General Provisions - Apr 2021 - Copy.docx

DOCX document 108 KB Posted

Attached to
Remove and Replace Red Carpet Bricks Main Apron Federal contract opportunity
Solicitation number
MC1010-1
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Other files attached to Remove and Replace Red Carpet Bricks Main Apron, newest first.
File Type Posted
MC1010 Question and Answers.docx DOCX document
ADD1-MC1010.docx DOCX document
OK21 1-6-23 MOD 0.pdf PDF
MC1010 Instructions to Offeror - Copy.docx DOCX document
FP1017360 SoW - Repair Red Carpet on Main Parking Apron F7001.pdf PDF
W-9 as of november 2018 per the IRS.pdf PDF
PR-FRM-12 Rev 09 Annual Commercial item Acquisition Reps Certs Form - Copy.docx DOCX document
Federal Supplement Apr 2021 - Copy.docx DOCX document
Q A Form 004 - Copy.docx DOCX document
MC1010 Solicitation and Offer.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enter P.O./ ContractNumber Below:

ASRC Federal Holding Company and Subsidiary Companies (CONTRACTOR) General Provisions and FAR Flowdown Provisions for Subcontracts for Construction Services Under a U.S. Government Prime Contract

GENERAL PROVISIONS

1 Formation of Contract and Terms and Conditions 2 Description of Work 3 Applicable Laws 4 Contract Documents 5 Price 6 Payment 7 Assignment and Subcontracting 8 Changes 9 Inspection and Defective Work 10 Default 11 Delays by Subcontractor 12 Extension of Time and Delays 13 Loss or Damage to Work 14 Indemnification 15 Insurance 16 Bonds 17 Patents 18 Termination for Convenience 19 Time of Performance 20 Warranty 21 Disputes 22 Ceaning Up 23 Ethics and Compliance 24 Labor to be Employed 25 Taxes and Contributions 26 Accident Pevention and other Policies 27 U.S. Government Prime Contract 28 Audit 29 Severability 30 Entire Agreement

GENERAL PROVISIONS

Formation of Contract and Terms and Conditions

This Contract, made as of the ___ day of ___ in the year ___ by and between ASRC Holding Company and Subsidiary Companies (hereinafter called the Contractor) and __________ (hereinafter called the Subcontractor).

Witnesseth, that the Subcontractor and Contractor agree as follows:

Description of Work

The Subcontractor shall perform and furnish all the work, labor, services, materials, plant, equipment, tools, scaffolds, appliances and other things necessary for ___ (hereinafter called the Work) for and at the ___ (hereinafter called the Project), located on premises at ___ (hereinafter called the Premises), as shown and described in and in strict accordance with the Plans, Specifications, General Conditions, Special Conditions and Addenda thereto prepared by ___ (hereinafter called the Architect) and with the terms and provisions of the General Contract (hereinafter called the General Contract) between Contractor and ___ (hereinafter called the Government) dated ___ and in strict accordance with the Additional Provisions, page(s) ___ annexed hereto and made a part hereof. Additional or differing terms or conditions proposed by Subcontractor or included in Subcontractor’s acknowledgment hereof are hereby objected to by Contractor and have no effect unless accepted in writing by Contractor.

1. Applicable Laws

(a)This Contract shall be governed by the laws of the state of Maryland, excluding its choice of laws rules, except that any provision in this Contract that is (i) incorporated in full text or by reference from the Federal Acquisition Regulation (FAR); or (ii) incorporated in full text or by reference from any agency regulation that implements or supplements the FAR or; (iii) that is substantially based on any such agency regulation or FAR provision, shall be construed and interpreted according to the federal common law of government contracts as enunciated and applied by federal judicial bodies, Boards of Contracts Appeals, and quasi-judicial agencies of the Federal Government.
(b)(1)Subcontractor agrees to comply with all applicable laws, orders, rules, regulations, and ordinances of the United States and the country where Subcontractor will be performing the Contract.
(2)If, as a result of any violation of applicable laws, orders, rules, regulations, or ordinances by Subcontractor, its officers, employees, agents, suppliers, or subcontractors at any tier, (i) Contractor’s General Contract price or fee is reduced; (ii) Contractor’s costs are determined to be unallowable; (iii) any fines, penalties, or interest are assessed on Contractor; or (iv) Contractor incurs any other costs or damages; Contractor may proceed as provided for in (3) below.
(3)Upon the occurrence of any of the circumstances identified in (2) above, Contractor may make a reduction of corresponding amounts (in whole or in part) in the price, or in the costs and fee, of this Contract or any other contract with Subcontractor, or may demand payment (in whole or in part) of the corresponding amounts. Subcontractor promptly pay amounts so demanded.
(4)These rights and obligations shall survive the termination or completion of this Contract.

