A0001-SF30-ORCAS.pdf

PDF 296 KB Posted

Attached to
USCGC ORCAS - Dry Dock Repairs Federal contract opportunity
Solicitation number
HSCG80-13-R-P45030
Issued by
Department of Homeland Security US Coast Guard

About this file

USCGC ORCAS - Amendment 1

View the file

Other files for this federal contract opportunity

Other files attached to USCGC ORCAS - Dry Dock Repairs, newest first.
File Type Posted
ORCAS__WPB_110B__DD_JSZ_13R1.pdf PDF
A0002-SF30-ORCAS.pdf PDF
ORCAS DD FY13 SPECS REV-0.pdf PDF
RFP-ORCAS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLARIFICATIONS AND GOVERNMENT RESPONSES

HSCG80-13-R-P45030

USCGC ORCAS - Dry Dock Repairs

QUESTION 1. In item 1 Hull Plating U/W Body Inspect para. 3.1.6 coating system inspection, it states to visual inspect the U/W body coating system and document the condition. Due to the fact that the scope of work will not be known till after the inspection, the question is shouldn’t item 49 be an optional item, the same as option item 48?

RESPONSE 1. The government already anticipates a partial preservation so WI #49 was labeled as a Definite Item. In the event that the coverage extends more than 33%, WI # 48 would be activated and WI #49 would be de‐ scoped in its entirety.

QUESTION 2. If item 49 is to be a definite item will it be in conjunction with item O‐48?

RESPONSE 2. No (See RESPONSE 1).

QUESTION 3. In item 50 U/W Body Preserve Partial Condition A, para. 3.2.2 U/W Hull Appendages is this part of the 33% or in addition to the 33%.

RESPONSE 3. The appendages are in addition to the 33%.

QUESTION 4. In item 50 Stern Tube Interior surfaces Preserve 100%. Is it the intent of the Coast Guard to only preserve just one the stern tubes?

RESPONSE 4. Yes, the intent is to preserve one stern tube.