Replace Perimeter Boundary Wall, Busan Storage Facility Federal contract opportunity
Solicitation number
W90VN921R0095
Issued by
Department of the Army Materiel Command Army Contracting Command

View the file

Other files for this federal contract opportunity

Other files attached to Replace Perimeter Boundary Wall, Busan Storage Facility, newest first.
File Type Posted
Attachment1-Drawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WT4KB41242N020

THIS IS A "NON-WORK PLAN" TASK ORDER RFP FOR THE FOLLOWING MATOC CONTRACTOS ONLY.

ONLY Proposals for this requirements are being solicited from the MATOC contractors for the follow ing MATOC contracts issued by 411th Contracting Support Brigade (CSB).

Proposals from offerors other than these MATOC Contractors w ill not be considered for aw ard, Contract Number; W91QVN-18-D-0100, 0102, 0104, 0105, 0106, 0110, 0111, 0112, 0134, 0135, 0137, 0138, 0139, 0141, 0142, 0143, 0145 and 0146.

A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encourage to attend site visit. See site visit clause FAR 52.236-27 in Section L. Offerors are required to have a valid Korean Identif ication card w hen attending the site visit orientation.

B.SUBMISSION OF PROPOSAL: See section L for details. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit the "No-offer letter" by date and time specif ied in this solicitation.

C.BASIS OF AWARD: See Section M of this solicitation.

MS. YI, CHI HYON 315-763-5687

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

07-Sep-2021

(RFP)

(IFB)

X

CALL:

Replace Perimeter Boundary Wall at Busan Stoage Facility

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________06 Oct 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO DAEGU, UNIT #15682

APO AP 96218-5682

UNITED STATES

W90VN9

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

92-10012-1J

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W90VN921R0095 27

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN921R0095

Section B - Supplies or Services and Prices

"FUNDS ARE NOT PRESENTLY AVAILABLE FOR THIS ACQUISITION. NO CONTRACT AWARD

WILL BE MADE UNTIL APPROPRIATED FUNDS ARE MADE AVAILABLE."

FUNDED BY ROK MND IAW MOA BETWEEN USFK AND ROK MND

LCS STATEMENT

THIS IS A ROK MND (THE REPUBLIC OF KOREA, MINISTRY OF NATIONAL DEFENSE) FUNDED

ORDER. NO APPRORIATED FUNDS OF THE UNITED STATES SHALL BE OBLIGATED FOR PAYMENT

DUE UNDER THIS ORDER.

ROK LCS (LOGISTICS COST SHARING)-FUNDED ACQUISITION SHALL NOT REQUIRE OFFSHORE

PURCHASE OF MATERIALS. ONLY KOREAN SOURCES ARE ELIGIBLE FOR AWARD OF LCS-FUNDED

CONTRACT.

THIS SOLICITATION IS BEING CONDUCTED UNDER THE LOGISTICS COST SHARING (LCS)

PROGRAM, AND WILL RESULT IN A CONTRACT BETWEEN THE GOVERNMENT OF THE

REPUBLIC OF KOREA (ROK) AND THE CONTRACTOR. ROK WILL DIRECTLY PAY THE

CONTRACTOR. NO APPROPRIATED FUNDS OF THE UNITED STATES SHALL BE OBLIGATED

FOR PAYMENT DUE UNDER THIS CONTRACT.

411TH AWARD RECOMMENDATION PROCESS: THE 411TH CONTRACTING SUPPORT BRIGADE (CSB)

WILL CONDUCT THE SOLICITATION AND MAKE A RECOMMENDATION OF CONTRACT AWARD IN

ACCORDANCE WITH UNITED STATES LAW.