Contract Documents

The following documents shall be considered the “Contract Documents”

1. General Provisions and FAR Flowdown Provisions for Subcontracts for Construction Services Under a U.S. Government Prime Contract

2. ASRCC Form 142

3. Federal Suppliement dated 4/13/2021

4. RFP

5. PR-FRM-12 Rev 3 Reps and Certs

6. Specifications

7. Drawings

8. Schedule B, E

9. Instructions to Offeror 2

10. Solicitation and Offer

11. Q A Form 004

12. W-9

13. Applicable Wage Determination Scale

Notwithstanding the dimensions on the Plans, Specifications and other Contract Documents it shall be the obligation and responsibility of the Subcontractor to take such measurements as will ensure the proper matching and fitting of the Work covered by this Contract with contiguous work.

The Subcontractor shall prepare and submit to Contractor such shop drawings as may be necessary to describe completely the details and construction of the Work. Approval of such shop drawings by Contractor shall not relieve the Subcontractor of its obligation to perform the Work in strict accordance with the Plans, Specifications, the Additional Provisions hereof and the other Contract Documents, nor of its responsibility for the proper matching and fitting of the Work with contiguous work and the coordination of the Work with other work being performed on the site, which obligation and responsibility shall continue until completion of the Work.

The Subcontractor’s submission of a shop drawing to Contractor shall constitute the Subcontractor’s representation, upon which Contractor may rely, that the Subcontractor has reviewed the submission for accuracy and compliance with all Contract Documents and that wherever engineering is required to be performed, same has been performed by a qualified and licensed engineer. Furthermore, the review of the Shop Drawing by Contractor shall not constitute an undertaking by Contractor to identify deficiencies in the submission, that being an undertaking within the sole responsibility of the Subcontractor.

Should the proper and accurate performance of the Work hereunder depend upon the proper and accurate performance of other work not covered by this Contract, the Subcontractor shall carefully examine such other work, determine whether it is in fit, ready and suitable condition for the proper and accurate performance of the Work hereunder, use all means necessary to discover any defects in such other work, and before proceeding with the Work hereunder, report promptly any such improper conditions and defects to Contractor in writing and allow Contractor a reasonable time to have such improper conditions and defects remedied. Should Subcontractor fail to comply with the requirements of this Article, Subcontractor shall bear all costs incurred by Contractor, Government and other subcontractors, and shall not be entitled to extensions of time and adjustments in Price, that could have been avoided by Subcontractor’s compliance with the requirements of this Article.

The Work hereunder is to be performed and furnished under the direction and to the satisfaction of both the Architect and Contractor. The decision of the Architect as to the true construction, meaning and intent of the Plans and Specifications shall be final and binding upon the parties hereto. Contractor will furnish to the Subcontractor such additional information and Plans as may be prepared by the Architect to further describe the Work to be performed and furnished by the Subcontractor and the Subcontractor shall conform to and abide by the same.

The Subcontractor shall not make any changes, additions and/or omissions in the Work except upon written order of Contractor as provided in Article 8 hereof.

2. Price

The sum to be paid by Contractor, out of funds received from the Government, to the Subcontractor for the satisfactory performance and completion of the Work and of all of the duties, obligations and responsibilities of the Subcontractor under this Contract and the other Contract Documents shall be ___ (hereinafter called the Price) subject to additions and deductions as herein provided.

The Price includes all Federal, State, County, Municipal and other taxes imposed by law and based upon labor, services, materials, equipment or other items acquired, performed, furnished or used for and in connection with the Work, including but not limited to sales, use and personal property taxes payable by or levied or assessed against the Contractor or the Subcontractor. Where the law requires any such taxes to be stated and charged separately, the total price of all items included in the Work plus the amount of such taxes shall not exceed the Price.

3. Payment

On or before the last day of each month the Subcontractor shall submit to Contractor, in the form required by Contractor, a written requisition for payment invoice/AF3065 showing the proportionate value of the Work installed to that date, from which shall be deducted: a reserve of 10%; all previous payments; all amounts and claims against Subcontractor, by Contractor or any third party, for which Subcontractor is responsible hereunder; and all charges for services, materials, equipment and other items furnished by Contractor to or chargeable to the Subcontractor; and the balance of the amount of such requisition, as approved by Contractor and the Architect and for which payment has been received by Contractor from the Government, shall be due and paid to the Subcontractor on or about the fifteenth (15th) day of the succeeding month or in accordance with the Contract Documents. Contractor shall have the right, at its sole discretion, to issue payments to Subcontractor by way of joint checks to Subcontractor and suppliers and/or vendors of Subcontractor, and Subcontractor agrees to cooperate fully in facilitating the making of such joint payments.

The obligation of Contractor to make a payment under this Contract, whether a progress or final payment, or for extras or change orders or delays to the Work, is subject to the express condition precedent of payment therefor by the Government. If Contractor has provided payment or performance bonds or a combination payment and performance bond, the obligation of Contractor and its Surety under any of those bonds to make any payment (whether a progress payment or final payment) to a claimant on that bond is similarly subject to the express condition precedent of payment therefor by the Government.

The Subcontractor shall submit with its first requisition for payment a detailed schedule showing the breakdown of the Price into its various parts for use only as a basis of checking the Subcontractor’s monthly requisitions.

Contractor reserves the right to advance the date of any payment (including the final payment) under this Contract if, in its sole judgment, it becomes desirable to do so.

