 3-Way Rotary
Valve, Port
LESLIE
U107963101PORT
1 ea $2,365.00
12 Y 4” 3-Way Rotary
Valve, Stbd
LESLIE
U107963101STBD
1 ea $2,365.00
14 N Anti-fatigue matting Continental flooring, GSA
Contract #: GS-07F-
04929J (800-225-1221)
NSN: 7220-01-598-6144
40 sq ft 50.00 viii (Rev-1)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
11 Ultrasonic Thickness (UT) Measurement
14 Pilothouse Deck (Aluminum), Inspect ix (Rev-1)
PRINCIPAL CHARACTERISTICS
PC_110B_WPB_0909
110’ WPB (“B”-CLASS) PATROL BOAT
PHYSICAL CHARACTERISTICS
Length Overall 110' 0" or 113' if stern flap present
Length between Perpendiculars 104' 1/2"
Depth 10' 1/2"
Beam, Molded 21' 3"
Depth, Molded N/A
Full Load Draft 6' 5-3/4"
Height of Highest Projection 55'
Full Load Displacement 165 long tons
Anchor 150 lb Danforth with 450 ft. 3" nylon rope
Shore Tie Voltage Requirements 450VAC 400A 3PH, 60Hz ungrounded
HULL CHARACTERISTICS
Hull BS-4360, GR 43A Steel
Main Weatherdeck & Superstructure 5086 Aluminum Alloy
Frame Spacing Various
Bulkheads Seven watertight transverse
Fin Stabilizers Frame 22-1/2 x (Rev-1)
110’ WPB (“B”-CLASS) PATROL BOAT
MACHINERY CHARACTERISTICS
Main Propulsion Two Paxman Type 16 RP200M (Valenta) V-16 Diesel; 2880 BHP each @
1500 RPM (max)
Reduction Gears Two ZF Model BW 1500 reversible reduction gearboxes; 1.839:1 ratio
Number of Propellers 2
Number of Blades 5
Diameter of Propeller 49.6"
Pitch 61.4"
RPM N/A
Shaft AQUAMET 17
Shaft Diameter 4"
Shaft Seal Johnson Duramax split face seal
Shaft Bearings Rubber Cutless or Thordon
Rudders Twin underslung type, 5 sq ft each
Ship's Service Generators Two Caterpillar Type 3304BT diesel; 99KW, 460V, 60Hz, 3-phase, 3-wire
@ 1800 RPM
TANK CAPACITIES
Fuel Oil (95%) 9,306 gal
Fresh Water (100%) 940 gal
Lubricating Oil (95%) 109 gal
1 (Rev-1)
00000_0214_FLT
REC_00000_FLT_ Commercial Project @ CG Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) 6966, 2008, Standard Practice for Collection of Settled Dust Samples Using
Wipe Sampling Methods for Subsequent Determination of Metals
Code of Federal Regulations (CFR) Title 29, Part 1910, Jul 2008, Occupational Safety and Health
Standards
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
Code of Federal Regulations (CFR) Title 33 CFR, Jul 2010, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
3. REQUIREMENTS
2 (Rev-1)
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with (COMDTINST)_MI0360.3C , Chapter 11 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 5 of COMDTINST MI0360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazardous wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40
CFR 262, applicable to handling of hazardous wastes.
3.5.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification
(ID) Number for manifesting of hazardous wastes.
3.5.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW
Coordinator prior to any transfers of HW from ship to shore.
3.5.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW
Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the COR in writing 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.4 The Contractor shall be aware of the following:
3.5.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COR or KO-approval.
3 (Rev-1)
3.5.4.2 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with local and state regulations.
3.5.4.3 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the
Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.
4 (Rev-1)
3.6 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2012 Edition Standard Specifications and supersede published content:
3.6.1 SFLC Std Spec 8634, Drydocking, Appendix A, page A5, paragraph A2.7.1.3 Side Blocks: Remove formula value shown as g – Acceleration of gravity – 32.3 Ft/sec , and replace with formula value g -
Acceleration of gravity - 32.174 ft/sec
3.6.2 SFLC Std Spec 0740, Welding and Allied Processes. SFLC Std Spec 0740 added Appendix E, Stray
Current Protection: New Appendix is posted with SFLC Standard Specifications as a separate document on internet and intranet webpage.
