Final PWS.pdf

PDF 171 KB Posted

Attached to
Anzalduas Ballistic Glass Installation Federal contract opportunity
Solicitation number
191BWC20R0004
Issued by
International Boundary and Water Commission U.S.-Mexico

View the file

Other files for this federal contract opportunity

Other files attached to Anzalduas Ballistic Glass Installation, newest first.
File Type Posted
Wage Determination TX20200255 01032020.pdf PDF
Final QASP.pdf PDF
191BWC20R0004.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USIBWC/ANZALDUAS DAM

Ballistic Glass Project

Performance Work Statement

International Boundary and Water Commission United States and Mexico

United States Section

PERFORMANCE WORK STATEMENT (PWS)

FOR BALLISTIC GLASS PROJECT

I. BACKGROUND

The United States Section of the International Boundary and Water Commission (USIBWC) is located on the International boundary between the United States and Mexico. The Security Services Division (SSD) conducted research and analysis of the area and determined that the administration building, and the dam need ballistic glass for personnel protection while working on site. Anzalduas Dam is a diversion dam located in Hidalgo County, Texas, approximately 11 river miles upstream from Hidalgo, Texas between Mission, Texas and Reynosa, Tamaulipas. Construction of this dam began in April 1956 and became Lower Rio Grande Diversion Dam Locations fully operational in April of 1960. The purpose of Anzalduas Dam is to divert the U.S. Share of floodwaters to its interior floodway. It also enables the diversion of waters to Mexico's main irrigation canal.

II. SUMMARY

The purpose of this project is to install ballistic glass windows at the Anzalduas Dam. It is understood by the USIBWC that the recommended solutions that are outlined in the Performance Work Statement (PWS) may require slight adjustments to allow for quality installation of the recommended improvements.

The work to be performed under this Contract consists of installing complete and operational systems consisting of, but not limited to; fabrication, testing, documentation, packaging, delivery, removal of old glass, preparing window openings for new frames, installation of new frames, installation, and commissioning of the systems/measures as outlined in this PWS for the Anzalduas Dam. End result shall be a turn-key operation.

The Contractor shall provide all work plans, designs, investigations, studies, permits, project supervision, equipment, labor, materials, installation/implementation, testing, training, annual maintenance estimates, and travel required to meet the security requirements under the PWS for Anzalduas Dam.

The work supplied under this specification shall be complete in every detail for the purpose required. The Contract shall include the supply of materials and services not specifically mentioned herein, but which may be necessary to complete any portion of the work in compliance with the requirements of this PWS.

II. LOCATION

Anzalduas Dam is a diversion dam located in Hidalgo County, Texas, approximately 11 river miles upstream between Hidalgo, Texas and Reynosa, Tamaulipas.

Anzalduas Dam 6900 Anzalduas Dam Rd Mission, TX 78752

(956) 585-1221

III. APPLICABLE CODES, RULES, AND REGULATIONS

The Contractor shall comply with all applicable laws, standards, codes and regulations while designing, manufacturing, finishing, and installing the security measures at the Anzalduas Water Diversion Dam; including but not limited to the following:

A. Building Codes

1. Building Dwelling Code: 2012 International Building Code

2. Plumbing Code: 2012 International Plumbing Code

3. Mechanical Code: 2012 International Mechanical Code

4. Fire/Life Safety Code: 2012 International Fire Code

5. Electrical Code: 2014 National Electric Code

6. Energy Code: 2012 International Energy Conservation Code

7. Energy Code: IECC 2009 LEED 2009 New Construction Certification

8. Gas Code: 2012 International Fuel & Gas Code

9. Accessibility Code: Texas Government Code, Chapter 469, Texas

Accessibility Standards (TAS)

10. Building Security Code: Physical Security Criteria for Federal Facilities, (Level Rating III), April 2010

11. American with Disabilities Act: 2010 ADA Standards for Accessible

Design

B. Federal Regulations

1. GSA’s “Facilities Standards for Public Buildings Service (P1-2005)” which establishes design standards and criteria for new buildings, major and minor alternations, and work in historic structures for GSA’s Public Building Services.

2. Uniformed Federal Accessibility Standards

3. The National Environmental Policy Act of 1969 (NEPA)

4. The Endangered Species Act

5. The National Historic Preservation Act (NHPA) of 1966

6. The Archeological and Historic Preservation Act

7. Clean Water Act

8. Solid Waste Disposal Act

9. Resources Conservation and Recovery Act (RCRA)

10. Interagency Security Committee (ISC)-Risk Management Process for

Federal Facilities-Appendix B Countermeasures (FOUO)

C. Safety: The Contractor shall comply with all applicable provisions of the “U.S.

Army Corps of Engineers Safety and Health Requirements Manual”, EM385-1-1, 2008 edition, and the Federal Occupations Safety and Health Administration, 29 CFR 1926 – Construction Standards. In cases of conflicts between the two requirements, the most stringent requirement will apply. Contractor shall also be responsible for site utility clearance prior to installation. The Contractor shall contact and coordinate with underground utilities and/or utility location services for site clearance.

