M14_Burst_Diaphragm_Statement_of_Work.pdf

PDF 37 KB Posted

Attached to
Mach 14 Burst Diaphragms Federal contract opportunity
Solicitation number
FA9101-18-Q-0022
Issued by
Department of the Air Force Materiel Command Test Center

View the file

Other files for this federal contract opportunity

Other files attached to Mach 14 Burst Diaphragms, newest first.
File Type Posted
Burst_Diaphragm_Combined_Synopsis.pdf PDF
Drawing_77-1088.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Thursday, May 03, 2018

Distribution A.

Approved for Public Release. Distribution is unlimited. (AEDC PA # 2017‐221 & IRA # 3367)

Destruction Notice.

Destroy by any method that will prevent disclosure or contents or reconstruction of the document.

STATEMENT OF WORK FOR MACH BURST DIAPHRAGM

I. PURPOSE

The purpose of the effort is to fabricate hardware for the Arnold Engineering Development Complex (AEDC) Tunnel 9 Diaphragm Area in order to provide replacements for used hardware.

II. SCOPE

The scope of this effort is to fabricate Tunnel 9 Diaphragm Area Hardware to meet the operational needs of the Tunnel 9 facility. The fabricator shall manufacture the items listed in Table 1 according to their corresponding drawings. The fabricator shall supply a written material certification for the material used to fabricate the burst diaphragms which shall include chemical composition, yield strength, tensile strength, modulus of elasticity, and percent elongation. Prior to machining grooves shown in Drawing 77-1088-12, the fabricator shall provide the material certification to AEDC to allow AEDC to modify the remainder under the groove dimension to ensure proper diaphragm operation in the AEDC facility. The fabricator shall supply a copy of the required reports specified in each drawing. The fabricator shall supply a 100% inspection report for each part. The fabricator shall supply a certificate of compliance for each part. The fabricator shall mark each part with layout dye the part number, thickness, remainder from the corresponding drawing as well as an identification number in the range shown for each item in Table 1. Upon completion, all parts will be shipped to the Tunnel 9 facility, Arnold Engineering Development Complex-White Oak, 10905 New Hampshire Ave, Silver Spring, MD 20903-1050. Drawings and parts subject to distribution statement as contained in the drawings.

Table 1. Tunnel 9 Diaphragm Area Hardware Item

Drawing Number Description Material Quantity Identification

Number

1 77-1088-3 Mach 14 Burst Diaphragm (.125x.080)

Ta-10W (ASTM B708) 70 331801001 to

331801070

2 77-1088-12 Mach 14 Burst Diaphragm (.125x.085)

Niobium Alloy C-103 (ASTM B654) 50 331802001 to

331802050

III. PERIOD OF PERFORMANCE

The fabricator shall deliver the finished parts 180 calendar days after the contract is awarded.

Thursday, May 03, 2018

Distribution A.

Approved for Public Release. Distribution is unlimited. (AEDC PA # 2017‐221 & IRA # 3367)

Destruction Notice.

Destroy by any method that will prevent disclosure or contents or reconstruction of the document.

IV. DELIVERABLES

• 70x Mach 14 Burst Diaphragm (.125x.080) – Ta-10W per Drawing 77-1088-3

• 50x Mach 14 Burst Diaphragm (.125x.085) – Niobium Alloy C-103 per Drawing

77-1088-12

• Written material certification that includes chemical composition, yield strength, tensile strength, modulus of elasticity, and percent elongation for material used to fabricate Each Part

• 100% Inspection Report for Each Part

• Certificate of Compliance for Each Part

V. SPECIAL REQUIREMENTS

AEDC can furnish electronic CAD solid models of the parts on request in various formats such as STEP, IGES, and native Pro/E. Note that the accuracy of these files is not certified for driving CNC programming. If Vendor wishes to Drive CNC machining of the base parts with these files it is strongly urged to verify the accuracy of the file prior to machining the parts.

I. Purpose
II. Scope
III. Period of Performance
IV. Deliverables
V. SPECIAL REQUIREMENTS

File details come from the government source that posted it.