Brand Name Justification and Approval
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8126-15-Q-0214.pdf | ||
| Draft_Item_Description_IMO_Pumps.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification and Approval (J&A) for Other Than Full and Open Competition
Choose the funding level for this J&A Document:
Contracting Activity: AFSC-PZIMB
Purchase Request / Local ID Number:
Program / Project (and PE, if applicable): Purchase Colfax/IMO Pumps
Program Type (PEO or Other Contracting): Other Contracting
Authority (include full title):
Estimated Contract Cost (including options): J&A Type: Class Individual
COORDINATION (A F F A R S 5 3 0 6 . 3 0 4 ( a) ) ** To remove a row, click the "X" next to the signature block.
** To restore the row, click the appropriate link to the right: CO PM CSO Legal COCO CA SCO PEO AQC AQ Blank-1 Blank-2
X
APPROVAL (A F F A R S 5 3 0 6 . 3 0 4 ( a) ) ** To remove a row, click the "X" next to the signature block.
** To restore the row, click the appropriate link to the right: COCO CO CA PEO SPE Blank
NOTE: If a Justification and Approval was approved for the preceding acquisition, a copy of the approved J&A for the predecessor action must be included in the staff package for approval of the instant J&A. This applies to J&A staff packages that are submitted for review and approval at a level above the contracting officer. The predecessor J&A will be used as a reference document by the approving official.
Sign and Save Procedure
Date Contracting Officer Corey VanWoerkom
AFSC/PZIMB,
Signature
Date Project Lead / Program Mgr / Requiring Activity
Date Contracting Officer Corey VanWoerkom
AFSC/PZIMB
Note 1: See guidance at the end of this document for completing the following sections.
Note 2: Each field will expand automatically if additional space is needed.
I. Contracting Activity.
AFSC/PZIMB, (PR # F3YCHC5198A001)
3001 Staff Drive Tinker AFB, OK 73145
II. Nature and/or description of the action being processed.
This anticipated new Firm Fixed Price contract for CMXG is to replace the aging pumps in Bldg. 3907 Fuel Test Facility with OEM Pumps.
The pumps have been in service since the early 1990's and are now showing signs of their age.
(leaks, fluctuating pressures). The parent system they are attached to is a "Hard Line System" meaning they (pumps) are welded into place with Stainless Steel pipe and fittings. To replace the whole system, for new pumps, would be extremely expensive material wise, and will require the recertification of the entire fuel testing facility. These pumps are the foundation of that entire building and her workload (3907).
III. Description of supplies/services required to meet agency needs.
This is a request for Colfax/IMG Brand Pumps.
(2ea) 85200RDW @ $ each Colfax/IMO Pump: Total $ (2ea) 83250RDW @ $ each Colfax/IMO Pumps: Total $ (8ea) 55063RDW035 @ each Colfax/IMO Pumps: Total $
Total for Requirement is $ EDD is Estimated at 8 weeks After Award.
IV. Statutory authority permitting Other than Full and Open Competition.
6.301-1(c) 10USC 2304(c) (1), As implemented by FAR 6.302-1 (c) Due to parent system design, no other brands/MFGS, can be considered.
V. Demonstration that the contractor's unique qualifications or nature of the acquisition requires the use of the authority cited above (applicability of authority).
Colfax/IMO is the OEM for the existing pump system in Bldg. 3907. The Pumps requested are a direct bolt-on replacement.
The pumps have been in service since the early 1990's and are now showing signs of their age (leaks, fluctuating pressures). The parent system they are attached to is a "Hard Line System" meaning they (pumps) are welded into place with Stainless Steel pipe and fittings. To replace the whole system, for new pumps, would be extremely expensive material wise, and will require the recertification of the entire fuel testing facility.
It is estimated that the cost of re-engineering for new pumps would be in excess of $ each based on FEMWEB costs (OC#s 13313, 11893, 13312) of each pump system. The time estimated to re-engineer the system is approximately three months. Lost revenue can be estimated to be in range. These pumps are the foundation of that entire building and her workload (3907).
VI. Description of efforts made to ensure that offers are solicited from as many potential sources as practicable.
In future design requirements, systems will be designed with multiple sources to not create a single point of failure.
VII. Determination by the Contracting Officer that the anticipated cost to the Government will be fair and reasonable.
The contracting officer will ensure price is fair and reasonable to the Government. Price analysis will be conducted IAW FAR15.404-1. The contracting officer anticipates using adequate price analysis in order to determine price is reasonable.
VIII. Description of the market research conducted and the results, or a statement of the reasons market research was not conducted.
The market research concluded that no other manufacture could supply the pump other than Colfax/IMO. CMXG has considered other Brands and concluded that the down-time, training and recertification of a new pump to be cost prohibitive.
The market research was conducted from June 29, 2015 to July 15, 2015 by Internet search (using Bing, Google, and Yahoo), telephone calls to vendors interested in bidding, and telephone calls to IMO/CIG-Colfax (who does not sell direct) resulted in the local vendor Best Pumpworks in Tulsa, OK and United Commercial Supply in South Park, PA.
Communications to Best Pump works in Tulsa were by phone on 6/26/2015 with Mark Weidmann and email traffic from Brian Worley and David Bishop on 6/29/2015 that resulted in a ROM on 7/15/2015.
Communications to United Commercial Supply were by phone/email with Jackie Boff on 7/30/2015 that resulted in a ROM on 7/30/2015.
IX. Any other facts supporting the use of Other Than Full and Open Competition.
X. List of sources, if any, that expressed interest in the acquisition.
United Commercial Supply, Best Pumpworks, POC Jackie Boff, 877-827-8665 POC Brain Worley, 918-664-4822 Cage Code: 4EWP0 Cage Code: 3AU26
XI. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before making subsequent acquisitions for the supplies or services required.
At this time, this requirement is to sustain a fully fielded system, and no new development is required. if this portion of the system is redesigned in the future, there would be opportunity for full and open competition.
XII. Certification by the Contracting Officer.
As evidenced by my signature above, I have determined this document to be both accurate and complete to the best of my knowledge and belief.
XIII. Certification by the technical/requirements personnel.
As evidenced by my signature above, I certify that any supporting data contained herein, which is my (our) responsibility, is both accurate and complete.
Remove the Guidance pages below. Remove the IACR pages below.
| Choose the funding level for this J&A Document: |
| Purchase Request / Local ID Number: |
| X |
| X |
| I. Contracting Activity. |
| II. Nature and/or description of the action being processed. |
| III. Description of supplies/services required to meet agency needs. |
| IV. Statutory authority permitting Other than Full and Open Competition. |
| V. Demonstration that the contractor's unique qualifications or nature of the acquisition requires the use of the authority cited above (applicability of authority). |
| The pumps have been in service since the early 1990's and are now showing signs of their age (leaks, fluctuating pressures). The parent system they are attached to is a |
| foundation of that entire building and her workload (3907). |
| VI. Description of efforts made to ensure that offers are solicited from as many potential sources as practicable. |
| VII. Determination by the Contracting Officer that the anticipated cost to the Government will be fair and reasonable. |
| VIII. Description of the market research conducted and the results, or a statement of the reasons market research was not conducted. |
| IX. Any other facts supporting the use of Other Than Full and Open Competition. |
| XI. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before making subsequent acquisitions for the supplies or services required. |
| XII. Certification by the Contracting Officer. |
| XIII. Certification by the technical/requirements personnel. |
File details come from the government source that posted it. Updated .