87313_DD_SLF_09R1.doc
DOC document 910 KB Posted
- Attached to
- USCGC CORMORANT (WPB-87313) DD Federal contract opportunity
- Solicitation number
- HSCG80-09-Q-3FA005
About this file
Specification dated June 27 2008 Rev-1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| solicitation_Cormorant_DD.DOC | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC CORMORANT (WPB-87313)
87 FOOT PATROL BOAT
SPECIFICATIONS FOR DRYDOCK REPAIRS
Developed By:
Sonya Freeman
Commander (v) Maintenance and Logistics Command, Atlantic 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102
TABLE OF CONTENTS
Work Item Title Page iiiList of Sketches
Revisions Record iv List of Applicable References v List of Government-furnished Property ix List of Critical Inspection Items xi Specification Feedback xii Principal Characteristics xiii General Requirements Welding Repairs- Steel Plate (3/16” Steel Shell Plating) Welding Repairs – Stud Renewal Welding Repairs – Chine Renewal (3/16” Steel Plate) Welding Repairs – Clad Weld Chine Clean and Inspect Oil and Oily Waste Tanks Clean and Inspect Fuel Stowage and Overflow Tanks Clean and Inspect Sewage Tank Clean and Inspect Grey Water Tank Realign Main Engine/Reduction Gear Remove, Inspect, and Reinstall Propeller Shafts Repair Shaft Straighten Shaft Renew Intermediate Water-Lubricated Shaft Bearing Renew Aft Water-Lubricated Shaft Bearing Remove, Inspect, and Reinstall Propellers Perform Minor Repair and Recondition of Propeller Renew Depth Indicating Transducer Inspect Sea Chest Riser Piping and Flanges Remove, Inspect, and Reinstall Rudder Assemblies Renew Rudder Lower Bearing Clean Grey Water Piping System Clean Sewage Piping System Preserve Forward Peak Compartment Preserve Stern Tubes Preserve Underwater Body – “100%” Preserve Freeboard – “100%” Renew Cathodic Protection System Routine Drydocking Provide Temporary Logistics Preserve Bilge Surfaces in the Lazarette Overhaul and Renew Valves
List of Sketches
Work
Item Sketch Number Page
This section is not applicable to this package.
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
| DATE |
| REV# |
| WORK ITEM# |
| CHANGES MADE |
| 06/27/08 |
| 1 |
| 18 |
| Revised paragraph 3.1.2 to include “Overhaul and Renew Valves” as a related work item. |
| 26 |
| Inserted new paragraph 3.2.2 “Stern Door Inspection” and renumbered subsequent paragraph. |
| 26 |
| Revised paragraph 5.1 to include RHIB notch area. |
| 31 |
| Added new work item “Overhaul and Renew Valves”. |
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address: http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp. Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with MLCA Standard Specification 0000_STD, paragraph 3.2 (Order of precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)
MIL-STD-1687A, Sep 1994, Thermal Spray Processes For Naval Ship Machinery Application
MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 1001_STD, 2004 Edition, Temporary Hull Accesses
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8634_STD, 2004 Edition, Drydocking
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8635_STD, 2004 Edition, Provide Temporary Logistics
DRAWINGS
Coast Guard Drawing 87 WPB 085-003, Rev C, Docking Plan
Coast Guard Drawing 87 WPB 085-010, Rev C, Docking Plan
Coast Guard Drawing 87 WPB 085-011, Rev B, Lifting Slings
Coast Guard Drawing 87 WPB 085-012, Rev-, Lifting Cradle
Coast Guard Drawing 87 WPB 161-002, Rev-, Stern Tube Details Anode Access Ports Coast Guard Drawing 87 WPB 163-001, Rev F, Sea Chest Details Coast Guard Drawing 87 WPB 165-001, Rev D, Transducer Details
Coast Guard Drawing 87 WPB 182-001, Rev-, Main Engine and Generator Foundations
Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details
Coast Guard Drawing 87 WPB 245-002, Rev-, Propeller Details
Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details
Coast Guard Drawing 87 WPB 256-001, Rev T, Sea Water Cooling Piping Coast Guard Drawing 87 WPB 304-001, Rev B, Wireway Arrangement
Coast Guard Drawing 87 WPB 561-001, Rev G, Steering System Details
Coast Guard Drawing 87 WPB 562-001, Rev-, Rudder Details
Coast Guard Drawing 87 WPB 593-001, Rev K, Sewage Piping Coast Guard Drawing FL 6713-201, Rev B, Transducer adapter assembly
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual Coast Guard Technical Publication (TP) 4593B, Mar 2003, SWBS 562, Rudderstock Seal-Type EJ
Coast Guard Technical Publication (TP) 4593C, Jan 2008, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.
