FA8213-16-R-3047_Questions_and_Answers.pdf

PDF 76 KB Posted

Attached to
SELECTOR, EJECTION SEQUENCE Federal contract opportunity
Solicitation number
FA8213-16-R-3047
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Contractor Questions/Comments and the Government's Responses

View the file

Other files for this federal contract opportunity

Other files attached to SELECTOR, EJECTION SEQUENCE, newest first.
File Type Posted
FA821316R3047_______0001.RTF RTF text file
FA821316R3047_RepShip_16-50079.pdf PDF
FA821316R3047_QALI1650079.pdf PDF
FA821316R3047_RepairDataLists.pdf PDF
FA821316R3047_SPI_F003493943.pdf PDF
FA821316R3047.RTF RTF text file
FA821316R3047_JFQR_1377003493943ES_Redacted.pdf PDF
FA821316R3047_CPM_EXCELL_SPREADSHEET.xlsx XLSX spreadsheet
FA821316R3047_Appendix_A.pdf PDF
FA821316R3047_SOWPackaging_1650079.pdf PDF
FA821316R3047_SGFP_Form.pdf PDF
FA821316R3047_CADPAD_MarkingInstr_1650079.pdf PDF
FA821316R3047_JFQR_1377014374075ES_Redacted.pdf PDF
FA821316R3047_CDRLs.pdf PDF
FA821316R3047_JFQR_1377014799295ES_Redacted.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: July 8, 2016

The following are contractor questions/comments and the Government’s responses that arose from solicitation FA8213‐16‐R‐3047:

Contractor’s Question/Comment A significant number of years have passed since the contractor has last made the units solicited and not knowing the condition of the units to be remanufactured it may be more cost effective to manufacture new items.

Government’s Response At this time the Government only has funding for the remanufacture of the units rather than manufacture new units.

Contractor’s Question/Comment The contractor has not previously refurbished the units solicited and will required no‐recurring expenses for paperwork which would be amortized into the pricing.

Government’s Response The Government understands that if a contractor has not previously refurbished/remanufactured this item that a first article expense and possible non‐recurring expenses will be added into the unit price. Please include such expenses into your company’s proposal.

Contractor’s Question/Comment The contractor manufactures a similar part as the one solicited. If Hill is able to replace the part solicited with the part the contractor currently manufactures there would be very little non‐recurring expenses cost and a lower overall price.

Government’s Response Contractors may include in their proposal different part numbers and the cost to work out the procedures necessary for the alternate part to replace the one listed in the solicitation. Such proposed change procedures will be evaluated. Please note that this is still intended to be a remanufactured item and a first article will still be necessary.