3.6.2.1 SFLC Std Spec 0740, page 1, paragraph 1.2 Appendices: Add ‘Stray Current Protection’ to ‘Process
Standard column of appendices table. Add ‘E’ to ‘Appendix’ column of appendices table.
3.6.2.2 SFLC Std Spec 0740, page 4, paragraph 3.1.3 Stray current protection: Add “The Contractor shall meet all requirements for stray current protection as specified in Appendix E - Stray Current Protection.” directly after paragraph 3.1.3 title.
3.6.2.3 SFLC Std Spec 0740, page 4, paragraph 3.1.3 Stray current protection: Delete paragraphs 3.1.3.1 and
3.1.3.2.
3.6.3 SFLC Std Spec 0450, Electrical Power for Contractor’s Tools and Equipment, page 1, paragraph 1.1 Intent:
Add sentence, “Note that stray current protection for welding equipment is covered in SFLC Standard
Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.6.3.1 SFLC Std Spec 0450, page 5, paragraph 3.4 Equipment Grounding: Add sentence, “Stray current protection for welding equipment is covered in SFLC Standard Specification 0740, Welding and Allied Processes, Appendix E.” to end of paragraph.
3.6.3.2 SFLC Std Spec 0450, page 6, paragraph 3.4 Equipment Grounding: Delete paragraphs 3.4.1.4 and
3.4.1.5.
3.6.3.3 SFLC Std Spec 0450, page 6, paragraph 3.4 Equipment Grounding: Delete Figure 5.
3.6.4 SFLC Std Spec 0000, General Requirements, Appendix A Requirements for Environmental Protection:
Add paragraph A2.2.5.3.3, as follows:
“A2.2.5.3.3 Additional requirements during abatement of lead-based paint (LBP) and asbestos-containing coatings. Abide by the following additional requirements, during work that involves disturbance or abatement
LBP and asbestos-containing material (ACM)/vermiculite coatings:
A2.2.5.3.3.1 Certification documentation. At the Arrival Conference, submit documentation to the COR that all primary and sub contractors fulfilling abatement requirements related to the preceding disclosure paragraph possess all Local, State, and Federal certification licenses and applicable permits, for fulfilling those abatement requirements.
A2.2.5.3.3.2 Advance notification. Notify the COR 24 hours prior to any planned abatement actions.
Additionally, notify the Quarterdeck and COR, prior to starting any abatement task, to ensure a timely announcement to Coast Guard personnel to vacate the affected area.
5 (Rev-1)
NOTE
Be aware that Coast Guard personnel are not permitted to be in the location of abated spaces while abatement is being performed.
A2.2.5.3.3.3 Additional protective measures.
A2.2.5.3.3.3.1 Take the following additional safety precautions:
Separate work area from other non-affected areas.
Do not permit non-essential personnel in the work area.
Work in one compartment/space at a time.
Prevent dust from migrating to other areas, as follows:
o Seal doors, hatches, and all other openings between the work area and other areas with an airtight barrier, such as fire-rated polyethylene; seal both sides (inside the construction area, and inside the adjacent area) to provide a secondary dust barrier and prevent the doors and windows from being used (post alternative emergency exits, if applicable).
o Maintain work area under negative pressure in relation to adjacent areas.
Take, at a minimum, the following measures, to protect de-contamination workers:
o Use a HEPA (high-efficiency particulate air) vacuum.
o Workers must wear a respirator which is approved by NIOSH and has N100, P100 or R100 filters (the cartridges are usually purple); respirators must be fit-tested to insure proper seal, and employees must be medically screened and trained prior to wearing a respirator (see the
OSHA Respirator Standard, 29 CFR 1910.134).
o Workers must wear full-body protective clothing, head covering and shoes (or shoe covers).
o Workers must not leave the work area without having gone through a proper decontamination process, to prevent spread of lead dust to un-affected areas.
o Eating, drinking and smoking are prohibited in work areas.
o Workers must wash hands and face before eating, drinking or smoking.
o Workers must remove work clothes and shoes before leaving the work area, and seal work clothes in plastic.
o Workers must shower and wash hair as soon as possible after leaving the work area.
o Non-disposable work clothes must be washed separately from other clothes.