INDUSTRY STANDARDS
American Bureau of Shipping (ABS), 2, Rule Requirements for Survey After Construction, 2006, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
ASTM International (ASTM) A131, 2004, Standard Specification for Structural Steel for Ships ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D3951, Re-approved 2004, Standard Practice for Commercial Packaging
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant Alignment Instructions 8V396 TE94/Flange mounted BW 255
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-Petrolatum
Deep Sea Seals Tech Pub (TP) TM-EL-68839, Issue A, Mar 2005, Rudderstock Seal Type EJ
International Organization for Standardization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
| WORK ITEM |
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/Unit)
| 10 |
| N |
| **Propeller shaft |
| NSN: 2010-01-458-9175 |
| 2 ea. |
| 9,566.14 |
| 10 |
| N |
| Type FSE Face (split) |
| PN: H75440-01-2-2 |
NSN: 5330-01-521-3559
| 2 ea. |
| 2,042.57 |
| 10 |
| N |
| Type FSE Seal (split) |
| PN: H75440-01-1-1 |
NSN: 2040-01-521-2654
| 2 ea. |
| 4,186.26 |
| 10 |
| N |
| Type FSE Seal Cup (split) |
| PN: H75440-01-1-3 |
NSN: 3120-01-521-2390
| 2 ea. |
| 232.66 |
| 10 |
| N |
| Type FSE O-Cord |
| PN: H75440-01-1-4 |
NSN: 3120-01-521-2268
| 2 ea. |
| 266.80 |
| 10 |
| N |
| Type FSE Emergency Seal |
| PN: H75440-01-3-6 |
NSN: 5330-01-521-4855
| 2 ea. |
| 345.16 |
| 10 |
| N |
| Splashguard 4” FSE |
| PN: H75440-01-2-5 |
| 2 ea. |
| 395.73 |
| 10 |
| N |
| Clamp, Splashguard 4” FSE |
| PN: H75440-01-2-6 |
| 2 ea. |
| 37.84 |
| 10 |
| N |
| **Shaft Seal Bellow |
| PN: H75440-01-2-1 |
NSN: 5340-01-521-3573
| 2 ea. |
| 446.96 |
| 10 |
| N |
| *Compression Tool Assembly |
| N/A |
| 1 ea. |
| 200.00 |
| 10 |
| N |
| *Alignment Kit |
| N/A |
| 1 set |
| 3,000.00 |
| 13 |
| N |
| **Thordon bearing, Grade Orange |
(5.5" OD x 4" ID x 7.87" (200mm) LG)
PN: F54615-02-8-1
NSN: 3120-21-914-2012
| 2 ea. |
| 318.25 |
| 14 |
| N |
| **Thordon bearing, Grade Orange |
(5.5" OD x 4" ID x 11.41" (290mm) LG)
PN: F54615-02-8-0
NSN: 3120-21-914-2011
| 2 ea. |
| 410.02 |
| 15 |
| Y |
| **Starboard Propeller (RH) |
| PN: RH706-3350.00 |
NSN: 2010-01-457-0573
| 1 ea. |
| 12,498.00 |
| 15 |
| Y |
| **Port Propeller (LH) |
| PN: LH706-3350.00 |
NSN: 2010-01-459-0421
| 1 ea. |
| 12,498.00 |
| 15 |
| N |
| *Propeller Nut Wrench |
| N/A |
| 1 ea |
| 200.00 |
| 15 |
| N |
| **Propeller Nut |
| NSN: 2010-01-458-9217 |
| 2 ea. |
| 281.00 |
| 15 |
| N |
| **Propeller Nut, Locking |
| NSN: 5310-01-458-9125 |
| 2 ea. |
| 252.94 |
| 15 |
| N |
| Anode, Propeller Nut |
| NSN: 5342-01-481-8403 |
| 2 ea. |
| 239.51 |
| 17 |
| N |
| ***SS555 Sonar Transducer |
| NSN: 5845-01-465-9723 |
PN: M78733
| 1 ea. |
| 149.45 |
| 19 |
| Y |
| **Rudder Assembly, port |
| NSN: 2040-01-461-1944 |
PN: 87 WPB 561-001 PORT
| 1 ea. |
| 2,000.00 |
| 19 |
| Y |
| **Rudder Assembly, starboard |
| NSN: 2040-01-461-1943 |
PN: 87 WPB 561-001 STBD
| 1 ea. |
| 2,000.00 |
| 19 |
| N |
| Upper Roller Bearing |
| NSN: 3110-01-512-5534 |
SKF21318CC
| 2 ea. |
| 244.62 |
| 19 |
| N |
| Wartsila Lips EJ Seals Kit |
| P/N: H75492-01 |
NSN: 5330-01-491-7554
| 2 ea. |
| 3,311.63 |
| 20 |
| N |
