OMC_Equipment_Lease_Final_SOW_20_Sep_2016.pdf
PDF 182 KB Posted
- Attached to
- Mail Metering Lease Federal contract opportunity
- Solicitation number
- FA8601-16-T-0380
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OMC_Questions_and_Answers_(4_Nov_16).pdf | ||
| OMC_Equipment_Lease_Draft_SOW_Revised_4_Nov_2016.pdf | ||
| Additional_Instructions_to_Offerors_FA8601-16-T-0380.pdf | ||
| Evaluation_Factor_with_Prior_Experience_for_FA8601-16-T-0380.pdf | ||
| FA8601-16-T-0380_Solicitation_Doc.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
WPAFB OFFICIAL MAIL CENTER
POSTAGE AND METERING EQUIPMENT LEASE
Prepared by
88th Communications Group Wright-Patterson
Air Force Base
7 September 2016
STATEMENT OF WORK FOR OFFICIAL MAIL CENTER
1.0 SCOPE: This Statement of Work (SOW) defines the effort required for mail metering at the
Wright-Patterson AFB (WPAFB) Official Mail Center (OMC), hereinafter referred to as WPAFB
OMC, located at Wright-Patterson AFB, Ohio. The lease requirement shall be in accordance with
(IAW) this SOW.
Background. The WPAFB OMC requires the services of posted mail via metered postage through two high-volume postage meters and machines for use in the Base Information Transfer
Center (BITC), and one low/mid-volume postage meter and machine for use in the Document
Security Section. All users lease meters and postage meters are only compatible when used on postal equipment manufactured by the same vendor. Therefore, postage metering equipment and meters must be purchased or leased from United States Postal Service (USPS) certified vendors.
The Government requires the equipment to maintain a 97% operational rate. Further, the
Government requires currency on all USPS changes made to rates and methods/types of mailing.
These changes are mandated and authorized by the USPS Board of Governors for all commercial mailers and all vendors require USPS certification prior to implementing the USPS mandated changes.
2.0 APPLICABLE DOCUMENTS & TRAINING
2.1. Contractor shall make available operational handbooks on all leased equipment at start of contract. In lieu of printed handbooks, the contractor shall advise the government Contracting
Officer Representative (COR) of the on-line source for operational assistance.
2.2. The Contractor shall provide initial training by a factory trained technician on the postal metering equipment, software capabilities, and reports creation and generation when equipment is delivered and be available to respond to questions throughout the life of the contract. Further, training shall be provided by technicians who are trained on all aspects of equipment usage and software capabilities and must be available for further training as changes occur throughout the life of the contract at no additional cost to the Government.
3.0 REQUIREMENTS
3.1. The contractor shall provide lease equipment to meet the requirements specified in this
SOW.
3.1.1. Equipment and Software
3.1.1.1. Postage metering equipment shall be modular in design.
3.1.1.2. All postage metering equipment and software shall be USPS compliant and have the ability to accept GSA Schedule 48 pricing. Further, all future changes to terminology or rates
USPS enacts throughout the life of the contract shall be provided through updated software at no additional cost to the Government.
3.1.1.3. All postage metering equipment and software must be capable of interpreting P-39 barcode symbology and translating that information to the reports management system.
3.1.1.4. The contractor shall provide two (2) high-volume leased digital Postage Meters with dynamic weighing modes/differential weighing/integrated weighing platforms for the Base
Information Management Center (BITC) capable of processing letters and flats simultaneously, specifically, mixed mail.
3.1.1.4.1. High-volume postage metering equipment shall be capable of processing a minimum of 300 letters per minute, at a minimum size of 3.5” x 5” and a maximum size of 13” x
15”.
3.1.1.4.2. High-volume postage metering equipment shall be capable of automatically adjusting the thickness required for processing mixed mail with a minimum thickness of .25” and a maximum thickness of .8”.
3.1.1.4.3. High-volume postage metering equipment shall be capable of processing 1,500 pieces of mail per day for maximum productivity.
3.1.1.5. The contractor shall provide a remotely connected weighing platform for each high-volume postage metering machine capable of weighing a minimum of 70 lbs.
3.1.1.6. The contractor shall provide one (1) low-volume/mid-volume, leased digital Postage
Meter with dynamic weighing modes for the Document Security Section capable of processing
300 pieces per day for maximum productivity.
3.1.1.6.1. Low/Mid-volume postage metering equipment shall be capable of processing up to 150 letters per minute at a minimum size of 3.5” x 5” and a maximum size of 13” x 15”.
3.1.1.6.2. Low/Mid-volume postage metering equipment shall be capable of automatically adjusting the thickness required for processing mixed mail with a minimum thickness of .25” and a maximum thickness of .8”.
3.1.1.7. All postal metering equipment shall include capability to print posted meter tapes or labels.
3.1.1.8. The contractor shall provide three (3) Thermal Tape/Label Roll Dispensers.
3.1.1.9. The contractor shall provide (3)wired key boards and mice.
3.1.1.10 All postal metering equipment and software must be capable of processing multiple batches of mail at one time while applying billing to 100+ different accounts.
3.1.1.11. The contractor shall provide postal metering equipment and software capable of allowing user defined reports. Reports must be able to capture specific periods of time, for example, begin date to end date.
3.1.1.12. The contractor shall provide three external printers to be used for monthly reports.
3.2. REPORTS
3.2.1. User defined reports shall include the following information for each piece of postal metering equipment operated per day:
3.2.1.1. Total number pieces mailed, totaled by type of mail, and department identification.
3.2.1.2. Total cost applied for pieces mailed, totaled by type of mail, and department identification.
3.3.1.3. Total pounds and pieces processed, totaled by type of mail, and department identification.
3.3. Maintenance, Repairs, and Software Updates/Upgrades
3.3.1 The contractor shall be responsible for the maintenance, repairs, and software updates/upgrades for all leased equipment.
3.3.2. The contractor shall provide remedial maintenance upon notification that postal metering equipment is inoperable or presenting errors slowing down production or causing work stoppage.
3.3.2.1. Repair requests shall be responded to by a trained technician within 4 - 6 business hours of notification.
3.3.2.2. The contractor shall complete repair or remediate problems within 24 business hours of notification.
3.3.2.3. Technician that responds to service calls shall be capable of troubleshooting and repairing hardware and software.
3.3.3. If any equipment requires more than four (4) service calls for mechanical failure in any one month period, that machine will be removed and replaced within 10 business days and the removed unit will not be utilized further on this contract.
3.3.4. Preventative and Remedial Maintenance shall be provided and scheduled Monday through
Friday, excluding Federal Holidays, and during the business hours of 0700 (7:00 am) and 1630
(4:30pm). Holidays are as follows: New Year’s Day, Martin Luther King Day, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving, and Christmas.
3.3.5 The Contractor shall provide all maintenance and upkeep to three external printers.
3.4. Damaged Parts, Tools, and Instruments
3.4.1. The contractor shall be responsible for replacing all parts, module(s), machine, or meter which are damaged during Preventative, Remedial Maintenance or normal wear and tear.
Replacement items shall be of equal or better quality and shall be at no additional cost to the government. The Government shall be liable for damage caused by users negligence.
3.4.2 The contractor shall have all equipment and software installed/tested and fully operational at the start of the contract. This shall include installation and successful performance of required testing for all USPS certifications to ensure compliance.
4. SERVICE LOCATION
4.1. Equipment will be located at:
Official Mail Center
5237 Cooper Street
Building 258, Door 1
Wright-Patterson AFB, OH 45433
5. PERIOD OF PERFORMANCE
5.1. The Period of Performance shall be Base Year with four (4) 1-year options.