NOTES
1. Negative pressure means that more air is exhausted from the area than is supplied so that lead dust and/or asbestos particles are contained within the work area, and do not contaminate adjacent non-affected compartments. Exhaust air must be filtered with a suitable HEPA filter.
2. A HEPA vacuum removes 99.97% of particles that are less than 0.3 microns in size.
3. Use of compressed air, conventional vacuum, and dry-sweeping is not permissible, during abatement.
A2.2.5.3.3.3.2 Remove and dispose of all protective covers, upon completion of work.
A2.2.5.3.3.4 Abatement task particulars.
A2.2.5.3.3.4.1 Coating removal and surface preparation.
6 (Rev-1)
A2.2.5.3.3.4.1.1 ACM. Remove existing ACM by a suitable means such as chipping or scraping. Ensure all removed materials are carefully placed into bags that are specially designed for ACM removal, sealed and handed over to another worker to be sealed again.
A2.2.5.3.3.4.1.2 LBP. Remove LBP from identified areas, using one or a combination of the cleaning methods specified in Table A1 below, as applicable.
A2.2.5.3.3.4.2 Scope of spot abatement. When spot or partial abatement is required due to interference with other ship repair work (including but not limited to: hotwork, equipment and component installations, structural inspections and repairs,), do the following:
Perform inspections of all locations that have been slated for spot abatement, to identify paths of future hull cuts and weld seams and locations of weld repairs, as applicable.
Ensure that abatement shall also include the following:
o The area itself, including but not limited to: attached framing, stiffeners, piping, equipment support – in addition to up to a three-inch boundary segment where removal is faired into surrounding intact coating.
o All areas of the heat affected zone (estimated to be at a minimum of 3-4 inches on each side of a weld repair), to permit welders sufficient room to safety make required repairs.
o Areas intended for tack welds used during fit up.
o Areas that asbestos material could be disturbed by personnel transiting the work site, setting up/moving equipment, setting up containment measures, or any activity by contractor personnel that could damage asbestos material adjacent to the site of any hotwork activity.
Ensure that the presence of ACM and/or LBP adjacent to future weld repairs is readily apparent to welders through the use of signs on the compartment entry and local markings adjacent to repairs using a suitable means such grease pencils. Be aware that any accidental disturbance ACM and/or
LBP by subsequent hot work or grinding associated with weld repairs shall require clean up in and clearance testing, at no cost to the Government.
TABLE A1 - SURFACE PREPARATION METHODS
MECHANICAL CLEANING CHEMICAL STRIPPING
STEEL SUBSTRATE ALUMINUM
SUBSTRATE
Use a suitable chemical stripper to safely remove all existing coatings
– and expose the bare substrate, in accordance with manufacturer’s instructions.
1. Waterjet to a SSPC-SP WJ-
2/NACE WJ-2 standard.
2. Abrasive-blast to SSPC-
SP10/NACE No. 2, using grit conforming to MIL-A-22262
(1.5 to 2.5 mil anchor profile).
3. Power tool clean to a SSPC-
SP 11 (1.0 mil anchor profile), with vacuum attachment, to capture lead dust and debris.
1. Waterjet to a SSPC-SP
WJ-2/NACE WJ-2 standard.
2.Brush blasting with clean, fine aluminum oxide, garnet or equivalent inert material conforming CID A-A-
59316, Type I & IV, to remove all existing coatings and rust spots, down to bare metal (and produce a 1.0-1.5 mil anchor profile).
3. Mechanical cleaning, using power sanders and abrasive sandpaper with no metallic contents, to remove all existing coatings and rust spots, down to bare metal.
7 (Rev-1)
NOTES
1. Abrasive-blasting creates lead dust, which requires extensive post-surface preparation cleaning in affected compartments. Wet-abrasive blast cleaning (water introduced into the blast stream) may be used, to contain/eliminate dust.