| **Thordon Bearing |
| NSN: 3120-20-000-7677 |
P/N: TBFF113090
| 2 ea. |
| 332.72 |
| 28 |
| N |
| *Transducer cover plate |
| N/A |
| 1 ea. |
| 200.00 |
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment (ESD).
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):
Work Item Title
Remove, Inspect, and Reinstall Propeller Shafts Inspect Sea Chest Riser Piping and Flanges Remove, Inspect, and Reinstall Rudder Assemblies Preserve Forward Peak Compartment Preserve Stern Tubes Preserve Underwater Body – “100%” Preserve Bilge Surfaces in the Lazarette Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities. All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/specfeedback.asp
PC_87_WPB
(21 Mar 2005) Principal Characteristics
87’ WPB COASTAL PATROL BOAT
| Length Overall |
| 87’ 0” |
| Depth (main deck at frame 13 side to baseline) |
| 10’ 11” |
| Maximum Beam |
| 19.4’ |
| Height of Highest Projection (above DWL) |
| 50.2’ |
| Frame Spacing |
| Various |
| Full Load Draft |
| 5’ 9” |
| Full Load Displacement |
| 93.5 long tons |
| Shore Tie Voltage Requirements |
| 450v |
PROPELLER / SHAFT
| Number of Propellers |
| 2 |
| Number of Blades per Propeller |
| 5 |
| Diameter of Propeller |
| 1040 mm |
| Pitch |
| 1230 mm fixed |
| Revolutions per Minute (RPM) |
| 828 |
| Shaft Diameter |
| 4” |
00000_PWB_FLT (08 Apr 2008)
General Requirements
1. SCOPE
1.1 Scope. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and nondestructive inspection (NDI), in accordance with Std Spec 0740_STD.
3.4 Term substitution – COTR for COR. The Contractor shall be aware that the term “COR” (Contracting Officer’s Representative) has been discontinued in favor of “COTR” (Contracting Officer’s Technical Representative); consequently, whenever “COR” is encountered in this specification package, including referenced standard specifications and other referenced documents, it shall refer to “COTR”, explicitly.
3.5 Small boat storage particulars. When a small boat Rigid Hull Inflatable (RHI) boat is removed as interference to Contractor-work, the Contractor shall provide a suitable pierside storage cradle, for safely storing said boat.
3.5.1 Cradle design. Ensure that the cradle meets the following criteria:
· Be capable of safely supporting a boat weighing approximately 5100 pounds.
· Support the boat at the following locations:
· Along the full length of the flat portion of the keel.
· Forward and aft, in the locations similar to those provided by the shipboard davit cradle.
· Have the portions of the cradle directly contacting the hull or keel of the boat made from a homogeneous soft wood, such as Yellow Pine or Douglas Fir.
3.5.2 Boat protective cover. Provide a watertight cover with raised wooden spreaders, to protect the small boat from nature, during the storage period.
3.5.3 Boat accessibility. Ensure the storage is located in the vicinity of the vessel, and is unrestricted, to allow for ship's force to complete maintenance, if required.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address:
http://www.uscg.mil/directives/cim.asp
5.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in Std Spec 0000_STD to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this item.