The Subcontractor agrees that, if and when requested to do so by Contractor, it shall furnish such information, evidence and substantiation as Contractor may require with respect to the nature and extent of all obligations incurred by the Subcontractor for or in connection with the Work, all payments made by the Subcontractor thereon, and the amounts remaining unpaid, to whom and the reasons therefor.

Final payment to the Subcontractor shall be made only with funds received by Contractor from the Government, the Construction Lender or the Government’s Agent as final payment for Work under the General Contract. Final payment to Contractor by the Government shall be an express condition precedent that must occur before Contractor shall be obligated to make final payment to the Subcontractor. In addition, final payment by Contractor to the Subcontractor shall not become due and payable until the following other express conditions precedent have been met: (1) the completion and acceptance of the Work by Contractor and the Architect; (2) provision by the Subcontractor of evidence satisfactory to Contractor that there are no claims, obligations or liens outstanding or unsatisfied for labor, services, materials, equipment, taxes or other items performed, furnished, or incurred for or in connection with the Work; (3) execution and delivery by the Subcontractor, in a form satisfactory to Contractor of a general release running to and in favor of Contractor and the Government; and (4) complete and full satisfaction of all claims, demands and disputes, and all obligations and responsibilities of Subcontractor, arising out of or related to the Subcontract, including those as between Contractor and Subcontractor as well as those between Subcontractor and any third party. Should there be any such claim, obligation or lien or unsatisfied obligation or responsibility whether before or after final payment is made, the Subcontractor shall pay, refund or deliver to Contractor (1) all monies that Contractor and/or the Government shall pay in satisfying, discharging or defending against any such claim, obligation or lien or any action brought or judgment recovered thereon and all costs and expenses, including legal fees and disbursements, incurred in connection therewith; and (2) such amounts as Contractor or Government shall, in their sole discretion, determine to be an amount sufficient to protect Contractor and Government therefrom (in lieu of payment of such amounts, Subcontractor may, at Government’s and Contractor's sole discretion, deliver a bond satisfactory to Contractor and Government). Such refund and payment shall be made within ten (10) days of request by Contractor to Subcontractor for same. The final payment shall be due within forty (40) days after all of these express conditions precedent have been met.

No payment (final or otherwise) made under or in connection with this Contract shall be conclusive evidence of the performance of the Work or of this Contract, in whole or in part, and no such payment shall be construed to be an acceptance of defective, faulty or improper work or materials nor shall it release the Subcontractor from any of its obligations under this Contract; nor shall entrance and use by the Government constitute acceptance of the Work or any part thereof. The failure of Subcontractor to fully perform and satisfy any or all obligations set forth in this Contract shall constitute a default, entitling Contractor to take action as described in this Contract.

4. Assignment and Subcontracting

Any assignment of Subcontractor’s contract rights or delegation of duties shall be void, unless prior written consent is given by Contractor. However, Subcontractor may assign rights to be paid amounts due, or to become due, to a financing institution if Contractor is promptly furnished a signed copy of such assignment reasonably in advance of the due date for payment of any such amounts. Amounts assigned to an assignee shall be subject to setoffs or recoupment for any present or future claims of Contractor against Subcontractor. Contractor shall have the right to make settlements and adjustments in price with Subcontractor without notice to the assignee.

Without Contractor’s written consent, Subcontractor will not subcontract for the design, development, or procurement of any portion of goods or services under this Contract. This limitation does not apply to Subcontractor’s purchases of standard commercial supplies or raw materials. The Subcontractor shall flow down to the supply chain the applicable requirements when the Subcontractor provides written consent to subcontract. FAR 52.215-22 and 52.215-23 apply under this Contrtact.

5. Changes

Contractor reserves the right, from time to time, whether the Work or any part thereof shall or shall not have been completed, to make changes, additions and/or omissions in the Work as it may deem necessary, upon written order to the Subcontractor. The value of the work to be changed, added or omitted shall be stated in said written order and shall be added to or deducted from the Price.

The value of the work to be changed, added or omitted shall be determined by the lump sum or unit prices, if any, stipulated herein for such work. If no such prices are stipulated, such value shall be determined by whichever of the following methods or combination thereof Contractor may elect:

(a) By adding or deducting a lump sum or an amount determined by a unit price agreed upon between the parties hereto.

(b) By adding (1) the actual net cost to the Subcontractor of labor in accordance with the established rates, including required union benefits, premiums the Subcontractor is required to pay for workmen’s compensation and liability insurance, and payroll taxes on such labor, (2) the actual cost to the Subcontractor of materials and equipment and such other direct costs as may be approved by Contractor less all savings, discounts, rebates and credits, (3) an allowance of _10%__ for overhead on items (1) and (2) above, and (4) an allowance of _10%__ for profit on items (1), (2) and (3) above.

Should the parties hereto be unable to agree as to the value of the work to be changed, added or omitted, the Subcontractor shall proceed with the work promptly under the written order of Contractor from which order the stated value of the work shall be omitted, and the determination of the value of the work, if not resolved in the normal course, shall be addressed pursuant to the dispute resolution procedures in accordance with disputes procedures set forth in this Contract.