III. ADMINISTRATIVE TASKS

The Contractor shall install all recommended improvements from this PWS submitted under Contract number -(TBD). The report includes a conceptual design that will be available after a request for proposal is issued. The end result shall be a turn-key operation. The Contractor shall provide all work plans, designs, equipment, labor, materials, installation, testing, annual maintenance estimates, and training required to meet the security requirements under this PWS.

A. The selected contractor will provide the names, social security number, date of birth and other biographical data to the USIBWC Security Services Division (SSD). The SSD will conduct a limited background check on all contractor personnel working on the project. This includes subcontractors.

B. The contractor personnel who are physically working on this contract will be required to submit a photo (headshot) of each person and additional biographic information to the USIBWC SSD. The USIBWC will issue Commission cards which will allow the contractor personnel to cross the international border in Mexico for the purposes of official business (project work).

C. The Contractor shall appoint a Project Manager (PM) to serve as the single point-of-contact and liaison between the Contractor and the Contracting Officer and Contracting Officer's Representative (COR) for all work under the Contract. The selected Contractor (appropriate personnel) will sign a Non-Disclosure agreement.

Upon receipt of the Notice to Proceed (NTP), the Contractor shall immediately furnish for approval, the name of the designated individual who will act as the PM to the Contracting Officer, in writing. The Project Manager will be responsible for the complete coordination of all work developed under the Contract. The PM shall be the liaison between the work plan drafting phase and installation of the work and must promote a “team” approach for the project and monitor its progress. The PM must stay involved, be knowledgeable about the project, perform periodic regular visits and be proactive in dealing with issues that may arise.

D. The Contractor selected shall have 5 years of experience working with Department of Defense (DoD) Tier III Security project design and installation. DoD experience can be substituted for relevant experience with other similar Federal agencies as the DoD.

The Contractor should be very familiar with Interagency Security Committee (ISC) standards for federal facilities.

E. All work will be accomplished with adequate internal controls and review procedures which will eliminate conflicts, errors, and omissions, and ensure the technical accuracy of all designs, drawings, and specifications.

F. Schedule-The Consultant shall prepare a detailed project schedule that identifies all tasks and milestones for presentation and discussion at each of the kickoff meetings.

The schedule shall be prepared in a graphical format using the critical path method, which depicts the order and inter-dependence of tasks, subtasks, milestones, and deliverables for each of the requirements identified herein. The Consultant shall ensure that all tasks and work sequences in the schedule are logical and show a coordinated plan of the work. The agreed upon Project Schedule shall be used by the USIBWC to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis for payments and performance.

G. Monthly Reports -Consultant shall prepare and submit to the USIBWC a monthly update report by the fifth (5th) of every month on the work performed the previous month. The report shall include major accomplishments for the reported period, significant problems and proposed solutions, and any issues with contractual requirements. The report, along with an updated schedule, shall be submitted by e-mail no later than the fifth day of the following month.

H. Meetings

1. The Consultant shall conduct one (1) project kickoff meeting. The location of the kickoff meeting will be at the Mercedes Field Office, 325 Golf Course Road Mercedes, TX 78570, (956) 565-3150/3159. The USIBWC has video teleconference capabilities at the El Paso Headquarters Office and Mercedes Field Office. The date and time of the meeting shall be scheduled with the USIBWC's Contracting Officer. The Contractor shall prepare an agenda and minutes of the kickoff meeting.

2. The Consultant shall submit the draft minutes of all meetings to the USIBWC and to any primary stakeholders that participated in the meeting within three

(3) business days, after the day of the meeting. The USIBWC will provide comments within three (3) business days, of receipt of the draft minutes. The Consultant shall address the comments and submit the final minutes to the USIBWC and primary stakeholders within three (3) business days, after receipt of all comments.

I. The Contractor shall appoint a project superintendent for the Anzalduas Dam project that shall be onsite at all times during installation activities. The Superintendent is the first point of contact for the USIBWC inspectors on the project. The Superintendent reports directly to the Project Manager. The Onsite Superintendent is responsible for the safety and execution of the project on a daily basis and reports to the Project Manager. The Superintendent shall sign a Non-Disclosure agreement.

J. Coordination with Stakeholders: The Contractor shall be responsible for coordination with all required stakeholders during the design and installation of the project.

Stakeholders include, but are not limited to, utilities, local, state, and federal permitting agencies, etc. Coordination with USIBWC’s Environmental Management Division (EMD) may be required during the design process. EMD will coordinate with the appropriate state’s Historical Commission and other resource agencies for NEPA.

The Contractor will be required to coordinate with EMD should additional information be needed during this review.

K. The Contractor shall coordinate work activities with all other ongoing contracts to minimize any disruptions to work and USIBWC facilities. Work shall be coordinated so access to job sites under all contracts and access to USIBWC facilities is maintained. The Contractor shall keep the COR informed of all ongoing coordination activities. The Contractor shall immediately notify the CO, if there are any deviations from the approved work plan or coordination issues that may affect work requirements, period of performance, and/or cost. Adjustments to the conceptual design provided from the PSA reports may occur and should be presented to the CO if they arise before performing any tasks associated with the adjustment.