QA-1: QUALITY ASSURANCE INSPECTION FORM - PRESERVATION CHECKLIST
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 –2.5 for surfaces to be coated w/single coat of inorganic zinc).
Measure soluble salt conductivity (5 measurements per 1000 sqft) – maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the Coating Manufacturer(s).
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness.
Verify system cure for service resumption - U/W Body surfaces: 5-8 hours @ 77 degrees F; Potable water tanks: 7 days @ 77 degrees F.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure (minimum 7 days @ 77 degrees F.), to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Signature of Inspector:______________________________________________________Date:____________
QA-2. QUALITY ASSURANCE INSPECTION FORM
ENVIRONMENTAL READINGS
(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)
| DATE |
| TIME |
| ENTER ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…) |
| LOCATION |
| DEW POINT |
| SURFACE TEMP. |
| % REL. HUMIDITY |
| SIGNATURE OF INSPECTOR |
.Signature of Inspector:__________________________________________________Date:____________
QA-3 QUALITY ASSURANCE INSPECTION FORM
SURFACE PROFILE LOG
Vessel Name And Hull Number:__________________________________________________
Work Item Title:_______________________________________________________________
Location Of Work (Including Frame Numbers):_____________________________________
Area (Square Feet):_____________
Surface Preparation Method:_____________________________________________________
Abrasive Manufacturer And Size:_________________________________________________
Degreasing Method Used:________________________________________________________
Number Of Hours Surfaces (Steel Only) Left Unpainted:______________________________
Sweep blasting performed to remove flash rusting (steel)? Yes/No:_____________________
Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record.
Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.
AVERAGE MILS
(IAW ASTM D4417, METHOD C)
Place Surface Profile Replica Tape Here
Reading:__________ mils
· Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Date and Time:__________________________________________________
Location of Surface Profile Measurements:___________________________________________________________
Signature of Inspector:____________________________________________________________________________
QA-4. QUALITY ASSURANCE INSPECTION FORM
SURFACE SOLUBLE SALT CONDUCTIVITY LOG
Vessel Name and Hull Number:__________________________________________________
Work Item Title:_______________________________________________________________ Location of Work (including frame numbers):_______________________________________
Area (square feet):____________
| DATE |
| TEST LOCATIONS |
| CONDUCTIVITY |
(microsiemens/cm)
Date and Time:_________________________________________
Signature of Inspector:___________________________________
QA-5. QUALITY ASSURANCE DATA FORM
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2
(Use one sheet for each sequence)
Vessel Name and Hull Number:__________________________________________________
Work Item Title:______________________________________________________________
Coating Manufacturer:_________________________________________________________
Product Name:________________________________________________________________
Batch Number:________________________________________________________________
Induction Time:_______________________________________________________________
Coating System Sequence (Indicate whether: primer, touch-up primer, barrier coat, 3rd coat…):__________________
DFT
MEASUREMENT NUMBER
| LOCATION OF READINGS |
| MEASURED DFT |
Application Method (Airless, Conventional Spray, Rolled):____________________
Average DFT: __________________________________________________________
Date and Time: _________________________________________________________
Signature of Inspector: ___________________________________ 07400_DOD_FLT (13 May 2008) 87WPB (13 May 2008) WORK ITEM 1: Welding Repairs- Steel Plate (3/16” Steel Shell Plating)
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to perform welding repairs of 3/16” steel shell plating.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes ASTM International (ASTM) A131, 2004, Standard Specification for Structural Steel for Ships
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD. Be aware that this work item includes all welding related activities only and does not include interference removal.
3.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Piping.
· Strainers.
· Deck plate foundation.
3.3 Structural steel replacement. The Contractor shall be aware that the hull structure (plates, shapes, and bars) for the 87WPB class cutters is made primarily with ABS AH36 steel; if the ABS steel cannot be obtained for the hull structure, ASTM A131 Grade AH36 can be substituted.
3.4 Electronic equipment protection. The Contractor shall safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference. Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.5 Renewal. The Contractor shall renew the designated 3/16” steel shell plating.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Electronic equipment protection. The Coast Guard Inspector shall accomplish the following prior to welding:
· Secure wheelhouse power supply to the ODR, MCS, and RCS systems.
· Secure engine room power supply to the GCU and CCS box.