In the case of omitted work, Contractor shall have the right to withhold from payments due or to become due to the Subcontractor an amount which, in Contractor’s opinion, is equal to the value of such work until such time as the value thereof is determined by Contract.

All changes, additions or omissions in the Work ordered in writing by Contractor shall be deemed to be a part of the Work hereunder and shall be performed and furnished in strict accordance with all of the terms and provisions of this Contract and the other Contract Documents. Subcontractor accepts the responsibility to keep its surety informed of all such modifications to its contract. The obligations of Subcontractor and Subcontractor’s surety shall not be reduced, waived or adversely affected by the issuance of such change orders, additions or deductions even if Subcontractor fails to inform its surety of same and Contractor shall not be required to obtain consent of the Subcontractor’s surety to such modifications.

Subcontractor shall provide Contractor with written notice of any circumstance or direction given by Contractor which Subcontractor may regard as a change, addition and/or omission or which may otherwise serve as the basis for a request for an increase in Price or extension of time within five (5) days of the receipt of the direction or the occurrence of the event giving rise to such a request. Such written notice shall provide a full explanation of the circumstances or direction and the extent of the increase and extension sought, including a detailed breakdown and analysis supporting such request. Failure of the Subcontractor to provide such written notice shall constitute a waiver of Subcontractor’s right to any such increase or extension.

Subcontractor acknowledges that the General Contract may include provisions whereby Contractor is required to provide notice, information, reports and analyses in the event that Contractor intends to pursues or which may affect Contractor’s right’s to an extension of time or increase in Contractor’s price to the Government, whether by way of change order or otherwise, and that the failure to provide such notice, information, reports and analyses may result in a waiver or forfeiture of the right to such an extension or increase. Accordingly, Subcontractor agrees that Subcontractor shall provide all such notices, information, reports and analyses to Contractor, in the same form, content and manner as Contractor is required to provide to the Government under the General Contract in the event that Subcontractor intends to pursue an extension of time or increase in Price. Subcontractor shall provide all such notices, information, reports and analyses to Contractor not later than three (3) business days prior to the time by which Contractor must submit corresponding notice, information, reports and analyses to the Government so that Contractor can pursue like extensions and/or increases in Contractor’s price from the Government. Subcontractor acknowledges that its failure to comply with the terms of this paragraph may result in the loss of or prejudice to Contractor’s ability to receive adjustments and extensions time from the Government. Subcontractor therefore agrees that it shall be deemed to have waived and forfeited all such rights in the event that it fails to provide notice, information, reports and analyses to Contractor as required by this Article. The terms and provisions of this paragraph are neither intended to relieve Subcontractor of the obligation to provide timely notices, information, reports and analyses, nor to extend shorter durations, required by the Contract.

Notwithstanding the forgoing, Subcontractor agrees that it shall not be entitled to nor claim any cost reimbursement, compensation, damages or extensions of time attributable to any Government changes, additions and/or omissions directed by Contractor except to the limited extent that Contractor has actually recovered corresponding cost reimbursement, compensation, damages or extensions of time from the Government under the Contract Documents for such changes, additions and/or omissions and then only to the extent of the amount, if any, which Contractor on behalf of the Subcontractor, actually received from the Government on account of such delay, obstruction, hindrance or interference. The preceding sentence shall not apply in a situation in which Contractor directed the performance of changes, additions and/or omissions by Subcontractor notwithstanding express language in the General Contract clearly indicating that Contractor is not entitled to recover a corresponding cost reimbursement, compensation, damages or extensions of time from the Government. Subcontractor agrees to proceed with any and all changed work, even in the event of a dispute regarding the changed work.

Inspection and Defective Work

The Subcontractor shall at all times provide sufficient, safe and proper facilities for the inspection of the Work by Contractor, the Architect, and their authorized representatives in the field, at shops or at any other place where materials or equipment for the Work are in the course of preparation, manufacture, treatment or storage. The Subcontractor shall, within twenty-four (24) hours after receiving written notice from Contractor to that effect, proceed to take down all portions of the Work and remove from the premises all materials whether worked or unworked, which the Architect, Contractor, the Government or any of its design consultants shall condemn as unsound, defective or improper or as in any way failing to conform to this Contract or the Plans, Specifications or other Contract Documents, and the Subcontractor, at its own cost and expense, shall replace the same with proper and satisfactory work and materials and make good all work damaged or destroyed by or as a result of such unsound, defective, improper or nonconforming work or materials or by the taking down, removal or replacement thereof.

