Medium_Class_Stage_III_SOO.pdf

PDF 131 KB Posted

Attached to
ICBM Medium Class Rocket Motor BAA Federal contract opportunity
Solicitation number
FA8219-13-R-7001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

MCS SOO

View the file

Other files for this federal contract opportunity

Other files attached to ICBM Medium Class Rocket Motor BAA, newest first.
File Type Posted
AFI33-203V3.pdf PDF
Questions_and_Answers.docx DOCX document
FA821913R7001_Solicitation.pdf PDF
BAAGuide.pdf PDF
PAP_BAA_24_Apr_13.pdf PDF
CDRL_package.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 11 24 April 2013

Statement of Objectives (SOO) Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor

Technology Demonstration

Page 2 of 11 19 April 2013

TABLE OF CONTENTS

SECTION A: STATEMENT OF OBJECTIVES(SOO)/NEEDS

SECTION B: AWARD INFORMATION

SECTION C: BIDDER's LIBRARY ...……………………………………………………

Page 3 of 11 19 April 2013

SECTION A

STATEMENT OF OBJECTIVES (SOO)/NEEDS

I. Statement of Objective/Needs: This program seeks to demonstrate available / common technologies in a Medium Class Stage III motor that may be applicable to multiple future common strategic propulsion systems and potential application to a Family of Motors capability. This effort will begin the development of a flight motor design that is intended to be a direct replacement for the SR-73 (S-133-06658(A), Pt. I) and requirements will be based SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document, unless otherwise noted. Motors built for this effort will only require those capabilities required for static tests listed in I.E.1 & 2.

A. Performance Criteria: For proposal evaluation, provide a maximized ideal delta velocity (assuming zero g and zero drag) of no less than 13,500 feet per second to a mass of 1,450 lbm. These requirements are outlined in SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document.

The Supplier shall provide a list of Government Furnished Property required to complete the efforts of this SOO.

Performance of the tests in I.E.1 & 2 meeting the requirements in this SOO is one of the success criteria of this effort.

B. Design Criteria:

1. The nominal diameter of the motor shall be 52-in. The target length in a static

(unpressurized) condition from the forward to aft interface planes shall be 63.513-in, and the length from the aft interface plane to the nozzle exit plane shall be 28.055-in, IAW the SR73 Envelope ICD. There is no minimum length requirement. Stage mass including the, raceway, external insulation and all associated stage hardware should not exceed 8,100 lbm.

2. Design life shall be a minimum of 30 years with a goal of 35 years.

3. The motor case shall employ a domestic fiber.

4. The motor shall employ a Hazard Classification 1.3 propellant formulation.

5. The thrust vector actuation (TVA) system shall employ a low-cost, low-maintenance actuation system.

6. The motor shall include the capability to terminate the forward thrust of the motor per

SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document, paragraph 3.2.1.7.

7. The stage flight design shall include provisions for:

a. A flight configuration raceway

b. External insulation (for base heating and aerodynamic environments, including silo lift off environments.)

c. Roll control system installation

d. Installing Range Safety certified flight termination / stage destruct hardware

e. Other stage hardware (such as Ordnance Initiation Systems, etc.) including that which would be provided by an integrating contractor.

Page 4 of 11 19 April 2013

f. Accommodations for accessibility (access panels) for maintenance and inspection

C. Design and Analysis: This effort includes all design, analysis, and program management tasks.

1. Conduct stage design and analyses to determine the acceptability of a medium class motor based on the performance and design criteria in par. I.A and I.B.

2. Evaluate available emerging technologies to determine potential or future benefits to a common or optimized missile configuration including:

a. Advanced high performance Hazard Classification 1.3 propellants

b. Advanced high strength domestic fiber materials

c. Innovative design and manufacturing concepts

d. Other technology disciplines with potential impact toward optimization and commonality with other advanced propulsion systems.

3. Conduct risk analyses and assessments to identify potential risks for all stage elements and proposed risk mitigation programs that may be required.

4. Develop a Demonstration Test Plans for all components including the demonstration of motor thrust reversal/termination, case burst test and motor static testing IAW CDRL A011, DID # DI-NDTI-80566A. Provide Test Procedures IAW CDERL A012, DID # DI-NDTI-80603A. Report results of all tests in a Test/Inspection Report IAW CDRL A013, DID # DI-NDTI-80809B within 60 CD after test.

5. Conduct final design and analyses for a flight configuration and the demonstration motor to be static fired.

D. Program Reviews / Technical Interchange Meetings:

1. Host a kick-off meeting to review Government program objectives, design criteria, requirements, constraints, etc. and coordinate contractor’s comments, questions, etc.

2. Prepare a Program Management Plan, IAW CDRL A005, DID # DI-MGMT-81797, defining scheduled major milestones including program reviews, technical interchange meetings, component development testing, demonstration motor components fabrication and assembly, test readiness review, demonstration motor testing, etc.