· Disconnect all cannon plugs to the main engine governors (ECS-UNI).
· Remove all PIMS on MTU control systems.
· Disconnect all power to the Bridge electronics.
· Secure power to the battery chargers.
· Disconnect engine room batteries.
07400_DOD_FLT (13 May 2008) 87313_SLF (13 May 2008) WORK ITEM 2: Welding Repairs – Stud Renewal
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to perform welding repairs of the RHIB notch pad studs.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD. This work item includes all welding related activities only and does not include interference removal.
3.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Piping.
· Insulation (40 square feet).
· Sheathing.
· Wiring.
3.3 Electronic equipment protection. The Contractor shall safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference. Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.4 Stud renewal. The Contractor shall furnish and renew 13 stainless steel (16 TPI, 3" x 3/8", trim to fit) studs and associated nuts and washers for the RHIB notch pads. Be aware that insulation is an interference, in way of stud renewal.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Electronic equipment protection. The Coast Guard Inspector shall accomplish the following prior to welding:
· Secure wheelhouse power supply to the ODR, MCS, and RCS systems.
· Secure engine room power supply to the GCU and CCS box.
· Disconnect all cannon plugs to the main engine governors (ECS-UNI).
· Remove all PIMS on MTU control systems.
· Disconnect all power to the Bridge electronics.
· Secure power to the battery chargers.
· Disconnect engine room batteries.
07400_DOD_FLT (13 May 2008) 87313_SLF (13 May 2008) WORK ITEM 3: Welding Repairs – Chine Renewal (3/16” Steel Plate)
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to perform welding repairs to the chine area.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes ASTM International (ASTM) A131, 2004, Standard Specification for Structural Steel for Ships
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD. This work item includes all welding related activities only and does not include interference removal.
3.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Hull plate.
3.3 Structural steel replacement. The Contractor shall be aware that the hull structure (plates, shapes, and bars) for the 87WPB class cutters is made primarily with ABS AH36 steel; if the ABS steel cannot be obtained for the hull structure, ASTM A131 Grade AH36 can be substituted.
3.4 Electronic equipment protection. The Contractor shall safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference. Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.5 Renewal. The Contractor shall crop and renew the designated chine metal.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Electronic equipment protection. The Coast Guard Inspector shall accomplish the following prior to welding:
· Secure wheelhouse power supply to the ODR, MCS, and RCS systems.
· Secure engine room power supply to the GCU and CCS box.
· Disconnect all cannon plugs to the main engine governors (ECS-UNI).
· Remove all PIMS on MTU control systems.
· Disconnect all power to the Bridge electronics.
· Secure power to the battery chargers.
· Disconnect engine room batteries.
07400_DOD_FLT (13 May 2008) 87313_SLF (13 May 2008) WORK ITEM 4: Welding Repairs – Clad Weld Chine
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clad weld repair the chine.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes ASTM International (ASTM) A131, 2004, Standard Specification for Structural Steel for Ships
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD. This work item includes all welding related activities only and does not include interference removal.
3.2 Structural steel replacement. The hull structure (plates, shapes, and bars) for the 87WPB class cutters is made primarily with ABS AH36 steel. If the ABS steel cannot be obtained for the hull structure, ASTM A131 Grade AH36 can be substituted.
3.3 Electronic equipment protection. The Contractor shall safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference. Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.4 Clad Weld Chine. The Contractor shall clad weld the designated chine metal.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Electronic equipment protection. The Coast Guard Inspector shall accomplish the following prior to welding:
· Secure wheelhouse power supply to the ODR, MCS, and RCS systems.
· Secure engine room power supply to the GCU and CCS box.
· Disconnect all cannon plugs to the main engine governors (ECS-UNI).
· Remove all PIMS on MTU control systems.
· Disconnect all power to the Bridge electronics.
· Secure power to the battery chargers.
· Disconnect engine room batteries.
12310_DLA_FLT (13 May 2008)
87 WPB (27 May 2008) WORK ITEM 5: Clean and Inspect Oil and Oily Waste Tanks
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
| TYPE OF TANK |
| LOCATION |
| CAPACITY |
(gallons)
| Dirty Oil |
| Port Centerline |
| 85 |
| Oily Water |
| Stbd Centerline |
| 85 |
2. APPLICABLE DOCUMENTS
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.1.2 Related work item. The Contractor shall accomplish this work item in conjunction with “Routine Drydocking”, a separate work item in this specification package.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank residual contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition.