L. The Contractor shall include provisions for accessibility in the installation of the project: New systems and alterations to existing facilities are to be installed to meet the requirements of the Americans with Disabilities Act Architectural Guidelines (ADAAG), and the Uniform Accessibility Standards (UFAS), with the most stringent standards applied in the event of conflicts.

M. The Contractor shall address all questions regarding the Contract from the Project

Manager to the Contracting Officer in writing.

N. Establish, furnish and maintain suitable installation office facilities in the vicinity of the

Anzalduas Dam (within 50 miles), to serve as the project office for the duration of the project in the location specified in the Contractor's Technical Proposal.

O. The contractor shall furnish and maintain portable toilets and handwashing stations at the work site.

P. The Contractor shall maintain an adequate staff of qualified support personnel to perform the work necessary to complete the project.

Q. The Contractor shall establish internal accounting methods and procedures for documenting and monitoring project costs and monitor schedule.

R. The Contractor shall establish and maintain Contract administration procedures, which shall include preparation of supplemental agreements and requests for time extensions as well as administration of subcontracts.

S. The Contractor shall include the complete project name and number on all correspondence related to this Contract.

T. The Contractor shall participate in work plan consensus, status and team building meetings with all appropriate participants at the start, on a monthly basis during the project development period and as needed to maintain the project schedule. If requested by the USIBWC COR, the Contractor shall act as the lead. The Contractor shall attend and participate in all review conferences pertinent to the work under the Contract. Project Manager or other designated Contractor’s representative shall attend all Conferences and Meetings. Contractor shall submit monthly reports to the USIBWC COR (or designee) by the 5th of each month to review progress reports for the preceding month, identify issues and process invoices.

U. The Contractor shall assume complete responsibility for the accuracy and completeness of Installation Documents prepared under this project.

V. The Contractor shall furnish written and electronic (pdfs) documentation of communications between the Contractor and any party pertaining specifically to this project to USIBWC for their records within one week of the communication. The Contractor is responsible for recording and distributing to the participants the minutes of all meetings pertaining to this project within two (2) business days of the meeting.

V. WORK PLAN REQUIREMENTS

A. Examination of Site

1. Prior to submitting a Proposal for Work, it is recommended the Contractor perform the following:

a. The Contractor and Installer shall visit the Project site to become familiar with existing site conditions, including the site location and size, review of portions of the PSA report and 30% Plans.

b. At time of site visit, contractor shall request and confirm receipt of existing USIBWC Asbestos and Lead Based Paint surveys from facility staff for consideration in development of contractor Work Plans.

B. The work plan consisting of first draft, second draft, and final work plans and other supplemental installation documents as needed for the comprehensive Physical Security Improvements Installation at the Anzalduas Dam shall comply with the following:

1. The work plan shall meet all applicable requirements as recommended in the this PWS. The plan shall comply with all applicable codes, standards, and regulations.

2. The work plan shall follow industry standards in respect to format and content. The work plan should outline the plan for installation for each item outlined in this PWS.

3. The work plan shall include product data sheets for all equipment to be installed under this Contract.

4. The work plan shall include product maintenance requirements and annual opinion of probable costs.

5. The work plan shall include all survey control maps/data required for installation of the project.

6. Drawings shall be provided in AutoCAD 2012 or greater and shall be geo-referenced to the Anzalduas Dam.

7. The Contractor shall prepare a work plan report for the project to include the basis for the installation, existing conditions within the project limits, survey information compiled for the project, datum information for the drawings, product data sheets, product maintenance requirements and yearly estimated costs, designs to include drawings and details as required, and any other data found to be pertinent by the Consultant.

8. The plan should also include operational considerations to improve physical security at all three facilities.

9. There will be a separate work plan for each site.

B. Site Investigation and Design Data Research: The Contractor shall perform field reconnaissance, surveys, and site investigations as required to complete the installation project. The Contractor shall be required to make their own field investigations to verify dimensions and other information shown on USIBWC furnished reference drawings and the PSAs. The Contractor is responsible for all travel, reproduction costs, permitting costs, and work required to obtain engineering information and design data for the accomplishment of the Contract documents of the project in accordance with requirements of this Performance Work Statement (PWS).

1. The Contractor shall become familiar with existing site conditions, including location of existing utilities.

2. The contractor shall document in the plan any confirmed or potential asbestos or lead based paint facility features that may be impacted by the proposed work including drilling, cutting, or cabling activities and all contract worker and USIBWC personnel safety precautions that may be required. Any asbestos or lead based paint hazard abatement or mitigation plans prepared by the contractor must be submitted to USIBWC for safety and environmental compliance review and concurrence prior to initiation of material disturbing activities.