Default

Should the Subcontractor at any time, whether before or after final payment or completion of the Work, refuse or neglect to supply a sufficiency of skilled workers or materials of the proper quality and quantity, or fail in any respect to prosecute the Work with promptness and diligence, or cause by any act or omission the stoppage, impede, obstruct, hinder or delay of or interference with or damage to the work of Contractor or of any other contractors or subcontractors on the Project, or fail in the performance of any of the terms and provisions of this Contract or of the other Contract Documents, or should the Architect, Contractor, Government or any of its design consultants, determine that the Work or any portion thereof is not being performed in accordance with the Contract Documents, or should there be filed by or against the Subcontractor a petition in bankruptcy or for an arrangement or reorganization, or should the Subcontractor become insolvent or be adjudicated a bankrupt or go into liquidation or dissolution, either voluntarily or involuntarily or under a court order, or make a general assignment for the benefit of creditors, or otherwise acknowledge insolvency, then in any of such events, each of which shall constitute a default hereunder on the Subcontractor’s part, Contractor shall have the right, in addition to any other rights and remedies provided by this Contract and the other Contract Documents or by law, at one time or in phases at Contractor’s discretion, after three (3) days written notice to the Subcontractor mailed or delivered to the last known address of the latter, (a) to perform and furnish through itself or through others any such labor or materials for all or any portion of the Work and to deduct the cost thereof from any monies due or to become due to the Subcontractor under this Contract, (b) to terminate the employment of the Subcontractor for all or any portion of the Work, and/or (c) enter upon the premises and take possession, for the purpose of completing all or any portion of the Work, of all materials, equipment, scaffolds, tools, appliances and other items thereon as Contractor may select, all of which the Subcontractor hereby authorizes Contractor to employ and/or communicate with any person or persons in connection with the completion of the Work and/or to provide all the labor, services, materials, equipment and other items required therefor. In case of Contractor taking action under this Article, including termination of the employment of the Subcontractor, the Subcontractor shall not be entitled to receive any further payment under this Contract until the Work shall be wholly completed to the satisfaction of Contractor, Government and shall have been accepted by them, at which time, if the unpaid balance of the amount to be paid under this Contract shall exceed the cost and expense incurred by Contractor in completing the Work, such excess shall be paid by Contractor to the Subcontractor; but if such cost and expense shall exceed such unpaid balance, then the Subcontractor and its surety, if any, shall pay the difference to Contractor. Such cost and expense shall include, not only the cost of completing the Work to the satisfaction of Contractor and the Architect and of performing and furnishing all labor, services, materials, equipment, and other items required therefore, but also all losses, damages, costs and expenses (including legal fees and disbursements incurred in connection with reprocurement, in defending claims arising from such default and in seeking recovery of all such cost and expense from the Subcontractor and/or its surety), and disbursements sustained, incurred or suffered by reason of or resulting from the Subcontractor’s default. Should Contractor take action by effectuating the provisions of this paragraph, and should it subsequently be determined that such action, including a termination effectuated by the terms of this Article, was improper, such termination shall be treated as a termination for convenience pursuant to Article __. Subcontractor hereby transfers and assigns to Contractor all rights under agreements that Subcontractor may have with subcontractors to Subcontractor, suppliers and vendors in connection with the Work or the Project, which transfers and assignments may be accepted at Contractor’s sole discretion in the event that Contractor has taken action under this Article. Subcontractor agrees to fully cooperate with Contractor in pursuing Contractor’s rights hereunder and that Contractor shall not be required to defer or delay action taken pursuant to this Article during the pendency of any review, investigation, evaluation or assessment by Subcontractor or its surety.

It is recognized that, if the Subcontractor institutes or has instituted against it a case under Title 11 of the United States Code (Bankruptcy Code), such event could impair or frustrate the Subcontractor’s performance of this Contract. Accordingly, it is agreed that upon the occurrence of any such event, Contractor shall be entitled to request of Subcontractor or its trustee or other successor adequate assurances of future performance. Failure to comply with such request within ten (10) calendar days of delivery of the request shall entitle Contractor, in addition to any other rights and remedies provided by this Contract or by law, to terminate this Contract. Pending receipt of adequate assurances of performance and actual performance in accordance herewith, Contractor shall be entitled to perform and furnish through itself or through others any such labor, materials or equipment for the Work as may be necessary to maintain the progress of the Work and to deduct the cost thereof from any monies due or to become due to the Subcontractor under this Contract. In the event of such bankruptcy proceedings, this Contract shall terminate if the Subcontractor rejects this Contract or if there has been a default and the Subcontractor is unable to give adequate assurance that it will perform as provided in this Contract or otherwise is unable to comply with the requirements for assuming this Contract under the applicable provisions of the Bankruptcy Code.

Subcontractor, in addition to any other rights available to Contractor hereunder, agrees to indemnify, hold harmless and defend Contractor from and against any and all claims, demands, suits, damages, judgments, liabilities, costs and expenses (including legal fees and disbursements) arising out of or related to Subcontractor’s breach of any term of the Contract.

In the event that Contractor is found to have wrongfully terminated the Contract for default, Subcontractor’s sole and exclusive remedy shall be that set forth in Article _ pertaining to convenience terminations.