2. Abrasive-blasting and waterjetting are not permissible inside machinery spaces or other outfitted spaces due to the difficulty of containing water spray and contamination of blasting dust particles. These methods are allowed to be performed in voids and tanks where full containment, negative ventilation, and isolation of the affected areas can be performed.
3. Known paint strippers meeting the requirements specified in Table 1 include, but are not limited to the following:
a. Franmar LeadOut
b. STRIP-TOX Paint Stripper
c. Aquastrip ACB
d. Smart Strip™ Advanced Paint Remover
WARNING
Paint stripper formulated with the following hazardous materials are strictly prohibited for use onboard CG vessels:
a. Methylene chloride
b. Chlorinated solvents
c. Phenols
d. Chromates
e. Ammonia
f. Amines
CAUTION
Any action that has the potential to generate dust (blasting, hand tooling) shall be rigorously monitored to ensure contamination of the ship does not occur.
Certifications are required for any personnel who engage in these practices.
A2.2.5.3.3.4.3 Precautionary measures when using chemical stripping. Take the following precautionary measures, when chemical stripping is selected as one of coating removal methods:
A2.2.5.3.3.4.3.1 Ventilation. In addition to all temporary ventilation requirements specified in SFLC Std 0000 and the “General Requirements” item, ensure the following:
A flow rate ventilation (minimum 100 cfm) is installed in the affected compartment - and ventilation system inspected by COR, prior to commencement of work.
Exhaust ducts from ventilation fans are run outside and away from the ship’s ventilation intakes and downwind from cutter location. This shall be monitored and adjusted as necessary if there are changes in wind location.
8 (Rev-1)
A2.2.5.3.3.4.3.2 Chemical residue removal. After completion of coating removal, wash down all affected surfaces with suitable soap and water, required to ensure all solvents or solvent residues are removed.
A2.2.5.3.3.4.4 Treatment of existing coating edges bordering abated areas. In lieu of abiding by the feathering guidance provided in SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs), build up new coating to overlap all existing adjacent coating edges.
WARNING
Feathering of edges will generate lead/asbestos dust.
A2.2.5.3.3.4.5 Post-surface preparation cleaning, inspection, and clearance. Upon completion of coating removal procedures, do the following, as applicable:
A2.2.5.3.3.4.5.1 Lead dust clean-up. Clean all lead dust from the worksite by suitable clean-up cleaning methods, or as follows:
Step 1 - debris removal: Remove all gross debris, paint chips, etc. using either a vacuum with a
HEPA filter or by spraying the materials with water in a spray bottle and picking up chips or large pieces of contaminated debris by hand.
Step 2 – vacuum cleaning: Using a suitable HEPA vacuum, clean all affected surfaces, in accordance with the following guidelines:
o Begin cleaning with high areas first – with overhead surfaces and bulkheads working downward.
o Vacuum all surfaces in the compartment.
o Work in the direction furthest from the entry door toward it.
Step 3 – wet cleaning: Following thorough HEPA vacuuming, wash all surfaces with any suitable cleaning detergent following the same cleaning pattern (high to low/ furthest from and toward entrance). Change the cleaning solution as it becomes dirty. Rinse all areas with a fresh cloth/mop.
Do not reuse contaminated mops and cloths. Use a three-bucket system for cleaning. (Detergent solution in first bucket/ rinse water for mop in second/ surface rinse on deck and/or bilge surfaces in third).
Step 4 – vacuum cleaning: Perform a HEPA vacuum again as specified in “Step 2”.
Step 5 – waste disposal: Properly dispose of contaminated materials, in accordance with all applicable Federal, state, and local regulations.
WARNING
1. Work Wet, Work Smart, and Work Clean. DO NOT GENERATE DUSTS. It is easier to effectively clean an area when dusts are not being generated to resettle on previously cleaned areas. Worker exposures may be high during wet sweeping.
2 A wet/dry HEPA unit is ideal for working with hazardous dust clean up.
3. Lead-contaminated objects that are porous or materials that may suffer damage from water may not be able to be sufficiently decontaminated by these methods and should be discarded.
A2.2.5.3.3.4.5.2 Substrate inspection. Conduct a visual inspection, in the presence of the Coast Guard Inspector, to ensure that none of the following is present, and submit a CFR:
Visible coatings on any part of the substrate, including pitted areas.