C. Submitted work plans will reference all applicable laws, standards, codes and regulations and will be subjected to review and approval by USIBWC. In order to accomplish the USIBWC’s commitment to the protection and preservation of the environment and historical sites, the Contractor shall provide all drawings and supporting design analysis based on the requirements set forth in this PWS and in compliance with National Environmental Policy Act (NEPA). USIBWC’s Environmental Management Division will coordinate NEPA compliance. Areas to be avoided (historical sites, etc.) shall be provided to the Contractor upon request.

D. The Contractor shall be responsible for contacting, coordinating and obtaining review comments, approvals, permits and certifications by any and all applicable regulatory agencies except coordination with the State Historical Preservation Officer (SHPO) and resource agencies. EMD will coordinate with HC and other resource agencies based on the first draft of the work plan submittal for NEPA clearance. Contractor will be required to coordinate with EMD if additional project information is required by the resource agencies. The Contractor shall be required to coordinate, schedule, and conduct all necessary meetings with the regulatory agencies in order to accomplish the installation of the project. The Contractor shall coordinate with the USIBWC’s Contracting Officer’s Representative (COR) prior to commencing review and compliance confirmation with regulatory agencies.

E. The USIBWC’s COR shall be kept informed of all coordination efforts and communications with outside agencies and shall be provided with design comments and any pertinent documentation, and approval letters for each review submittal to all regulatory agencies.

F. The Contractor shall be responsible for incorporating revisions requested by the regulatory agencies. The Contractor will coordinate with the USIBWC’s COR prior to incorporating such revisions. The Contractor shall present its preliminary design to the USIBWC at the first draft stage and shall discuss with the USIBWC alternative approaches to installation of the project, including the feasibility of incorporating environmentally responsible approaches. The Contractor shall reach an understanding with the USIBWC regarding the requirements of the project.

G. The Contractor will make every effort to develop drawings to include materials that are resource-efficient and sustainable. The Contractor shall incorporate these principles into the work plan at the first draft submittal and clearly indicate these inclusions using bold-italicized lettering. A narrative shall also be provided in the work plan analysis which clearly identifies these areas of the specifications.

H. The IBWC Environmental Management Division (EMD) will submit the first draft work plan and applicable drawings provided by the Contractor to each State SHPO and other resource agencies. No work will begin prior to notification from EMD that clearance for installation to proceed has been given from these agencies.

I. Quality Control Plan Requirements: The Contractor is responsible for accuracy and completeness of the plans and related design prepared under this Contract and shall provide QC/QA measures defined in this PWS.

VI. REVIEWS AND OVERSIGHT VISITS

A. The work plan will be reviewed by the project team including representatives of

USIBWC technical divisions for conformity with USIBWC procedures and the terms of the Contract according to the QA/QC Plan requirements. Review by USIBWC does not include detailed review or checking of design of major components and related details or the accuracy with which such designs are depicted on the plans.

1. The review by the USIBWC’s Representative of the design work in order to verify that all the requirements of this Contract are adequately met.

2. The Contractor has complete responsibility for the accuracy and completeness of all design documents as well as the installation documents prepared under this project

B. USIBWC may also make periodic visits to the Contractor’s offices to discuss and verify progress and the Contractor’s QA/QC plan. USIBWC will give the Contractor (2) calendar days advance notice of intent to make an oversight visit.

C. Throughout the process, the Contractor may request additional oversight visits by USIBWC to discuss and verify progress and to assist the Contractor and/or its installers(s) in resolving questions and issues. The Contractor shall give USIBWC three (3) calendar days’ notice of any requested oversight visit.

D. Once the USIBWC has accepted the work plan, any item within the accepted work that the Contractor desires to subsequently change must be identified by Contractor through a written request identifying and requesting such change, and the change shall not be incorporated into the project until the USIBWC has agreed to the change.

VII. QA/QC REQUIREMENTS

A. The Contractor shall prepare a Quality Control Plan (QC). The QC Plan must be compliance confirmed by USIBWC prior to Contract execution. No activities may proceed until the Contractor’s Quality Control Plan has been compliance confirmed in writing by USIBWC. The plan shall detail how the Contractor will provide quality control (QC) for both the work plan and installation elements of the project, obtain samples from Contractor quality control testing, perform tests for Contractor quality control, provide inspection, and exercise management control (i.e. quality assurance testing) to ensure that work conforms to the Contract requirements.

B. The Contractor’s Quality Control Plan shall include a description of the quality control and quality assurance organization, including the number of full-time equivalent employees with specific Quality Control responsibilities and including a chart showing lines of authority and reporting responsibilities. The persons and organizations performing Quality Control functions shall have sufficient authority and organizational autonomy to identify quality problems, and to initiate, recommend, and verify implementation of solutions. All key personnel performing Quality Control shall be exclusively designated to such and shall not be assigned to perform conflicting duties.

C. The USIBWC reserves the right to require the Contractor to make changes in the quality control staff, including removal of personnel, as necessary, to obtain the quality specified.