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
4. QUALITY ASSURANCE
4.1 Operational test – final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12311_DLA_FLT (21 Mar 2008)
87 WPB (27 May 2008) WORK ITEM 6: Clean and Inspect Fuel Stowage and Overflow Tanks
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
| TYPE OF TANK |
| LOCATION |
| CAPACITY |
(gallons)
| Diesel fuel |
| Stbd Centerline |
| 1450 |
| Diesel fuel |
| Port Centerline |
| 1450 |
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.1.2 Related work item. The Contractor shall accomplish this work item in conjunction with “Routine Drydocking”, a separate work item in this specification package.
3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall dispose of tank residual contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition.
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
4. QUALITY ASSURANCE
4.1 Operational test – final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12319A_FLT (09 Nov 2007)
87 WPB (18 Sep 2007) WORK ITEM 7: Clean and Inspect Sewage Tank
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean the below designated tanks:
| TYPE OF TANK |
| LOCATION |
| CAPACITY (gallons) |
| Sewage (stainless steel, uncoated) |
| Hold Deck between Frames 6 and 8, 3-7-0-W |
| 363 |
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which are separate work items in this specification package:
· “Routine Drydocking”.
· “Clean Sewage Piping System”.
3.1.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Tank level indicators.
· Access covers.
3.2 Cleaning requirements. The Contractor shall do the following for the designated tanks listed in paragraph 1.1:
3.2.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLI’s to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations. (Note: Tank content removal is covered under “Routine Drydocking”, a separate work item in this specification package.)
3.2.3 Cleaning requirements. Remove manhole covers. Clean the designated structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove cleaning media and residues continuously from the tanks during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.2.4 Inspection. Visually inspect all interior surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Tank level indicator (TLI) condition.
· Suction and fill piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.3 Closing. The Contractor shall ensure that the tanks remain open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank. After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole covers with new gasket material conforming to ASTM D1330. Renew all stainless steel fasteners. The Contractor shall clean and reseal all tank sight glasses, if applicable, prior to reinstallation.
4. QUALITY ASSURANCE
4.1 Operational test - final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLI’s to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12319A_FLT (09 Nov 2007)
87 WPB (18 Sep 2007) WORK ITEM 8: Clean and Inspect Grey Water Tank
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean the below designated tanks:
| TYPE OF TANK |
| LOCATION |
| CAPACITY (gallons) |
| Grey Water (stainless steel, uncoated) |
| Below Hold Deck between Frames 8 and 9, 3-7-1-W |
| 55 |
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which are separate work items in this specification package:
· “Routine Drydocking”.
· “Clean Grey Water Piping System”.
3.1.2 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Tank level indicators.
· Access covers.
3.2 Cleaning requirements. The Contractor shall do the following for the designated tanks listed in paragraph 1.1:
3.2.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLI’s to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations.
3.2.3 Cleaning requirements. Remove manhole covers. Clean the designated structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove cleaning media and residues continuously from the tanks during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.2.4 Inspection. Visually inspect all interior surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Tank level indicator (TLI) condition.
· Suction and fill piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.3 Closing. The Contractor shall ensure that the tanks remain open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank. After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole covers with new gasket material conforming to ASTM D1330. Renew all stainless steel fasteners. The Contractor shall clean and reseal all tank sight glasses, if applicable, prior to reinstallation.
4. QUALITY ASSURANCE
4.1 Operational test - final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLI’s to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
23320L_87 (21 Apr 2008)
WORK ITEM 9: Realign Main Engine/Reduction Gear
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to realign a designated main diesel engine and its corresponding reduction gear assembly to the propeller shaft.
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 87 WPB 182-001, Rev-, Main Engine and Generator Foundations Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant Alignment Instructions 8V396 TE94/Flange mounted BW 255
3. REQUIREMENTS
3.1 General. The Contractor shall use USCG CPB Project MTU-FA 771903 as a guide.
3.1.1 Related work item. The Contractor shall accomplish this work in conjunction with "Remove, Inspect, and Reinstall Propeller Shafts”, which is a separate work item in this specification package.