REPUBLIC OF KOREA MINISTRY OF NATIONAL DEFENSE (ROK MND) CONTRACT AWARD

PROCESS: ROK MND WILL AWARD LCS CONTRACTS IN ACCORDANCE WITH THE

FOLLOWING CRITERIA: "ALL LCS WORK MUST BE ACCOMPLISHED IN THE ROK OR ITS

TERRITORIAL WATERS AND THAT ALL EQUIPMENT AND SUPPLIES THAT ARE TO BE

ACQUIRED WITH ROKG FUNDS SHALL BE MANUFACTURED IN THE ROK, AND THAT ALL LCS

SERVICE WORK SHALL BE CARRIED OUT BY KOREAN CONTRACTOR(S), KOREA RAILROAD

CORPORATION, OR THE ROK MILITARY. EQUIPMENT AND SUPPLIES THAT ARE IMPORTED INTO

KOREA AND ASSEMBLED IN KOREA ARE CONSIDERED OFF-SHORE MATERIALS AND NOT

MANUFACTURED IN THE ROK FOR PURPOSES OF LCS WORK." FOR INFORMATION ABOUT THE

ROK AWARD PROCESS, CONTACT THE REPUBLIC OF KOREA MINISTRY OF NATIONAL DEFENSE

LOGISTICS MANAGEMENT BUREAU. FOR ALL OTHER INFORMATION ABOUT THIS PROCUREMENT,

CONTACT THE 411TH CSB CONTRACTING OFFICER.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Work Class: K (NWP)

FFP

Replace Perimeter Boundary Wall at Busan Storage Facility. The Contractor shall provide all necessary resources for this requirement and perform Project No.92- 10012-1J, in accordance with the Statement of Work (SOW), Specification, Drawings, Terms and Conditions of this contract contained herein.

FOB: Destination

PURCHASE REQUEST NUMBER: WT4KB41242N020

PSC CD: Z1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Estimated Cost for War Hazard

FFP

is Zero(0).

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

PROJECT NO TITLE LOCATION

92-10012-1J Replace Perimeter Boundary Wall BSF

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.

(2) The contractor shall replace perimeter boundary wall, BSF in accordance with the specifications and drawings.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

(3) Performance Period: Shall be 180 calendar days after Notice to Proceed (NTP) is issued at the Post

Award Conference (PAC).

PRINCIPAL FEATURES: This project shall include the following:

General Services:

The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design and Technical Review Branch.

Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.

A. Civil Work

1. Replace existing cement masonry unit /red-brick wall perimeter fences with new decorative masonry wall perimeter fences.

2. Restore existing items such as asphalt concrete/ Portland cement concrete pavements, pavement markings, concrete ditches, concrete retaining walls, sidewalks, curbs, planters, paint, signs, boards and others around perimeter fence.

3. Cut/ trim and remove existing trees & shrubs branches.

4. Sod with top soil and solid sodding.

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.

SPECIAL CONDITIONS

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which is incorporated in-to the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours must be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). Please note that there will be an exception for night shift when working on the fire alarm system.

3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.

4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.

5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.

6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.

7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, and other equipment necessary for proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, and any other items, as required by law.

8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR.

Equipment not completely safe or functional shall be repaired and accepted by the government before work is initiated.

9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings any changes in such work which constitute any change from the original contract drawings per government’s approval. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.

10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed dependent on Government’s direction if such material is not yet determined.

11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.

12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.

13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make request fourteen (14) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, associated level of work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.

14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor additional cost. These additional incurred costs are contractor’s responsibility. The Contractor shall reflect these costs in the preparation of their proposal.

15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear per safety regulations are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and Fire and Emergency Service (POC: Fire Communication office, DSN: 768-4120) prior to entering confined spaces (i.e.

manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.

16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to provide information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.

17. WARRANTY: The contractor shall be responsible for resolution on any defect/ failure on the contract during the one (1) year warranty period. The contractor shall provide services or/and repair and replacement to the satisfaction of the government. The one (1) year warranty starts the day after final inspection approval from the authorized government personnel.

18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.

18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

18.3. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;

Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;

Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;

Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;

20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.

21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch.

12, Para 12-3 J)

22. FUEL TANK AND LINES: If applicable, underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b. (5))

23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB transformer certification to COR for each installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.

24. CONTRACTING MANPOWER REPORTING

Contract Manpower Requirement (CMR): The contractor shall report ALL contractor labor hours (including subcontractor labor hours) requires for performance of services provided under this contract for PM and Repair Security Barrier Systems. The contractor is required to completely fill in all required data fields using the following web address: http://www.sam.gov.

The Contractor shall reference FAR clause 52.204-14: Service Contract Reporting Requirements. And follow reporting instruction in accordance with paragraphs (c) and (d) of the clause annually by October 31 for services performed under this contract during the preceding Government fiscal year (October 1-September 30).

(c) The Contractor shall report the following information:

(1) Contract number and, as applicable, order number.

(2) The total dollar amount invoiced for services performed during the previous Government fiscal year under the contract.

(3) The number of Contractor direct labor hours expended on the services performed during the previous Government fiscal year.

(4) Data reported by subcontractors under paragraph (f) of this clause.