1. Technicians and Inspectors

a. In addition to the above, technicians and inspectors shall be employed when necessary. The Testing Technicians and Inspection Technicians shall have the following qualifications:

b. For all concrete work, the operator is either ACI certified or qualified by a recognized equivalent, for written or performance testing program for all of the tests to be performed.

c. For all other work, industry standard certification and/or training shall be required for all technicians and inspectors.

2. If any reference material is outdated, contractor is responsible for using the most up to date requirements.

J. USIBWC Review of Work Plan

If USIBWC at any time determines that the Work Plan or Installation is proceeding which does not conform to Contract requirements, USIBWC reserves the right to suspend work for cause until resolution of the issue at no additional cost to the government.

K. Work Plan Quality Review

1. Prior to the release of final Work Plan Documents and Installation Documents, the

Contractor shall complete review with personnel experienced in the appropriate disciplines(s).

2. The review shall verify that the Work Plan Documents and Installation Documents were prepared in such a manner as to ensure that they will be acceptable to USIBWC, as well as the Management/Installation Team.

3. The criteria used in such review shall include:

a. Conformity of the final Work Plan documents and Installation Documents with the Contract Provisions.

b. Assurance that all materials, equipment and elements of the Work provided for in such documents which shall be incorporated into the Project have been provided to perform satisfactorily for the purpose intended.

c. The appearance, organization, technical and grammatical accuracy of such documents.

d. Verification that such documents have been checked and signed by the drafter, designer, checker and reviewers.

Assurance that such documents fully provide for proper installation, compatibility of materials and conformity to acceptance criteria for inspections and tests as provided in the Contract and in accordance with all documents listed in section III Applicable Codes Rules and Regulations.

L. Installation Quality Control (IQC) Plan Requirements

The IQC Plan shall include, as a minimum, the following to cover all installation operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers and purchasing agents:

1. Describe the Installation Contractor’s quality control organization, including the number of full-time equivalent employees with specific Quality Control responsibilities and including a chart showing lines of authority and reporting responsibilities.

2. List by discipline the name, qualifications, duties, responsibilities and authorities for all persons proposed to be responsible for Installation Quality Control and/or Quality Assurance.

3. Installation progress schedule

4. Installation submittal schedule.

5. Inspection requirements.

6. Quality control sampling, testing, and analysis plan with frequencies, location and methods.

7. Specify documentation for QC activities, including control charts.

8. Contractor’s requirements for corrective action when quality control and/or acceptance criteria are not met.

9. Procedures for tracking preparatory, initial and follow up control phases and control, verification and acceptance tests including documentation.

10. A list of the definable features of work.

11. A definable feature of Work is a task that is separate and distinct from other tasks and has separate control requirements. It could be identified by different trades or disciplines, or it could be work by the same trade in a different environment. This list will be agreed upon during the coordination meeting.

12. The USIBWC may supplement the IQC testing with independent assurance tests and inspections (Quality Assurance).

M. Acceptance of the Work by the Installation QC Manager does not mean the USIBWC accepts the Work.

N. Control of Phases of Work

1. Prior to the start of any work activity the Contractor shall hold a meeting to ensure that all project personnel have a thorough understanding of work to be done. The meeting should include discussions relating to what will be accomplished, by whom it will be performed, and where, when, and how the work will be done. These meetings are to ensure that all parties have the same understanding of the installation intent, have the appropriate plans and any special details, and are aware of safety regulations and procedures that need to be followed. At this time the QC inspection checklist for this activity should be reviewed.

O. Installation QC Documentation

1. The Contractor, Project Manager, Installation Contractor, and/or subcontractor shall maintain current records providing factual evidence that required quality control activities and/or tests have been performed. These records shall include the work of subcontractors and suppliers.

P. These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered.

These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the Contract.

Q. IBWC Form 163, Contractor's Daily Quality Control Report, shall be used to document this data. The original Form 163 with copies of these records in report form shall be hand carried to the USIBWC daily within twelve (12) hours after the date(s) covered by the report, except that reports need not be submitted on calendar days on which no work is performed. As a minimum, one (1) report shall be prepared and submitted for every seven (7) calendar days of no work and on the last day of a no work period.

All calendar days shall be accounted for throughout the life of the Contract. The first report following a day of no work shall be for that day only.

R. IBWC Form 163 shall be signed and dated by the Installation QC Manager. The report from the Installation QC Manager shall include copies of test reports and copies of reports prepared by all subordinate quality control personnel. All of these items shall also be provided to the COR in electronic format. IBWC Form 163 can be provided as a pdf scan of the original or as a pdf or word document containing a scanned electronic signature. All test reports and other items attached to the daily report shall also be scanned into pdf format.

1. The minimum scan resolution shall be 300 dpi by 300 dpi.

2. Color documents shall be scanned in color.

3. Test reports, QC reports, inspections, minutes, etc. shall all be submitted in separate electronic files.

4. The file names for the electronic files shall always start with the Contract day number and shall also contain a brief description as well as the calendar date. For example, 065 DR Contractor Name IBM16C0012 12-13-2016.pdf or 065 QC IBM16C0012 12-13-2016.pdf.

