HR001118S0053_Att_2_Summary_Charts.PPTX

PPTX presentation 2 MB Posted

Attached to
Atomic-Photonic Integration Federal contract opportunity
Solicitation number
HR001118S0053
Issued by
Defense Advanced Research Projects Agency

About this file

This PowerPoint presentation outlines a technical proposal for an atomic-photonic integration research project. It includes an abstract, technical rationale and approach, team organization and costs by phase, schedule, and budgets broken down by task, performer, and category. The proposal involves developing a new class of atom-based systems utilizing integrated photonics and trapped atoms to enable high-performance, robust, portable clocks and gyroscopes. The related federal contract opportunity is a pre-solicitation notice from the Defense Advanced Research Projects Agency seeking research proposals for the atomic-photonic integration concept with responses due on an unspecified future date.

Not Listed

View the file

Other files for this federal contract opportunity

Other files attached to Atomic-Photonic Integration, newest first.
File Type Posted
HR001118S0053.pdf PDF
HR001118S0053_Att_1_Proposer_Checklist.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Abstract or Proposal Title Principal Investigator (organization) | Teaming Partner Organizations | Total budget Technical Rationale and Approach Team Organization and Cost Innovative Claims What are most significant challenges?

Why will it succeed?

What is unique about your approach?

What are you trying to do?

Include a figure that captures the technical approach, if supportive.

Proposed team organization and responsibilities.

Proposed cost by program phase.

Technical Results Prior results from team that support proposed concept.

SOURCE SELECTION SENSITIVE – SEE FAR 2.101 AND 3.104

Schedule

SOURCE SELECTION SENSITIVE – SEE FAR 2.101 AND 3.104

Phase 1Phase 2
2019202020212022
SOW Task456789101112123456789101112123456789101112123
1.1
1.2
…
1.n
2.1
…
2.n
…

Phase I Budget

SOURCE SELECTION SENSITIVE – SEE FAR 2.101 AND 3.104

SOW TaskFTELaborMaterialsEquipmentFTELaborMaterialsEquipmentTotal
1.1X.X$$$X.X$$$$
1.2X.X$$$X.X$$$$
1.3X.X$$$X.X$$$$
1.4X.X$$$X.X$$$$
…………………………
1.nX.X$$$X.X$$$$
TotalX.X$$$X.X$$$$

Prime Contractor Subcontractor 1 Breakdown of costs by subtask, performer (prime and all subcontractors), and major category

SOW TaskFTELaborMaterialsEquipmentFTELaborMaterialsEquipmentTotal
2.1X.X$$$X.X$$$$
2.2X.X$$$X.X$$$$
2.3X.X$$$X.X$$$$
2.4X.X$$$X.X$$$$
…………………………
2.nX.X$$$X.X$$$$
TotalX.X$$$X.X$$$$

Phase II Budget Prime Contractor Subcontractor 1

SOURCE SELECTION SENSITIVE – SEE FAR 2.101 AND 3.104

Breakdown of costs by subtask, performer (prime and all subcontractors), and major category image21.png image1.jpeg image2.png image3.jpeg image7.jpeg image8.png image9.png image13.jpeg