(d) The information required in paragraph (c) of this clause shall be submitted via the internet at www.sam.gov. (See SAM User Guide). If the Contractor fails to submit the report in a timely manner, the contracting officer will exercise appropriate contractual remedies. In addition, the Contracting Officer will make the Contractor’s failure to comply with the reporting requirements a part of the Contractor’s performance information under FAR subpart 42.15.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2021. Contractor may direct questions to the help desk at: http://www.sam.gov.

This requirement is being implemented via DFARS Case 2018-D063. Currently, this case is open for public comment.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days after Notice to Proceed (NTP) is issued.

* The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

AUG 2020

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports

DEC 2018

52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO

SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Items. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.

(a) Definitions. As used in this provision-

Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition.

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."

(d) Representations. The Offeror represents that--

(1) It [] will, [] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and

(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--

It [] does, [] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.

(e) Disclosures.

(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:

(i) For covered equipment--

(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);

(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and

(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.

(ii) For covered services--

(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or

(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.

(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:

(i) For covered equipment--

(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);

(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and

(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.

(ii) For covered services--

(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or

(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.

(End of provision)

52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT

2020)

(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.

(c) Representations.

(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.

(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.

52.232-18 AVAILABILITY OF FUNDS (APR 1984)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least 50 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

5152.229-4012 TAX EXEMPTION CUSTOMS, REPUBLIC OF KOREA

Pursuant to Article IX of the Status of Forces Agreement between the Republic of Korea and the United States of America, the United States and its contractors are exempt from Republic of Korea customs duties and other related charges. By submission of its offer or quote, the Contractor certifies that the price for all material, supplies, and equipment to be imported for the performance of this contract do not include any otherwise applicable customs duties. To obtain an exemption or reimbursement for customs duties paid pursuant to performance of the contract, the contractor must provide the Contracting Officer with the total amount of customs duties that have been excluded from the contract price. The Contracting Officer will return USFK Form 75 to the contractor for filing with the Republic of Korea Customs Office at the time of import declaration or later if the customs duties were paid before award of the contract.

5152.229-4013 TAX EXEMPTION SPECIAL EXCISE TAX, REPUBLIC OF KOREA

This clause is in implementation of Article XVI of the Status of Forces Agreement between the Republic of Korea and the United States, granting Contractors exemption from Republic of Korea Special Excise Taxes. At the time this contract is awarded the Contractor shall indicate to the Contracting Officer which items will be purchased for the contract that are subject to Special Excise Tax. It shall indicate the name of the item, the number of units to be purchased, the cost per unit without tax, the percentage of tax, the tax amount per unit, the total tax, and the manufacturer of the item. The Contracting Officer will verify the reasonableness of the quantities claimed and ensure that the Contractor has certified that the contract price excludes Special Excise Tax on those items subject to the tax. The Contractor shall purchase the special-excise-taxed items from the manufacturer, tax-inclusive. For construction and single-delivery type supply and service contracts, the Contractor shall employ the following procedure: At the time it purchases the items it shall present the manufacturer with a notification letter requesting refund of the Special Excise Tax. (Copies of this letter can be obtained from the 411th CSB, Korea Contracting Officer.) The manufacturer will endorse the letter to the manufacturer's District Tax Office which will make refund to the manufacturer. The manufacturer will make subsequent refund to the Contractor. Requests for refund under requirements-type contracts will be submitted monthly and will be accompanied by copies of the USFK delivery orders issue

5152.229-4014 TAX EXEMPTION VALUE ADDED TAX (VAT), REPUBLIC OF KOREA

This clause implements Article XVI of the Status of Forces Agreement between the Republic of Korea and the United States of America, which exempts contractors from paying the Republic of Korea Value-Added Taxes.

When the contractor submits an offer, it shall certify to the Contracting Officer that all the costs in the offer will be exclusive of any Value-Added Tax; and further, that the proposed contract price includes no Value-Added Tax. The contractor shall also indicate the amount and type of Value-Added Taxes excluded from the contract price. If supplies and/or services which the contractor purchases for this contract include Value-Added Taxes, it can obtain a full refund for the amount of the Value-Added Tax by submitting to the ROK District Tax Office tax invoices which the contractor receives when it purchases materials and/or services for this contract. The contractor must submit a copy of the USFK contract with its first tax invoice submission. Subsequent tax invoice submissions must be accompanied by a letter which references the USFK contract submitted with the first tax invoice submission.