S. Notification of Noncompliance - The USIBWC will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor shall take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the worksite, shall be deemed sufficient for the purpose of notification.

T. Contractor Responsibilities - The Contractor shall be responsible for the quality of installation and materials incorporated into the project. The Contractor’s Quality Control measures are to ensure that operational techniques and activities provide material of acceptable quality. Contractor sampling and testing shall be performed to control the processes and determine the degree of material compliance with the Contract Provisions.

VIII. INSTALLATION TASKS

Installation shall not commence until after USIBWC review and compliance confirmation of design and NEPA review.

A. The Contractor shall furnish all services, materials, supplies, equipment, investigations, studies, project supervision, and travel as required in connection with this PWS. Below is a list of tasks to be completed.

1. Contractor is responsible for coordinating an assessment of requirements to ensure that weigh limits of the structure are not compromised. This may include a weight study to determine the appropriate materials.

2. Contractor is responsible for ensuring that the weight of any crane used for installation of the ballistic glass meets the weight limits of the bridge.

3. Contractor shall remove all south side aluminum paneling from the window on the 4th floor of pier # 4.

4. Contractor shall remove all south side windows and framing from the 4th floor of pier # 4.

5. Contractor shall remove all west side windows and framing from the 4th floor of pier # 4.

6. Contractor shall prepare window opening and install new Level 8 ballistic glass and framing on the south side windows of the 4th floor of pier # 4. This includes ballistic glass to replace the aluminum paneling from the bottom row of windows.

The Contractor shall ensure that the ballistic glass is properly formed to fit the current window openings. This must also include any conduits that run out of the window openings.

7. Contractor shall prepare window opening and install new Level 8 ballistic glass and framing on the west side windows of the 4th floor of pier # 4.

8. Contractor shall remove the west side administration building window and framing to include burglar bars.

9. Contractor shall remove the north side administration building window and framing to include burglar bars.

10. Contractor shall prepare window opening and install new Level 8 ballistic glass and framing on the west side administration building window and re-install burglar bars.

11. Contractor shall prepare window opening and install new Level 8 ballistic glass and framing on the north side administration building window and re-install burglar bars.

B. The contractor shall ensure that the ballistic glass is properly formed to fit the current window openings. This must also include any conduits that run out of the window openings.

C. The contractor shall ensure that the ballistic glass meets the standard to prevent the penetration of multiple 7.62 mm rounds. Contractor shall use National Institute of Justice (NIJ) and Underwriters Laboratories (UL) standards to develop the appropriate level of protection.

D. The contractor shall install fabricated and install aluminum strips to match the current window appearance. The aluminum strips shall be mounted to the outside of the ballistic glass.

E. The contractor will establish plans to secure and cover window openings in the event a window is removed and the new window is not installed at the end of the workday.

F. The contractor shall ensure that The Contractor will have an opportunity to review the conceptual drawings after RFP is issued. In addition, the Contractor after award will be able to review the documents to draft the Work plan and perform the subsequent installation.

B. The Contractor shall obtain all required installation related permits including Storm

Water Pollution Prevention Plan permit as applicable.

C. Prior to commencing installation, the Contractor shall become familiar with existing site conditions, including location of existing utilities. The Contractor shall be responsible for locating all underground utilities at the site prior to commencing installation. Contractor shall contact a utility locator company and if necessary, contact any utility directly. Prior to utility outages, the Contractor shall submit request for an outage, in writing, a minimum of 10 calendar days before with an estimated duration, to the Contracting Officer or his/her designated representative and notify facility that will be affected. This will give the facility ample time to basically shut down and save works in process, and in the case of ADF there is a sewage lift station that is electrically powered.

D. The Contractor shall keep the work site and staging area free from accumulation of waste material and rubbish during the Contract. The work site shall be cleaned daily.

E. The Contractor shall be responsible for the cleanup and disposal/recycling of solid, liquid, and electronic waste materials and rubbish from the installation site, field office(s) and staging area(s). Methods of disposal/recycling and all related service agreements shall be provided in the Work Plan.

1. The disposal of waste materials and rubbish shall be in accordance with applicable federal, state and local laws and regulations and with the requirements in these Contract documents. Should a conflict exist in the requirements for cleanup and disposal of waste materials, the most stringent requirements shall apply. All waste shall be disposed of at a licensed landfill or waste disposal facility.

2. No excess materials shall be deposited within USIBWC property, unless compliance confirmed by the USIBWC. Excess materials not compliance confirmed by the USIBWC for placement on Government property shall be disposed of or reused by the Contractor.

3. The Contractor shall keep records of the types and amounts of waste materials produced and of the disposal of all waste materials. These records shall be kept current and accurate and shall be available for review by the USIBWC.

4. The Contractor shall maintain work and storage areas free from accumulations of waste materials and rubbish and before completing the work, shall remove all temporary facilities, including, buildings, unused materials, concrete forms and other like materials, which are not a part of the permanent work.