Lead dust.
9 (Rev-1)
Cleaning material haze.
A2.2.5.3.3.4.5.3 Post- abatement clearance. Upon acceptance of the visual inspection results by the COR, do the following:
A2.2.5.3.3.4.5.3.1 Lead dust wipe sampling.
A2.2.5.3.3.4.5.3.1.1 Conduct wipe sampling clearance testing, in accordance with ASTM 6966, in three locations in each affected compartment/space, as designated by the Coast Guard Inspector; to ensure that there exist no lead dust residues in excess of the below-listed concentrations, as specified below in TABLE A2. Submit a CFR with sample results. If a Change Request (CR) has been authorized and released, conduct additional wipe sampling and testing, as designated on the CR.
A2.2.5.3.3.4.5.3.1.2 Ensure that dust lead samples are analyzed by a laboratory certified by the National Lead
Laboratory Accreditation Program (NLLAP) or the American Industrial Hygiene Association.
TABLE A2 - ACCEPTABLE LEAD CONCENTRATIONS
BERTHING AND/OR FOOD PREPARATION AREAS ALL OTHER AREAS
40 micrograms/square foot (mcg/ft 2) 200 micrograms/square foot (mcg/ft 2)
A2.2.5.3.3.4.5.4 Additional lead dust cleaning and sampling. If laboratory analysis proves lead concentrations in excess of the thresholds specified in TABLE A2, then perform lead dust cleaning, and take subsequent wipe samples until the concentration of lead falls below the above standards.
NOTES
1. Be aware that the Coast Guard reserves the right to coordinate additional wipe clearance testing, at no cost to the contractor, to verify the sample results.
2. All additional wipe clearance testing conducted by the Coast Guard must be witnessed by the Contractor, to verify where and how samples were collected – and thus, prevent contract disputes.
A2.2.5.3.3.4.5.3.2 Aggressive sampling – asbestos. After the completion of abatement, take at least five aggressive air samples in each affected compartment/space, using the Phase Contrast Microscopy (PCM) method to determine that the level of airborne fibers for each sample inside the work site is 0.01 or less fiber per cubic centimeter. Perform aggressive air sampling in accordance with EPA 600/4-85-049. Submit a CFR.
A2.2.5.3.3.5 Surface coating.
A2.2.5.3.3.1 Contaminant removal. Prior to applying primer coat, and in accordance with SFLC Std Spec 6310, paragraphs 3.1.8.7 (Flash rusting/surface oxidation limitations) and 3.1.8.6 (Hydrocarbon substance removal), respectively, Remove all flash rusting, as applicable.
Remove all grease and oil surface contaminants.
A2.2.5.3.3.2 Coating application. Coat all prepared surfaces, in accordance with Table A3.
TABLE A3 - COATING SYSTEM
SPOT ABATED AREAS FULLY-ABATED SURFACES AND
10 (Rev-1)
COMPARTMENT/SPACES
Prime and coat all abated surfaces, including adjacent structural members, in accordance with SFLC Std Spec 6310, to match existing adjacent surfaces in accordance with SFLC
Std Spec 6310, Appendix A and Appendix B, as applicable.
Prime and coat all abated surfaces, including adjacent structural members, as specified in applicable work item(s).
A2.2.5.3.4 Waste Disposal. Collect, test, dispose of all generated wastes, including waste water from cleaning of work spaces, in accordance with all applicable Federal, state, and local regulations.”
3.6.4.1 SFLC Std Spec 0000, page 22, paragraph 3.3.3.1 NOTE. Add "Flame-retardant polyethylene deck plate with a non-slip diamond pattern from 10 to 40mil thickness" to body of Note.
3.6.4.2 SFLC Std Spec 0000, page 3, bullet “ISC.” Delete “lead-contaminated materials.”
3.6.4.3 SFLC Std Spec 0000, page 27, after Note box under paragraph 3.3.13.1.2 add the following paragraphs:
“3.3.13.1.3 Dock and Sea trials. The Contractor shall conduct dock trials to test the work performed during the contract when required by individual work items (see 3.3.13 Tests and Inspections). This shall include operational tests or inspections, as appropriate, of all machinery, piping, wiring, insulation, preservation work, deck coverings, and any other article removed, moved, disturbed, or damaged by the Contractor in accomplishing the work outlined in the specification. Schedule for these specific dockside tests or inspections shall be included within the planning document (see 3.2.5 Planning document).