5152.229-4015 TAX EXEMPTION POL PRODUCTS, REPUBLIC OF KOREA

(a) This clause is in implementation of Article XVI of the Status of Forces Agreement between the Republic of Korea and the United States of America, granting Contractors exemption from Republic of Korea taxes for petroleum products (POL) utilized on USFK acquisitions in the Republic of Korea. At the time this contract is awarded, the Contractor shall make a final nomination in writing of its point of purchase for POL products to be used on this contract. If the Contractor intends to purchase directly from an oil company refinery, it may nominate any of the three ROK oil companies below which have agreed to sell to Contractor FOB refinery at a fixed exempt price.

List of Oil Companies and their Respective Tax Offices

(1) Hyundai Oil Refinery Co., Ltd.: Dong-Inchon District Tax ATTN: POL Tax Administrator Inchon City, Korea

(2) SK Corporation: Ulsan District Tax Office ATTN: POL Tax Administrator Ulsan City, Kyongsang Nam Do, Korea

(3) LG Caltex Company: Yosu District Tax Office ATTN: POL Tax Administrator Yosu City, Chonla Nam Do, Korea

(b) If the contractor instead intends to purchase its POL products from an individual gasoline station, the Contracting Officer will advise the contractor as to which individual gasoline stations will sell to it at the fixed exempt price. The contractor shall specify from which of those stations it will purchase. In addition to specifying the oil company/gas station, the Contractor shall state the estimated quantity and the amount of POL to be purchased from each refinery/gas station. The USFK Contracting Officer will verify the reasonableness of the amounts of POL products claimed for use on the contract and, based on this verification, the USFK Responsible Officer will issue USFK POL Tax Exemption Coupons. If the Contractor wishes to purchase from an individual gas station, it will be required to make advance payment for the amount of POL covered by the coupons. Advance payment will be at the fixed-exempt price and will be made to the gas station(s) previously nominated. Representatives from the nominated gas station(s) shall be present at the issuing session. They will collect the advance payments; marks “paid” on the back of the original copy of the coupons issued, and provide the purchasing Contractor with tax invoices to be used by the Contractor to obtain a refund from its governing ROK District Tax Office. All coupons for construction contracts will be issued at the time of award. Coupons for requirements-type contracts will be issued on a delivery order increment basis or on a monthly basis. Pre-selected oil company refineries will sell their POL products at the fixed exempted prices upon presentation of the coupons. Individual gas stations, which have previously collected POL payment in advance will accept the pre-paid USFK POL Tax Exemption Coupons from contractors and will provide the POL amounts reflected on tendered coupons without any further charge.

5152.232-4028 – Funding of ROK MND Contracts

FUNDING OF ROK MND CONTRACTS

(a) This is a contract between the Government of the Republic of Korea (ROK) and the contractor. ROK will directly pay the contractor. No appropriated funds of the United States (US) shall be obligated for payment due under this contract.

(b) Funding advisement: This contract, any modifications (including exercise of option(s)) thereto, and any delivery or task orders thereunder, shall be paid with ROK funds and shall cite “MOA Contract - funded by ROK MND” (in lieu of citing appropriations and accounting data). No U.S. funds, appropriated or other, are or will be obligated under this contract.

(c) Limitation of US liability: The U.S. Government shall incur no liability, and no appropriated or other funds of the United States shall be obligated, for payment for services, supplies, claims, or other costs arising out of or under this contracts, delivery or service orders, exercises of options, or other modifications.

(d) Identification of invoices: Contractor shall state clearly “MOA Contract - funded by ROK MND” on all invoices for performance under contracts, delivery or service orders that are designated as “MOA Contract - funded by ROK

MND.”

(e) Funding carry-over:

(1) The Contractor will make every reasonable effort to obtain completion of all performance under the contract and to obtain, approve, and forward Contractor’s invoices under the contract before the end of the calendar year of the contract. In the event that any work initiated under the contract cannot be completed by the end of the calendar year, the Contractor shall furnish the Contracting Officer and USFK, ATTN: FKJ4-P-G, not later than 30 November, the following information:

(i) A list of work that apparently will not be completed and invoiced by, and apparently will require payments after, the end of the calendar year;

(ii) Estimated price of work that apparently will be carried beyond the calendar year; and

(iii) Date of anticipated completion of the work.

(2) The ROK MND shall seek mutually agreeable procedures for payment for work carried over to the next calendar year.