3.1.2 Personnel qualification. The Contractor shall ensure that the shaft alignment is performed under the direct supervision of personnel experienced in and regularly engaged in shaft and engine alignment. The qualified personnel shall meet the following requirements:
· Be familiar with manufacturer's installation techniques, able to assist with proper bearing and shaft alignment, analyze shaft and bearing clearances, and ensure compliance with engine/reduction gear manufacturer's standards during inspection and installation of the engine and shaft system.
· Have a resume of previously demonstrated alignment experience as described within this work item.
· Be able to provide a list of references upon request to the COTR.
3.2 Alignment preparation. Prior to shaft realignment, the Contractor shall ensure the following conditions are met for at least 24 hours before the alignment check:
· The vessel is waterborne with fuel, water, and temporary ballast tanks filled to normal operating levels, a minimum of three-quarters capacity.
· All major equipment and machinery weighing over 1,000 pounds (450 kilograms) are either installed or simulated by equivalent weights appropriately located.
3.3 Shaft realignment. The Contractor shall accomplish the shaft realignment using Coast Guard Drawings 87 WPB 182-001, 87 WPB 243-001, and Engine/Gearbox Plant Alignment Instructions (USCG CPB Project MTU-FA 771903) as guidance.
3.3.1 Alignment adjustment. Correct any misalignment by repositioning the propulsion engines and reduction gears. Chock resin the engine foundations in place as necessary.
3.3.2 Final readings. Recheck all alignment readings, insert the bolts in the flanges, and tighten to the proper torque for the size and type.
NOTICE!
The tightening torque for the flange bolts shall be 430 Nm according to Engine/Gearbox Plant Alignment Instructions (USCG CPB Project MTU-FA 771903.
3.3.3 Report. After taking the alignment readings, submit to the COTR a written report of all the final readings within 24 hours after alignment check.
4. QUALITY ASSURANCE
4.1 Operational test. The Contractor shall demonstrate proper operation of the propeller shaft without binding during sea trials. Inspect and correct any abnormal noise and vibration generated from the shaft or bearings.
5. NOTES
This section is not applicable to this work item.
24313_ANL_87 (14 May 2008)
WORK ITEM 10: Remove, Inspect, and Reinstall Propeller Shafts
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to remove, inspect, and reinstall the port and starboard propeller shafts.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes Coast Guard Drawing 87 WPB 243-001, Rev M, Propulsion Shaft Details Coast Guard Technical Publication (TP) 4593C, Jan 2008, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seals, John Crane Type F.S.E.
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraphs:
· 3.3 (Shaft inspections).
· 3.5 (Bearing inspections).
· 3.6 (Establishing baseline bearing positions).
· 3.8 (Stern tube inspection).
3.1.2 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which are separate work items in this specification package:
· “Remove, Inspect, and Reinstall Propellers”.
· “Remove, Inspect, and Reinstall Rudder Assemblies”.
3.1.3 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the following:
· Deck plates.
· Deck plate framing.
· Stern tube mid bearing access hatch.
· Stern tube aft bearing access hatch.
3.1.4 Weighing of shaft coupling. The Contractor shall weigh the shaft coupling and its hardware, and clearly stamp the total weight into the body of the coupling (i.e. WT XX#).”
3.1.5 Standard forms. The Contractor shall complete and submit the measurement forms at the end of this work item as part of the required CFR/CIR's.
3.1.6 Initial shaft coupling alignment check. The Contractor shall, prior to the vessel’s initial drydocking, perform the bore and face alignment between the reduction gear output flange and shaft coupling per paragraphs 3.10.1 and 3.10.2. Submit CFR.
3.2 Removal. The Contractor shall remove each shaft, using Coast Guard Drawing 87 WPB 243-001 as guidance.
3.2.1 Protect the shaft from damage during removal, storage, and reinstallation.
3.2.2 Ensure the shaft is properly supported at all bearing journals while being transported, inspected, and stored.
3.3 Shaft inspections. The Contractor shall clean each shaft of all surface contaminants; set up the shaft in a lathe, and accomplish the following in-shop inspection. Submit a CIR:
3.3.1 Visual inspection. Visually inspect the…
This is the start of the file's text. The full file is on GovTribe.