5. Hazardous Materials.

All hazardous materials or wastes used or generated by the Contractor or discovered in work or storage areas defined as hazardous by 40 CFR 261.3, or other federal, state or local laws or regulations shall be disposed of by the Contractor in accordance with these Contract documents and applicable Federal, State and local laws and regulations.

a. Unknown waste materials that may be hazardous shall be tested and the test results shall be submitted immediately to the USIBWC for review.

b. A copy of all hazardous waste manifests shall also be submitted immediately to the USIBWC for review.

6. Non-hazardous Materials.

All non-hazardous materials or wastes used or generated by the Contractor to include, but not limited to, refuse, garbage, sanitary wastes, industrial wastes, paints, sealers, adhesives, oil and other petroleum products shall be disposed of by the Contractor in accordance with these Contract documents and applicable federal, state and local laws and regulations.

a. Disposal of materials shall be by removal from the installation site, Contractor’s field office and staging area(s).

b. All materials within the work site, Contractor’s field office and staging area(s) shall be removed prior to completion of the work under these Contract documents. All materials removed shall become the property of the Contractor.

7. In the event of the Contractor’s failure to perform the Work required by this

Specification, the Work will be performed by the USIBWC and the Contractor shall be responsible for the cost of such work. The costs for temporary controls provided by the USIBWC shall include both direct labor costs and other direct costs associated with the Work.

F. Record Drawings

1. The Contractor shall keep one current and updated record copy of all Contract documents (work plan.) at the Contractor’s field office. Specifications, plans, supplementary drawings and shop drawings shall be annotated to show all changes made during the installation process. These shall be available to the USIBWC on a monthly basis to inspect for accuracy and completeness.

2. The Contractor shall submit to the USIBWC, within ten (10) calendar days after completion of installation of work, a record copy of the Record Drawings for review and compliance confirmed. Record Drawings will be submitted to the COR for review and compliance confirmation.

3. Record Drawings Requirements/Deliverables:

a. Record Drawings are an official record of the project at the time of installation completion. The original "as-designed" Contract drawings are modified to show all additions, deletions and other changes made during installation. Accurate Record Drawings are very important for project operation and maintenance as well as future modifications.

b. Any deviations from plan design elevations, layout, quantities, coordinates, slopes, dimensions, workmanship, material and method of installation shall be clearly noted on the Record Drawings.

c. Cross out words like "equal to" or "similar to" and replace them with the specific information used during the installation process.

d. Detail locations and description of any utilities encountered during installation.

e. Stamp sheet with "RECORD DRAWING" and include Contractor’s name, USIBWC Contract number and date.

f. Record Drawings are required to reflect the same degree of detail as the original plans.

g. The Record Drawings shall contain a certification similar to: "I certify that the locations, elevations, depths and comments regarding installation accurately reflect existing field conditions."

h. "As-Designed" items that are not shown on the Record Drawing shall be frozen instead of deleted.

i. Final Record Drawings will be submitted as:

i. One (1) complete plan and profile set printed at half scale on 11"x17" paper.

ii. Two (2) complete Record Drawing set printed at full scale of 22"x34” paper.

iii. Five (5) electronic sets of drawings in pdf format.

iv. Five (5) electronic sets of drawing in AutoCAD (dwg) 2012 format. This set shall fully contain all necessary items to access the data in AutoCAD.

v. All CD/DVDs shall be labeled with the Contract Name, IBWC Contract

Number, general contents and preparer’s name.

a. Contractor's and Inspector’s Daily Report The Contractor shall maintain daily records of installation activities in the form of a Contractor's Daily QC Report and an Inspector’s Daily Report. Together they shall provide a complete word picture of the project, covering both the normal work process and anything unusual that occurs on the project.

b. Installation Contractor’s Record of Safety

The Contractor shall maintain a record of all safety meetings, incidents, near missed, and accidents.

c. Materials Certification

The Contractor shall submit a materials certification package to USIBWC which contains a checklist and supporting documentation. The supporting documentation shall consist of a summary of all documentation practices utilized for material acceptance and explanations of any deficiencies noted on the checklist. Material certifications shall ensure that all items meet the Buy American Act (41 USC 10a - 10d).

d. Other Records

Other records are comprised of all relevant installation records. These records shall be attached to the daily reports. Examples of these records include but are not limited to the following: Quantity delivery tickets; Material acceptance test reports; Concrete placement records; Source of materials documentation;

Prints of shop drawings; Horizontal and vertical alignment data; Earthwork calculation data; Scale test report; Grade books; Cross section notes.

e. Final Installation Record Report’

The Contractor shall prepare for review a summary report of all installed equipment, product data sheets, training documentation, OPC of yearly maintenance Costs, list of maintenance activities required and frequency required, record drawings or plans showing all installed components.