3. Conduct a preliminary program review / technical interchange meeting to be held within 60 days after contract award. Provide a Meeting Agenda IAW CDRL A002, Conference Agenda (Meeting Agenda) DID # DI-ADMN 81249A, 5 working days prior to the meeting. Provide handouts IAW CDRL A003, Briefing Materials, DID # DI-MGMT-81605. A Record of Meeting Minutes Report IAW A004, DID # DI- ADMN-81505, shall be provided 10 working days after the meeting. The agenda for the meeting shall include a review of the following:

a. Program Management Plan, IAW CDRL A005, DID # DI-MGMT-81797 and schedule of major milestone events.

Page 5 of 11 19 April 2013

b. Proposed design modifications to meet performance and design criteria (stated in par. I.A and I.B).

c. Supporting trade studies, rational for design decisions, and initial risk assessment IAW CDRL A015, Technical Report –Study/Services, DID DI # DI-MISC- 80508B/T.

d. Component and motor demonstration test plan (defined in par. C.4).

e. Initial performance evaluation of alternative and / or advanced technologies for propellants, materials, designs, etc. (for future proposal planning).

4. In addition to the formal design reviews (PDR, CDR, etc) conduct up to four additional program reviews / technical interchange meetings over the course of the program. Provide a Meeting Agenda IAW CDRL A002, Conference Agenda (Meeting Agenda) DID # DI-ADMN 81249A, 5 working days prior to the meeting.

Provide handouts IAW CDRL A003, Briefing Materials, DID # DI-MGMT-81605, 5 working days prior to the meeting. A Record of Meeting Minutes Report IAW A004, DID # DI-ADMN-81505, shall be provided 10 working days after the meeting

5. Conduct technical interchange meetings no later than 30 days prior to the start of the component fabrication of each demonstration motor test. Provide handouts IAW CDRL A003, Briefing Materials, DID # DI-MGMT-81605. The meeting agenda shall include a review of the following:

a. Conceptual drawings, IAW CDRL A014, DID # DI-SESS-81001D, and Design Analysis Reports of major components IAW CDRL A015, Technical Report – Study/Services, DID # DI-MISC-80508B/T, motor performance pre-test ballistic predictions, component test data generated to support the design and analysis of stage design and update to risk assessment.

b. Final design of the stage flight configuration with projected performance parameters and mass properties data

c. Design exceptions in the demonstration motor to be static tested

d. Updates to the motor demonstration test plan

6. Program reviews / technical interchange meetings shall be held at agreed upon government or contractor facility.

7. A government provided integrator will be used to support the government and assure that the stage meets the Stage III motor specification. As such, they will accompany the government to all design reviews. This work will be facilitated through the government and it’s Integrator. Proprietary data will not be shared with any other rocket motor manufacturing contractor. This effort is anticipated to include support of Interface Control Working Group and Systems Requirements Working Group to include approximately seven Technical Interchange Meetings and twenty Teleconferences.

E. Hardware Fabrication and Test Support:

1. Baseline Program (items are in priority order and to be priced separately):

Page 6 of 11 19 April 2013

a. Sea Level Static Test with Thrust Termination System – fabrication and static test of a demonstration motor to be conducted at ambient (sea level) conditions to obtain baseline characterization of the motor performance. The test shall also demonstrate the proposed forward thrust reversal / termination requirement during tail-off per the requirements of SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document, paragraphs 3.2.1.7.1.2 and 3.2.1.7.3.

2. Options (items are in priority order and to be priced separately):

a. Option 1: Altitude Static Test with Thrust Termination System – fabricating and static firing a demonstration motor test at simulated altitude conditions.

i. The test shall also demonstrate the proposed forward thrust reversal / termination requirement during tail-off per SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document, paragraphs 3.2.1.7.1.2 and 3.2.1.7.3. The motor test will be conducted at Arnold Engineering Development Center (AEDC) at Tullahoma, TN.

ii. Contractor shall be responsible for motor shipment and all costs associated with planning and test conduct.

iii. Facility power may be assumed for static fire operations, no battery will be required for this test.

b. Option 2: Early Thrust Termination Test – The static test of a demonstration motor will be conducted at ambient (sea level) conditions. The test shall demonstrate the proposed forward thrust reversal / termination requirement. Per the requirements of SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document, paragraphs 3.2.1.7.1.2 and 3.2.1.7.3.

c. Option 3: Flight Weight Chamber Structural Load and Burst Test – fabrication, structural load, and hydro burst demonstration testing of a motor case built to the flight design suitable for case burst testing. Use loads specified in SDL-63-2013- 01 Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document, paragraph 3.3.8.1.2.

d. Option 4: Sea Level Static Test of a Flight Weight Designed Motor – Design, fabrication and static test of a Flight weight designed motor will be conducted at ambient (sea level) conditions to obtain baseline characterization of the motor performance. There will be no test of the thrust termination system on this static test.