3.6.4.4 SFLC Std Spec 0000, page 11, paragraph 3.2.5, add the following bullets to the bulleted list:
Identifies the “critical paths” for the project.
Shows calculations for the “float” along the critical paths and labels the critical paths with the number of delay days the critical paths can absorb without affecting the final delivery date.
3.6.4.4.1 SFLC Std Spec 0000, page 11,Add the following Note between paragraphs 3.2.5 and 3.2.5.1:
NOTE
Float is the number of days that the critical paths can be delayed without affecting the final delivery date.
3.6.4.4.2 SFLC Std Spec 0000, page 12, and the following paragraph and Note after Figure 1, “3.2.5.4 When the critical path extends beyond or encroaches upon the final delivery date, provide a resource constraint and scheduling evaluation of the critical path before any request for extension will be entertained. Submit the resource constraint and scheduling evaluation via a CFR.
NOTE
The intent of the resource constraint and scheduling evaluation is to identify the resources necessary to ‘crash’ the critical path or make adjustments to the production schedule to meet the delivery date in lieu of a project extension.”
3.3.13.1.3.1 The Contractor shall provide a pier facility or allow the vessel to move to a Coast Guard pier to support dock trials. The Contractor shall not conduct trials that require the vessel to be waterborne while the vessel is floating inside a dock (e.g., graving dock, floating drydock).
3.3.13.1.3.2 Sea trials to conduct equipment operational tests are not required unless a Sea Trial Performance work item is specifically included within the specification.”
11 (Rev-1)
3.6.5 SFLC Std Spec 6310, Requirements For Preservation Of Ship Structures, page 10, add “3.1.6.5
Preconstruction Primers. Also known as shop primers, preconstruction primers are used as a temporary coating to protect steel from corrosion during welding, storage, and fabrication. Preconstruction primers shall be removed prior to applying the permanent coating system on all critical coated surfaces. Preconstruction primers may be left in place in other interior areas (such as machinery spaces, habitability spaces, etc.) if they are intact, uncontaminated, and compatible with the overcoating system.”
3.6.5.1 Std Spec 6310, Appendix B, page B12 , the formatting for of Notes 17-19 change and add as per the following:
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 17, delete sentence, “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area.”
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 18, replace entire note with “Persistent corrosion in a particular area of an aluminum bilge may dictate the need for a protective High Build Epoxy coating to be applied to that local area. “
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Note 19, replace entire note with “Painting plastic surfaces is highly discouraged, but after it is done once, it must be maintained.”
SFLC Std Spec 6310, Cutter And Boat Interior Painting Systems, Appendix B12, Add Note “20. For aluminum surfaces, remove all oil, grease, dirt, metal oxides (corrosion products) and other foreign material by cleaning per SSPC-SP 1 prior to blast cleaning and following blast cleaning immediately prior to coating. The end result of abrasive blasting will be a surface cleanliness similar to that of
SSPC-SP 10 for steel with all coating removed.
3.6.5.2 Std Spec 6310, Appendix E, pages E1, E3, and E4, QA Inspection Forms QA-1, QA-3a, and QA-3b respectively, reference The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface
Preparation Standard SSPC-SP 12/NACE No. 5 erroneously, and are corrected as per the following:
3.6.5.2.1 Std Spec 6310, Appendix E, pages E1, QA Inspection Form QA-1, Check point 5- Surface Preparation, check box description 2, replace “(i.e.: SSPC SP-12, SP-11, SP-10…).” with “(i.e.: SSPC SP-11, SP-10, SP WJ-
2…).”
3.6.5.2.2 Std Spec 6310, Appendix E, page E3, QA Inspection Form QA-3a, Surface Preparation Method column of the Profile Achieved table, 2 nd record, replace “SSPC-SP-12/NACE No. 5” with “SSPC-SP WJ-1/NACE WJ-
1”.