Delays by Subcontractor

Should the progress of the Work or of the Project be delayed, disrupted, hindered, obstructed, or interfered with by any fault or neglect or act or failure to act of the Subcontractor or any of its officers, agents, servants, employees, subcontractors or suppliers so as to cause any additional cost, expense, liability or damage to Contractor including legal fees and disbursements incurred by Contractor (whether incurred in defending claims arising from such delay or in seeking reimbursement and indemnity from the Subcontractor and its surety hereunder or otherwise) or to the Government or any damages or additional costs or expenses for which Contractor or the Government may or shall become liable, the Subcontractor and its surety shall and does hereby agree to compensate Contractor and the Government for and indemnify them against all such costs, expenses, damages and liability.

If the progress of the Work or of the Project be delayed by any fault or neglect or act or failure to act of the Subcontractor or any of its officers, agents, servants, employees, subcontractors or suppliers, then the Subcontractor shall, in addition to all of the other obligations imposed by this Contract upon the Subcontractor in such case, and at its own cost and expense, work such overtime as may be necessary to make up for all time lost in the completion of the Work and of the Project due to such delay. Should the Subcontractor fail to make up for the time lost by reason of such delay, Contractor shall have the right to cause other Subcontractors to work overtime and to take whatever other action it deems necessary to avoid delay in the completion of the Work and of the Project, and the cost and expense of such overtime and/or such other action shall be borne by the Subcontractor.

Contractor, if it deems necessary, may direct the Subcontractor to work overtime and, if so directed, the Subcontractor shall work said overtime and, provided that the Subcontractor is not in default under any of the terms or provisions of this Contractor of any of the other Contract Documents and the direction to work overtime was not due in whole or in part to any fault or failure of Subcontractor, Contractor will pay the Subcontractor only for such actual additional wages paid, if any, at rates which have been approved by Contractor plus taxes imposed by law on such additional wages, plus workers’ compensation insurance, liability insurance and levies on such additional wages if required to be paid by the Subcontractor to comply with Subcontractor’s obligations under this Contract. Subcontractor acknowledges that in the event that it may intend to pursue a claim of inefficiency, loss of productivity or other similar or related request for additional compensation, Subcontractor may rely only on evidence indicating the actual inefficiency, loss of productivity or other similar consequence as it occurred on the Project and agrees that no reports, analyses, data, industry or academic studies or any other evidence that do not exclusively rely on and pertain to the Work performed at the Project shall be used or in any way considered, in whole or in part, in connection with the resolution of such a claim, whether by Contractor or any forum for dispute resolution.

Extension of Time and Delays

Should the Subcontractor be delayed, obstructed, hindered or interfered with in the commencement, prosecution or completion of the Work by any cause including but not limited to any act, omission, neglect, negligence or default of Contractor or of anyone employed by Contractor or by any other contractor or subcontractor on the Project, or by the Architect, the Government or their contractors, subcontractors, agents or consultants, or by damage caused by fire or other casualty or by the combined action of workers or by governmental directive or order in no way chargeable to the Subcontractor, or by any extraordinary conditions arising out of war or government regulations, or by any other cause beyond the control of and not due to any fault, neglect, act or omission of the Subcontractor, its officers, agents, employees, subcontractors or suppliers, then except where the General Contract has specific requirements at variance with the foregoing, in which case the requirements of the General Contract shall govern, the Subcontractor shall be entitled to an extension of time for a period equivalent to the time lost by reason of any and all of the aforesaid causes; provided, however, that the Subcontractor shall not be entitled to any such extension of time unless the Subcontractor (1) notifies Contractor in writing of the cause or causes of such delay, obstruction, hindrance or interference within forty eight (48) hours of the commencement thereof and (2) demonstrates that it could not have anticipated or avoided such delay, obstruction, hindrance or interference and has used all available means to minimize the consequences thereof. Subcontractor acknowledges that provision of such notice is an essential condition precedent to Subcontractor's rights in connection with any such delays, obstructive hindrances or interferences to Contractor's ability to fully identify, and expeditiously, address and avoid such cause or causes, and, accordingly, Subcontractor expressly waives all rights with respect to any such cause or causes for which notice hereunder was not provided. Notwithstanding the foregoing, if the General Contract is at variance with granting such time extension, then the provisions of the General Contract shall control.

The Subcontractor agrees that it shall not be entitled to nor claim any cost reimbursement, compensation or damages for any delay, obstruction, hindrance or interference to the Work except to the limited extent that Contractor has actually recovered corresponding cost reimbursement, compensation or damages from the Government under the Contract Documents for such delay, obstruction, hindrance or interference, and then only to the extent of the amount, if any, which Contractor on behalf of the Subcontractor, actually received from the Government on account of such delay, obstruction, hindrance or interference. Notwithstanding any term or provision herein to the contrary, Subcontractor expressly waives and releases all claims or rights to recover lost profit (except for profit on work actually performed), recovery of overhead (including home office overhead), and any other indirect damages, costs or expenses in any way arising out of or related to the Contract, including the breach thereof by Contractor, delays, charges, acceleration, loss of efficiency or productivity disruptions and interferences with the performance of the work.