(f) Availability of ROK Funds for the Next Calendar Year:

(1) This contract is funded with calendar year ROK MND funds, from date of award through 31 December of the year in which the contract is awarded and/or into which the contract is extended. ROK MND funds are not available for performance, under this contract, beyond 31 December of the current contract’s calendar year period. Any obligation and/or legal liability on the part of ROK MND for the next calendar year’s performance, including exercise of any option to extend the services/contract, is contingent upon the Contracting Officer’s explicit notification to the Contractor of availability of that new calendar year’s ROK MND funds, from which contractual payment(s) can be made.

(2) Unavailability of ROK MND funds until a few months into the new calendar year may necessitate a break in performance of the contract until those funds become available. In the event of a break in performance because of unavailability of the new calendar year’s ROK MND funds for obligation under the contract, that break in performance shall not be deemed a breach or default of the contract.

5152.232-4030 – Payments of ROK MND Contracts

PAYMENTS OF ROK MND CONTRACTS

(a) Responsibility for Payment: The ROK Government shall make payment directly to the contractor for performance rendered and accepted under any contract part, or delivery or service order identified as “MOA contract

– funded by ROK MND.” Payments shall be made at the prices specified in the contract.

(b) Performance Certification and Contract Administration: The U.S. Government has sole authority to administer this contract. The U.S. Government, through its designated USFK official(s), has sole authority to inspect and accept goods and services and to determine the Contractor’s entitlement to payment from the ROK under this contract. The administering U.S. Government Contracting Officer will resolve all disputes, claims, and appeals before certifying invoices for payment. Neither ROK MND nor ROK Defense Logistics Agency will pay any invoice or claim under this contract without prior U.S. Government certification of the invoice.

(c) Payment for Partial Deliveries: Unless otherwise specified in this contract, payment shall be made on partial deliveries accepted by the U.S. Government, if (1) the amount due on the deliveries warrants it, or (2) the Contractor requests it and the amount due on the deliveries is at least either the local currency equivalent of $1,000.00 or 50% of the total contract price.

(d) Invoices: An invoice is a written request for payment for supplies rendered. In order to be proper, an invoice must include as applicable the following:

(1) Invoice date;

(2) Name and address of contractor;

(3) Contract number or other authorization for supplies delivered or service performed (including order number and contract line item number);

(4) Description, quantity, unit of measure, unit price and extended price of supplies delivered or services performed;

(5) Shipping and payment terms (e.g. shipment number and date of shipment, prompt payment discount terms). Bill of lading number and weight of shipment will be shown for shipments on Government bills of lading;

(6) Name and address to which payment is to be sent (which must be the same as that in the contract or on a proper notice of assignment);

(7) Name, title, phone number and mailing address of person to be notified in event of a defective invoice; and

(8) Any other information or documentation required by other provisions of the contract (such as evidence of shipment).

(9) Invoices shall be prepared and submitted in five (5) copies (one copy of the invoice shall be marked “Original”) unless otherwise specified.

(e) Procedures for Payment by ROK MND:

(1) The Contractor shall forward to the Contracting Officer’s Representative (COR), for certification of inspection and acceptance, all invoices in five (5) copies.

(2) If the contractor doesn’t receive payment within 35 days of the government’s receipt of the invoices, the contractor should contact the COR.

(f) Payment Addresses:

ROK Ministry of National Defense Defense Logistics Agency (DLA) Seoul, Korea

5152.233-4008 – Disputes Ministry of National Defense Funded Contracts, ROK

As prescribed in 25.003.c, insert the following clause:

DISPUTES, MINISTRY OF NATIONAL DEFENSE FUNDED CONTRACTS, ROK

(This clause applies only to ROK-funded acquisitions or parts of acquisitions.)

(a) All disputes arising under, or relating to, this contract shall be resolved under this clause.

(b) "Claim", as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. A claim arising under a contract, unlike a claim relating to that contract, is a claim than can be resolved under a contract clause that provides for the relief sought by the claimant; however, a written demand or written assertion by the Contractor seeking the payment of money exceeding $100,000 is not a claim under the clause until certified as required by subparagraph (d)(2) below. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under the clause. The submission may be converted to a claim under the clause, by complying with the submission and certification requirements of this clause, if it is disputed either as to liability or amount or is not acted upon in a reasonable time.

(c) The contractor shall have the right to submit to the Contracting Officer, disputes, demands, and/or claims, relating to or arising under this contract, only on the issue of whether the…

This is the start of the file's text. The full file is on GovTribe.