3.6.5.2.2.1 Add record to table beneath “SSPC-SP WJ-1/NACE WJ-1” and label as “SSPC-SP WJ-2/NACE WJ-
2”
3.6.5.2.2.2 Add record to table beneath “SSPC-SP WJ-2/NACE WJ-2” and label as “SSPC-SP WJ-3/NACE WJ-
3”
3.6.5.2.2.3 Add record to table beneath “SSPC-SP WJ-3/NACE WJ-3” and label as “SSPC-SP WJ-4/NACE WJ-
4”
3.6.5.2.3 Std Spec 6310, Appendix E, page E4, QA Inspection Form QA-3b, Surface Preparation Method column of the Profile Achieved table, 2 nd record, replace “SSPC-SP-12/NACE No. 5” with “SSPC-SP WJ-1/NACE WJ-
1”.
12 (Rev-1)
3.6.5.2.3.1 Add record to table beneath “SSPC-SP WJ-1/NACE WJ-1” and label as “SSPC-SP WJ-2/NACE WJ-
2”
3.6.5.2.3.2 Add record to table beneath “SSPC-SP WJ-2/NACE WJ-2” and label as “SSPC-SP WJ-3/NACE WJ-
3”
3.6.5.2.3.3 Add record to table beneath “SSPC-SP WJ-3/NACE WJ-3” and label as “SSPC-SP WJ-4/NACE WJ-
4”
3.6.6 SFLC Std Spec 8635, Temporary Services, page 2, delete paragraph 3.3.2.2.
3.6.7 SFLC Std Spec 5000, Auxiliary Machine Systems, Appendix C, page C9: Replace paragraph C2.8.1.3 and
Table C-3, and add additional paragraphs C2.8.1.4, C2.8.1.5, and C2.8.1.6. as follows:
“C2.8.1.3 Flushing fluid minimum flow rate requirements. Ensure the minimum flow rates provided in Table C-
3 are maintained for each circuit. If multiple loops are flushed concurrently, each loop shall be provided with a flow measuring device. Provide calibrated flow meters. Prior to flushing, submit the certification of calibration to the CG Inspector.
TABLE C-3 - MINIMUM FLOW RATE FOR FLUSHING WITH FLUID
PIPE SIZE INSIDE DIA
(INCH)
GAL/MIN
To 0.5 18
0.5 to 0.75 34
0.75 to 1.0 56
1.0 to 1.25 100
1.25 to 1.5 138
1.5 to 2.0 230
2.0 to 2.5 330
2.5 to 3.0 420
NOTES
1. Flow rates represent minimum flows needed to achieve a turbulent flow condition and maximize benefits of flushing effort.
2. Flow rate selected for flow velocity of 25 ft/sec in the schedule 80/160 pipe, as applicable. If there is a conflict between the pressure and flow rate requirements of this specification, the minimum flow rates shall be governing, unless the working pressure of the system is exceeded. The uses of by-pass (flow control) valves are not allowed downstream of the flow meters.
C2.8.1.4 Whenever a noticeable increase in the pressure drop across strainers is observed, the strainers should be cleaned and bag renewed. Be aware that this may occur as frequency as 15 min intervals.
C2.8.1.5 During flushing, constant monitoring of the flushing oil must be maintained in order to determine the contamination level. Filtering shall continue until the fluid entering the return flow filter meets the particle population ISO cleanliness code of 17/14, in accordance with ISO 4406. All flushing fluid shall pass through the return filter after passing through each system flushing circuit. All samples shall be taken at a point just prior to this filter
13 (Rev-1)
C2.8.1.6 Take a representative sample of oil from the hydraulic system of the hydraulic system. Send samples out for laboratory analysis. Analysis shall include viscosity, moisture, total acid number, particle size and population in sufficient detail to determine ISO cleanliness code of 17/14, in accordance with ISO 4406. Submit CFR.”
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
14 (Rev-1)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
15 (Rev-1)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT.
SURFACE AMBIENT
ΔT
| DP -
Surface |
16 (Rev-1)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
17 (Rev-1)
18 (Rev-1)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Mean Mil Reading (IAW ASTM D4417-Method B)…