It shall be an express condition precedent to any obligation on the part of Contractor to make payment of any such cost, reimbursement, compensation or damages to the Subcontractor hereunder that Contractor shall first be determined to be entitled to such compensation on behalf of the Subcontractor and then receive such payment from Government, and Subcontractor expressly acknowledges that Contractor is not obligated or required to pursue Subcontractor claims as against Government if Contractor, in its sole discretion, after review of Subcontractor's claim, has deemed the claim to lack merit in whole or in part.

The Subcontractor agrees that it shall contribute a fair and proportionate share of the costs of advancing the claims of the Subcontractor for delay, including but not limited to legal and other professional fees.

6. Loss or Damage to Work Contractor shall not be responsible for any loss or damage to the Work to be performed and furnished under this Contract, however caused, until after final acceptance thereof by Contractor and the Architect, nor shall Contractor be responsible for loss of or damage to materials, tools, equipment, appliances or other personal property owned, rented or used by the Subcontractor or anyone employed by it in the performance of the Work, however caused.

7. Indemnification

Throughout this Contract, the “Indemnified Party(ies)” means Contractor, the Government, any party required to be indemnified pursuant to the General Contract, and any of their respective officers, agents, servants, or employees, and affiliates, parents and subsidiaries. The Subcontractor hereby assumes the entire responsibility and liability for any and all actual or potential damage or injury of any kind or nature whatever (including death, business interruption or loss of use resulting therefrom) to all persons and entities, whether employees of any tier of the Subcontractor or otherwise, or to all property; or as a result of a perceived risk of such damage or injury (including actions taken to avoid or contain such actual or potential damage or injury, whether required or incurred by a public authority or otherwise); caused by, resulting from, arising out of or occurring in connection with the execution of the Work, or in preparation for the Work, or any extension, modification, or amendment to the Work by change order or otherwise. The Subcontractor agrees to indemnify and save harmless the Indemnified Party from and against any and all such claims and further from and against any and all loss, cost, expense, liability, damage, penalties, fines or injury, including legal fees and disbursements, that the Indemnified Party may directly or indirectly sustain, suffer or incur as a result thereof, with the exception of damage to property or bodily injury resulting from the sole negligence of an Indemnified Party. The Subcontractor, its agent, and its employees are not obligated to indemnify the Indemnified Party for damage to property or bodily injury caused by or resulting from the sole negligence of the Indemnified Party.

The Subcontractor agrees to and does hereby assume, on behalf of the Indemnified Party when the Subcontractor has the obligation to indemnify the Indemnified Party, the defense of any action at law or in equity which may be brought against the Indemnified Party upon or by reason of such claims and to pay on behalf of the Indemnified Party, upon demand, the amount of any judgment that may be entered against the Indemnified Party in any such action. In the event that any such claims, loss, cost, expense, liability, damage, penalties, fines or injury arise or are made, asserted or threatened against the Indemnified Party, Contractor shall have the right to withhold from any payments due or to become due to the Subcontractor an amount sufficient in its judgment to protect and indemnify the Indemnified Party from and against any and all such claims, loss, cost, expense, liability, damage, penalties, fines or injury, including legal fees and disbursements, or Contractor in its discretion may require the Subcontractor to furnish a surety bond satisfactory to Contractor guaranteeing such protection, which bond shall be furnished by the Subcontractor within five (5) days after written demand has been made therefor.

In furtherance to but not in limitation of the indemnity provisions in this Contract, Subcontractor hereby expressly and specifically agrees that its obligation to indemnify, defend and save harmless as provided in this Contract shall not in any way be affected or diminished by any statutory or constitutional immunity it enjoys from suits by its own employees or from limitations of liability or recovery under worker’s compensation laws.

In the event that the law of the state in which the Project is located (or other applicalble law) limits the indemnity obligations of the Subcontractor, then the indemnity obligations of the Subcontractor shall be enforced to the fullest extent permitted by applicable law, and this Article shall be construed to conform to such law.

8. Insurance

(a) Required Insurance

Before commencing the Work, the following insurance coverages from insurance companies satisfactory to Contractor shall be in place and maintained until completion and final acceptance of the Work:

(1) WORKERS’ COMPENSATION in accordance with laws of the State in which the Work is situated, and EMPLOYERS' LIABILITY INSURANCE in the amount of $1,000,000.

(2) COMMERCIAL GENERAL LIABILITY INSURANCE INCLUDING COMPLETED OPERATIONS, CONTRACTUAL LIABILITY INSURANCE AGAINST THE LIABILITY ASSUMED HEREINABOVE, and including INDEPENDENT CONTRACTOR’S LIABILITY INSURANCE if the Subcontractor sublets to another all or any portion of the Work, Personal Injury Liability, Broad Form Property Damage (including completed operations), and Explosion, Collapse and Underground Hazards, with the following minimum limits: (Coverage shall be equivalent to current ISO Occurrence Form). No exclusions or restrictions for Crane usage will be permitted.

