About this file

First Article Requirements Form 260

View the file

Other files for this federal contract opportunity

Other files attached to LAU-12X Electrical Solenoid, newest first.
File Type Posted
Contract_Data_Requirements_List.pdf PDF
First_Article_Process.pdf PDF
Packaging_Requirements.pdf PDF
Transportation_Data.pdf PDF
FA855417R0010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRST ARTICLE REQUIREMENTS 1. DATE

04 FEB 2017(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

98752 / 653752-2

4. NSN

5945013348082AL

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 2 UNIT(S) OF LOT / ITEM 1

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

WILL X WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

REQUIRED X NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

Performance or other characteristics which the First Articles must meet are Dimensional Inspection, Specification Control

B. The detailed technical requirements for First Article approval tests are contained in

Ensure all features are IAW Respective drawings/TDP

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

Number of days for government approval / disapproval 75 days.

D. Contractor's notification to ACO and

782cbsg.afat@robins.af.mil

(Requesting Activity) of test time and location due 45 days prior to start of testing.

E. X TEST REPORT REQUIRED

(1) Forwarded to

AFLCMC/EBHAEM, First Article Man

235 Byron Street Ste 19A

Robins AFB, GA 31098-1813

OFFICIAL BUSINESS

(2) Government written notice of approval / disapproval due 45 days after receipt of contractor's report.

F. FIRST ARTICLE DELIVERY

(1) Due within calendar days from date contract.

(2) Notify calendar days prior to shipment.

(3) Delivered to government at

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

$0.0000

Page 1 of 2AFMC IMT 260, 20020830, V-3 Version 4Generated by PRPS using Jasper Reports on 17 Mar 2017

FIRST ARTICLE REQUIREMENTS 1. DATE

04 FEB 2017(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

10. DISPOSITION OF FIRST ARTICLES

Approved First Articles will be forwarded to

(insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

Disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

X Other Disposition:

Will be retained by the vendor

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. X Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, X Air Force.

b. X Offerors currently in production of the same or similar article for a Government, DoD, X Air Force contract and who have received First Article approval under the existing contract.

c. X Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, X Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. X Provided not more than 36 months have elapsed since completion of the contract.

e. First Article testing will not be waived.

f. X See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

12. REMARKS

Brigmond, Ronald LNAME: 06 FEB 2017DATE:

NAME: Silver, Dean DATE: 14 JUL 2016 For any metal that is not created in the United States, an independent chemical analysis, hardness, and microstructure analysis will be required. Also, any processing performed outside the United States will require an independent verification performed/applied IAW Tech Data. The FA will be made available for the EBREM to perform a Form/Fit/Function test. Provide an uncoated exhibit and a coated/assembled exhibit.

NAME: Brigmond, Ronald L DATE: 01 JUN 2015 Two (2) exhibits required, Exhibit 1 shall be assembled and Exhibit 2 Unassembled.

Exhibit 1 shall be tested IAW Specification Control Drawing Number 653752 (CAGE 98752) Rev K. Exhibit 2 shall undergo dimensional inspection to ensure all features are IAW Drawing Number 653752 Rev K. Testing on the two exhibits can be performed concurrently.

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST

(Name, Organization, Phone)

Oliver, Michael

AFLCMC/EBREM

478-327-4330

497-4330

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

TEST (Name, Organization, Phone)

Silver, Dean

409 SCMS/GUEA

478-327-2785

497-2785

Page 2 of 2AFMC IMT 260, 20020830, V-3 Version 4Generated by PRPS using Jasper Reports on 17 Mar 2017