CLARIFICATIONS.pdf
PDF 8 KB Posted
- Attached to
- RECOVERY: Flint Courthouse Chiller System Upgrades Federal contract opportunity
- Solicitation number
- GS-05P-10-SP-C-0004
About this file
Clarifications for all contractor questions regarding the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WALK THRU INFORMATION.pdf | ||
| Site Visit Sign-In Sheet Handout.pdf | ||
| Site Visit Information.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLARIFICATIONS
FLINT CHILLER SYSTEM UPGRADES
SOLICITATION GS05P10SPC0004
Q1. What is the routing for trash and deliveries to the target space?
A1. There is hallway access in the basement to the loading dock, outside of which is where the placement of the dumpster shall be.
Q2. Can the existing support steel be reused for the new support system?
A2. The steel specifications and dimensions must adhere to the specifications and drawing documents.
Q3. No new controls were specified, was it GSA’s intent to have new controls for the chillers?
A3. No new controls are included in this project. GSA plans to separately procure and install chiller system controls.
Q4. Is there any asbestos removal required for this job?
A4. No, there is no asbestos removal required.