$ 1,000.000_ /Occurrence

$ 1,000,000_General Aggregate

Subcontractor has elected to obtain the above insurance coverages set forth in paragraphs 1 and 2 above in the manner set forth in the Subcontractor Election A, B or C (with Subcontractor Election B having a further coverage option that is stated in, and may be elected by checking, Sub-Part B-1 ) that is checked below (Note: only one of Subcontractor Election A, B or C is to be selected; however. Subpart B-1 may also be selected but only if Subcontractor Election B is selected):

___ Subcontractor Election A). The above insurance coverages shall be provided by insurance companies selected by the Subcontractor. Contractor shall have the right, without limitation, to reject any insurance company selected by Subcontractor that has an A.M. Best rating of less than A or Standard and Poor’s rating of less than AA or a Moody’s rating of less than Aa. This insurance coverage shall include Products and Completed Operations coverage which Subcontractor agrees to maintain for a period equal to the statute of repose in the state in which the project is located. Subcontractor further agrees that it shall require each of its sub-subcontractors to provide the above insurance coverages subject to the terms and conditions set forth below. All costs are included in the Price and are to be paid by the Subcontractor.

or

___ Subcontractor Election B). The above insurance coverages shall be provided through a consolidated insurance program that insures Subcontractor and its eligible lower tier subcontractors, which program has been made available to Subcontractor by Contractor, as described and with limits of liability, terms and conditions set forth in the Contract Documents, including, but not limited to, the Contractor Controlled Insurance Program (CCIP) Manual, and Subcontractor agrees to all terms and conditions therein, and makes all representations and warranties, associated therewith. Subcontractor acknowledges and agrees i) that insurance costs will be incurred to provide the above insurance coverages under the consolidated program; ii) that as opposed to Subcontractor including such insurance costs in the Price and paying such costs directly, the Price does not include insurance costs for the above insurance coverages, iii) that it is more convenient and efficient for Contractor to pay such insurance costs on Subcontractor’s and Subcontractor’s eligible lower tier subcontractor’s behalf, and iv) that Contractor is authorized by Subcontractor to pay such insurance premiums on Subcontractor’s behalf and Subcontractor’s eligible lower tier subcontractor’s behalf.

___ Sub-Part B-1 to Subcontractor Election B. By checking this further election, Subcontractor agrees that it has selected Subcontractor Election B with respect to providing the above insurance coverages for eligible lower tier subcontractors engaged by or through Subcontractor to the extent permitted by the Contract Documents (including the CCIP Manual); however, Subcontractor agrees that as to Subcontractor itself, the above insurances will be provided by Subcontractor in accordance with the terms and conditions of Subcontractor Election A above. Accordingly, Subcontractor itself shall be deemed an “Excluded Party” with respect to the consolidated insurance program as described in the Contract Documents (including the CCIP Manual). Any other “Excluded Party” lower tier subcontractors (if applicable) with respect to the consolidated insurance program arranged by Contractor shall be required to procure their own insurance coverages at their expense. For Subcontractor’s lower tier subcontractors that are not an “Excluded Party”, the above insurance coverages shall be provided through the consolidated insurance program as described in Subcontractor Election B to the extent permitted by the Contract Documents (including the CCIP Manual).

Subcontractor represents and warrants that all amounts, information and data that Subcontractor and its lower tier subcontractors has provided or will provide in connection with CCIP applications and other related forms and documents, including estimated payroll and insurance costs, are, or shall be when submitted, true and accurate. Subcontractor represents and warrants that the amount of estimated unburdened payroll (payroll without benefits or overtime, unless the overtime portion is included as required by the regulations of the State in which the project is located) actually used by Subcontractor and its eligible lower tier subcontractors in calculating the Price is $ ___ (“Initial Payroll Estimate” or “Estimated On-Site Payroll”) (if Sub-Part B-1 is elected, this amount only pertains to Subcontractor’s eligible lower tier subcontractors). Subcontractor further agrees that all such amounts, data and information, including the estimated unburdened payroll amount used to calculate the Price, shall be to subject to audit and verification if Contractor or the CCIP Administrator elects to do so and Subcontractor agrees to cooperate fully and provide documents and other records requested in connection with such audit and verification and to cause its lower tier subcontractors to do the same. Subcontractor acknowledges that such amounts, information and data or such other amounts as verified in accordance with the CCIP Manual or through audit may be used to calculate final and interim cost adjustments to the Price and/or payments to Subcontractor (at Contractor’s discretion) as described in the CCIP Manual. Contractor and the CCIP Administrator shall not be required to use any amount greater than the foregoing “Estimated On-Site Payroll” as the unburdened payroll amount when calculating such adjustments for Subcontractor and its lower tier subcontractors as described in the CCIP Manual.

or

___ Subcontractor Election C). The above insurance coverages shall be provided through an Government Controlled Insurance Program (OCIP) as described and with limits of liability set forth in the Contract Documents and Subcontractor agrees to all terms, and makes all representations and warranties, associated therewith.

Subcontractor acknowledges that if any of the above insurance coverages are provided through a consolidated program arranged pursuant to Subcontractor Election B, Subcontractor Election B-1 or Subcontractor Election C, such coverage will not apply to any operations off of the premises (as defined in the CCIP Policy or Manual or OCIP Policy or Manual) and Subcontractor shall provide and maintain the above insurance coverages with respect to off-premises operations.