Question Set 2.docx

DOCX document 18 KB Posted

Attached to
FA8604 - MMHS - Storage Aids System at Eielson AFB, AK Federal contract opportunity
Solicitation number
FA8604-20-R-8103
Issued by
Department of the Air Force Materiel Command

About this file

This document contains a request for proposal and related questions and answers for a storage aid system project at Eielson Air Force Base in Alaska. The solicitation requests proposals for the design, fabrication, installation and testing of a storage aid system on base. Proposals are due by January 7, 2020 with an anticipated contract completion date of 210 days after award. The storage aid system will be located in Buildings 3446 and 3213. Evaluation will be based on lowest price technically acceptable with award going to the responsible offeror providing the lowest price. The work includes modifying an existing electrical system to support the new storage aid system. A site visit is optional and at the offeror's expense. Prevailing wage does not apply. The opportunity is set aside for small businesses with less than 500 employees.

View the file

Other files for this federal contract opportunity

Other files attached to FA8604 - MMHS - Storage Aids System at Eielson AFB, AK, newest first.
File Type Posted
RFP FA8604-20-R-8103.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question Set 2 FA8604-20-R-8101 Eielson AFB, AK Question 1:

For the Eielson AFB cabinet supported mezzaning the customer will want to consider switching the 4 - YD double 60” wide cabinets to the upper position in this configuration with the 8 - XDC standard 30” wide cabinets to the floor or lower level and keeping the 1 – YD on the floor with these XDC’s. I’ve highlighted the cabinets on the drawing attached to be switched. Stacking the 30” cabinets on top of the 60” will create stress points that will eventually cause the drawers in the 60” cabinet to stick or not open at all.

For stacking MDC’s 60” wide & 30” wide we recommend the following:

You can always place a 60” wide on top of another 60” wide.

Also you can place the 60” wide on top of 2 @ 30” wide.

You cannot place 2 @ 30” wide on top of the 60” wide.

The sheet metal to center of the 60” wide will experience stress points created by 2 @ 30” wide

Answer 1:

Agree with switching position of 30” cabinets to lower level and 60” cabinets to upper level. See AF drawing PEL 701-02 REV A.

Question 2: Do we need to provide the foam lining for the cabinet drawers without compartments? If so, could you please describe the type of foam lining i.e. Plain or the type that is used to create cutouts to hold tools?

Answer 2: All cabinets with “F” designation (XF, YF) are provided with foam lining. Foam shall be the type used to create tool cutouts.

Question 3: Is there a site visit scheduled in the near future.

Answer 3: You are welcome to schedule a site visit (at your expense) by contacting the Base Project Officer. The BPO’s contact information can be found in the RFP, Attachment 8 “Contractor Information”. This optional site visit is not chargeable to the Government or any anticipated contract.

Question 4: Will this job be under prevailing wage (David/Bacon) or regular hourly wages

Answer 4: As this is considered a supply requirement with incidental service, this acquisition is not subject to the Davis Bacon Act or prevailing wage rates.

Question 5: For the modification to existing system, removal of mezzanines. Looking at the drawing PEL701-02 is there any type of roll up doors for the mezzanine removal other than the 3 regular sized doors.

Answer 5: There is not an overhead roll up door.

Question 6: Regarding the subject solicitation (CSN PEL701) request for clarification on the electrical system scope of work. The SF1449 continuation sheet states:

MODIFICATION TO EXISTING SYSTEM

0007 1 __________ Lot __________ Noun: MODIFICATION TO EXISTING SYSTEM

ACRN: AA

PSC: 3990

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

Existing equipment shall be dismantled, removed and disposed of off-base in accordance with Cover PD and APP F, and Figure 1 of APP F as detailed below: 2 existing mezzanines from Building 3213.

The PD at 3.2.1 goes on to state the scope of work as:

The Contractor shall run electrical power to the modular cabinet mezzanine system from the electrical supply that presently provides service to the two existing mezzanines which are to be removed (Appendix F). The Contractor shall indicate the new load served by each circuit breaker utilized on the existing directory.

The contract document is silent as to installation of any new equipment such as light fixtures, receptacles, etc.

Can you please clarify the scope of the electrical work?

Answer 6:

See Appendix E

3.2.10.3. Lighting

The Contractor shall provide LED lighting underneath the mezzanine with a minimum luminance level of 50 foot-candles measured at 30 inches above the floor. Lighting shall be supported by the bar grate deck.

3.2.10.3.1. Fixtures

Fixtures shall not be suspended. T-8 LED light fixtures and lights shall be utilized. LED lighting using 4-foot tubes shall be utilized to light the aisle area underneath the walkway. Lenses shall be provided for all lights.

3.2.10.3.2. On/Off switches

On/off switch locations shall be located as shown on AF Drawing PEL701-02. Switches shall be of the totally enclosed, tumbler type. Switches shall be located 52 inches +/- 2 inches in height from the floor.