Question_and_Responses.DOC

DOC document 14 KB Posted

Attached to
DISA PAC HVAC Federal contract opportunity
Solicitation number
HC102819R0005
Issued by
Defense Information Systems Agency

About this file

Questions and Responses to the RFP

View the file

Other files for this federal contract opportunity

Other files attached to DISA PAC HVAC, newest first.
File Type Posted
HC102819R0005.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Responses

HC102819R0005

1) Q: What make and model units comprise the existing system?

A:Make: Data Aire 26 Ton
Condenser Model: DARC 2832
Serial Numbers:2007-4657-E
2007-4658-E
2007-4659-E
Evaporator Model: DAAU 2632
Serial Numbers: 2007-4654-E
2007-4655-E
2007-4656-E

2) Q: What is the available electric? (3 phase, single phase, 460?)

A: 3 Phase, 208vAC

3) Q: Information on the existing Trane BAS monitoring system, if available.

A: Please contact Trane POC: R J Ritter (808) 352-0197 rjritter@trane.com

4) Q: What, if any, are the desired features for the new units? (Liebert units tend to be built to order.)

A: 30-Ton with similar features to what we have now.

5) Q: Please provide the model and information regarding the existing Trane BAS monitoring system.

A: Please contact Trane POC: R J Ritter (808) 352-0197 rjritter@trane.com

6) Q: Has the Trane BAS monitoring been upgraded to remain current?

A: Please contact Trane POC: R J Ritter (808) 352-0197 rjritter@trane.com

7) Q: Please provide height of building where the rooftop units are to be installed. This information is required to enable estimation for size of crane. Also are there any surrounding impediments to a crane lift, such as overhead wires.

A: The building is approximately 35’ high. There are there no surrounding impediments to a crane lift. There are no overhead wires or other obstructions. The building is set off from any tall structures or overhead wires. The crane or boom will have a clear shot, from the front of the building to remove rooftop condensers.

8) Q: Please provide any minutes generated by the site visit.

A: No minutes were captured. It was just a walk through on the roof and in the building. No significant discussions were held or questions were asked.

Comment made to contractors: Specified that a 30-ton unit was preferred, since 26-Ton units are no longer manufactured, nor meet requirements to cool the room. Also that we would prefer Liebert or Trane HVAC units if it is not possible to obtain Data Aire.