II. Deliverables:

A. Integrated Program Management Report IAW CDRL A001, DID # DI-MGMT-81861 Project or Primavera format

B. Quality Assurance Program Plan IAW CDRL A006, DID # DI-QCIC-81794 Contractor format

C. Operations Security (OPSEC) Plan IAW CDRL A007, DID # DI-MGMT-80934C

Page 7 of 11 19 April 2013

D. Program Status Reports IAW CDRL A010, DID # DI-MGMT-80368A

E. Contractor Funds Status Report IAW CDRL A008, DID # DI-MGMT-81468

F. Technical Report – Study / Services (Final Report) IAW CDRL A016, DID # DI-MISC- 80508B/T

G. Technical Report – Study / Services (Small Business) IAW CDRL A017, DID # DI- MISC-80508B/T, per paragraph IV of BAA FD2020-13-50035.

H. Safety Assessment Report (SAR) IAW CDRL A018, DI-SAFT-80102B

I. System Safety Program Plan IAW CDRL A019, DID # DI-SAFT-81626

J. Risk Management Status Report IAW CDRL A020, DID # DI-MGMT-81809

K. Final report IAW CDRL A009, Contract Summary Report, DID # DI-ADMN-80447A/T that summarizes the total contracted technical performance including design drawings, specifications, analyses and results of component and motor testing.

L. Property Control Report IAW CDRL A021, Property Control Report, DID # DI-MISC- 81420/T

M. Data Items as stipulated in Exhibit A below

N. Software: None

O. Hardware: None

Page 8 of 11 19 April 2013

EXHIBIT A

ITEM Para.

Ref.

TITLE DID FREQUENCY

A001 II.A Integrated Program Management Report

DI-MGMT-81861

Project or

Primavera format

Due on the 15th of each month following contract award.

A002 I.D.3

I.D.4 Conference Agenda (Meeting Agenda)

DI-ADMN-81249A Monthly

A003 I.D.3 I.D.4 I.D.5

Briefing Materials DI-MGMT-81605 ASREQ

A004 I.D.3 I.D.4

Report, Record of Meeting Minutes

DI-ADMN-81505 Meeting minutes due 15 CD after meeting

A005 I.D.2 I.D.3.a

Program Management Plan (PMP)

DI-MGMT-81797 ONE/R

A006 II.C Quality Assurance Program Plan

DI-QCIC-81794

Contractor format

Due NLT 30 CD after contract award

A007 II.D Operations Security (OPSEC) Plan

DI-MGMT-80934C Due 60 days after contact award.

Contractor’s format acceptable

A008 II.G Contractor Funds Status Report

DI-MGMT-81468 Qtrly

A009 II.P Contract Summary Report

DI-ADMN-

80447A/T

ONE/R

A010 II.F Status Report DI-MGMT-80368A Qtrly

A011 I.C.4 TEST PLAN DI-NDTI-80566A ONE/R

A012 I.C.4 Test Procedures DI-NDTI-80603A A013 I.C.4 Test/Inspection Report DI-NDTI-80809B For report, due 60 CD after test.

A014 I.D.5.a Conceptual Design

Drawings/Models

DI-SESS-81001D 2TIMES

A015 I.D.3.c I.D.5.a

Technical Report – Study/Services

DI-MISC-

80508B/T

ONE/R

A016 II.L Technical Report – Study / Services (Final Design Certification Report)

DI-MISC-

80508B/T

A017 II.M Technical Report – Study / Services (Small Business)

DI-MISC-

80508B/T

Due 60 days after contact award.

Contractor’s format acceptable

A018 II.N Safety Assessment Report

(SAR)

DI-SAFT-80102B Due 60 days after contact award.

Contractor’s format acceptable

A019 II.O System Safety Program DI-SAFT-81626 Due 60 days after

Page 9 of 11 19 April 2013

Plan contact award.

Contractor’s format acceptable A020 II.P Risk Management Status

Report DI-MGMT-81809 Due quarterly

Contractor’s format acceptable

A021 II.R Property Control Report DI-MISC-81420/T

Page 10 of 11 19 April 2013

SECTION B

AWARD INFORMATION

I. Anticipated Award Date: TBD

II. Contract Type: Cost Plus Fixed Fee

III. Number of awards anticipated: None, one or more than one

Page 11 of 11 19 April 2013

SECTION C

BIDDER’s LIBRARY

I. BIDDER’S LIBRARY: The applicable documents listed in the SOO which contain data necessary for the execution of this requirement are available upon request for review. The MCS Program Manager (PM) must be notified via email at minimum one week prior to requesting review of the applicable documents. Once the MCS PM is notified, visit requests must be submitted to the ICBM Systems Directorate security office (SMO Code: HP1MFGKQ).

Document review is limited to four (4) individuals per company with a maximum time limit of two hours per visit. Visits are limited to three (3) per company.

A. S-133-06658(A), Pt. I, MOTOR, ROCKET, SOLID PROPELLANT MODEL SR73 AJ-1, Prime Item Development Specification

B. S-133-128C, Appendix I & III

C. ICD 25-60032, Interface Control Stage III Motor Envelope

D. SDL-63-2013-01, Propulsion Application Program (PAP) Medium Class Stage (MCS) III Motor Technical Requirements Document

SECTION A
STATEMENT OF OBJECTIVES (SOO)/NEEDS
SECTION B
AWARD INFORMATION
SECTION C
BIDDER’s LIBRARY

File details come from the government source that posted it. Updated .