G. Completion of Work Inspections

1. Contractor Inspection.

At the completion of all work or any increment thereof established by a completion time stated in FAR Clause 52.211-10, entitled "Commencement, Prosecution and Completion of Work," or stated elsewhere in the Contract documents, the Installation QC Manager shall conduct an inspection of the work and develop a "Contractor’s Punch List" of items of work which do not conform to the Contract documents. Such a list of deficiencies shall be included in the QC documentation and shall include the estimated date by which the deficiencies will be corrected.

Contractor shall have xxx days to complete punch list items and all close-out documents after the completion of construction.

a. The Installation QC Manager or staff shall make a second inspection to ascertain that all deficiencies have been corrected and so notify the USIBWC.

b. These inspections and any deficiency corrections required by this paragraph will be accomplished within the time stated for completion of the entire work.

2. Contractor and USIBWC Pre-Final Inspection.

The Installation QC Manager, Contractor's superintendent, or other primary management person and the USIBWC will be in attendance at this inspection. The Pre-Final Inspection will be formally scheduled by the USIBWC based upon notice from the Contractor. This notice will be given to the USIBWC at least fourteen (14) calendar days prior to the Pre-Final Inspection. The notice must include the Contractor’s assurance that all deficiencies listed in the "Contractor’s Punch List" developed during the Contractor Inspection phase have been corrected and all Installation Work is complete and acceptable by the date scheduled for the Pre- Final Inspection.

a. Failure of the Contractor to have all Installation Work acceptably complete will be cause for the USIBWC to cancel the inspection and bill the Contractor for the USIBWC’s additional inspection costs in accordance with the Contract clause entitled, "Inspection of Installation."

b. At this inspection the USIBWC will develop a "USIBWC’s Punch List" of incomplete and/or unacceptable work performed under the Contract and will subsequently furnish this list to the Contractor.

c. Failure of the USIBWC to detect and list all incomplete and/or unacceptable work during this inspection will not relieve the Contractor from acceptably performing all work required by the Contract documents.

d. The USIBWC, at its option, may accept this inspection as the final acceptance inspection if in its opinion, the completion status of the inspected facilities and other work performed under the Contract, warrant this consideration.

3. Contractor and USIBWC Final Acceptance Inspection.

The Installation QC Manager, the superintendent or other primary management personnel and the USIBWC will be in attendance at this inspection. The final acceptance inspection will be formally scheduled by the USIBWC based upon notice from the Contractor. This notice will be given to the USIBWC at least fourteen (14) calendar days prior to the final acceptance inspection. The notice must include the Contractor’s assurance that all items in the "USIBWC’s Punch List" developed during the Contractor and USIBWC Pre-Final Inspection phase have been corrected.

a. Failure of the Contractor to have all Contract Work acceptably completed for this final acceptance inspection will be cause for the USIBWC to cancel the inspection and bill the Contractor for the USIBWC’s additional inspection costs in accordance with Contract clause 52.246-12, entitled "Inspection of Construction."

b. This inspection will be considered another Contractor/USIBWC Pre-Final Inspection and the Contractor must schedule another Contractor/USIBWC Final Acceptance Inspection after all items have been corrected.

c. Otherwise, this inspection will be considered a Contractor and USIBWC Final Acceptance Inspection if all items in the "USIBWC’s Punch List" and all other work are considered acceptably complete by the USIBWC.

IX. CONTRACT CLOSE-OUT

A. The Contractor shall complete/submit the following for the Contract to be closed and prior to final payment:

1. 100% completed project in accordance with the PWS and final Installation

Record Report prepared by the Contractor.

2. All installation management and administrative items as specified in this PWS are completed.

3. The installation site and all work shall pass all final inspections.

4. All punch list items shall be completed and inspected by the USIBWC Inspector and COR.

5. The entire work site shall be cleaned.

6. The Contractor shall submit all reports for testing and inspections of the work.

a. QC tests and reports shall be organized by type of material, type of test and location.

b. Original minutes from all preparatory phase inspections and initial inspections shall be provided.

c. The Contractor shall indicate by manner of testing, material tested and locations tested how the quality control requirements of the Contract were met. This shall be provided in a written report signed by the Contractor that contains a certification that all work was constructed per Contract requirements.

7. All submittals required shall have been submitted to the COR.

8. The Final Installation Record Report including Drawings shall have been submitted and compliance confirmed.

9. Submit Operation and Maintenance (O&M) Data/Manuals.

a. O&M Manuals shall contain data specifically applicable to this Contract and a complete and concise depiction of the provided equipment, product, or system, stressing, and enhancing the importance of system interactions, troubleshooting and long-term preventative maintenance and operation.

b. The Contractor shall compile and prepare data and deliver to the COR prior to the training of USIBWC personnel.

c. Data for each system shall include operating instructions, safety precautions, normal operations, operator service requirements, preventative maintenance, lubrications data, preventative maintenance plan and schedule, corrective maintenance (repair), maintenance and repair procedures, removal and replacement instructions, spare parts and supply lists, testing requirements, and special tool information,…

This is the start of the file's text. The full file is on GovTribe.