This is a Standard Form 30 amendment to solicitation FA812525Q0023, issued by the Air Force Sustainment Center at Tinker AFB. The amendment adds FAR 52.212-2 Addendum which outlines the evaluation criteria for award, establishing price as the only evaluated factor. The award will be made to the vendor with the lowest total evaluated price (TEP) whose quotation conforms to solicitation requirements.
The amendment details that the government intends to award without interchanges but reserves the right to conduct them if necessary. Price quotations will be evaluated for completeness, reasonableness, realism, and unbalanced pricing. The TEP will be calculated as the sum of proposed prices for all separately priced line items in the base period. The government intends to select one contractor but reserves the right not to award depending on quote quality, prices, and fund availability. The amendment is dated January 6, 2025 and is signed by Contracting Officer Sheridan Robison.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BNJ for Geomagic Redacted.pdf | ||
| C24-030 Geomagic Design X Annual - ID.pdf | ||
| Solicitation - FA812525Q0023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Evaluation Factors for Award
The following clauses were modified:
52.212-2Evaluation-Commercial Products and Commercial Services.Nov 2021 hereby reads as follows:
As prescribed in , the Contracting Officer may insert a provision substantially as follows:12.301(c)
Evaluation-Commercial Products and Commercial Services (Nov 2021)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
____________[Contracting Officer shall insert the significant evaluation factors, such as (i) technical capability of the item offered to meet the Government requirement; (ii) price; (iii) past performance (see FAR 15.304); and include them in the relative order of importance of the evaluation factors, such as in descending order of importance.]
Technical and past performance, when combined, are [Contracting Officer state, in accordance with FAR 15.304, the relative importance of all other evaluation ____ factors, when combined, when compared to price.]
(b) . The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Options Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
Addendum to FAR 52.212-2 -- Evaluation - Commercial Items
1.0 Basis for Contract Award:
This acquisition will be conducted under the procedures of FAR Part 12 -- Commercial Items and FAR Part13 -- Simplified Acquisition Procedures. This acquisition will utilize price as the only evaluated factor. Award will be made to the vendor with the lowest total evaluated price (TEP) and whose quotation conforms to the solicitation requirements (to include all stated terms, conditions, representations, and certifications). The Government intends to award without interchanges. However, the Government reserves the right to conduct interchanges if determined necessary by the Contracting Officer (ref. FAR 52.212-2 Addendum, section 1.3).
1.1 Solicitation Requirements (Terms and Conditions)
Vendors are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and , in addition to the price factor. Failure to item description requirements comply with the terms and conditions of the solicitation may result in the vendor being ineligible for award. Vendors must clearly identify any exception to the solicitation terms and conditions and must
FA812525Q00230001
provide complete supporting rationale. reserves the right to determine any such The Government exceptions unacceptable, and the quotation, therefore, ineligible for award.
1.2 Number of Contracts to be Awarded:
The Government intends to select contractor for this acquisition. However, the Government reserves the right not to award a contract at all, depending on the one quality of the quotation, prices submitted, and the availability of funds.
1.3 Interchanges
In accordance with FAR 1.102-2(c)(3) the Government shall exercise discretion, use sound business judgement, and comply with applicable laws and regulations during the course of this acquisition. The Government intends to award without interchanges, but reserves the right to conduct interchanges if necessary.
Therefore, it is imperative that vendors submit their best terms initially. If during the evaluation of quotations it is determined to be in the best interest of the Government to conduct interchanges, the Contracting Officer may conduct interchanges with one, some, or all vendors before issuing any purchase order.
Interchanges are information sharing between the Government and vendors after receipt of quotations which can be conducted to address any aspect of the quotation. Interchanges may be oral or written. Written interchanges take the form of Interchange Notices (IN)s. INs are used to accurately capture contemporaneous sharing of information. If interchanges are conducted, the Government may request final quotation revisions at the conclusion of interchanges.
2.0 Evaluation Factor:
2.1. Factor 1 - Price
Price quotations will be evaluated as follows:
2.1.1 Completeness
Quotations will be reviewed for completeness. will be considered ineligible for award. Incomplete quotes
2.1.2 Price Reasonableness
The proposed prices will be evaluated for reasonableness. Reasonableness must represent a price to the Government a prudent person would pay in the conduct of competitive business. Normally, price reasonableness is established through adequate price competition, but may also be determined through price analysis techniques as described in FAR 15.404-1(b)(2).
2.1.3 Price Realism
The Government intends to determine price realism based on adequate price competition. In the event the Government cannot determine price realism based on adequate price competition, the Government reserves the right to conduct a more detailed price realism evaluation using one or more of the price analysis techniques described in FAR15.404-1(b)(2). The Government may also use other evaluation techniques, as needed. To be realistic, the proposed price must demonstrate an adequate understanding of the requirement. that are determined to be unrealistically low due to an inadequate understanding of the Quoted prices requirement will make the quotation ineligible for award.
2.1.4 Unbalanced Pricing
Vendors' quotations will be reviewed for unbalanced pricing. The Government will evaluate any supporting information provided by the vendor explaining variances that appear unbalanced. Evaluated quotes that are determined to be unbalanced may be deemed ineligible for award by the Contracting Officer if a determination is made that lack of balance poses an unacceptable risk to the Government. Unbalanced pricing exists when, despite an acceptable total price, the price of one or more line items (including sub line items) is significantly over or understated as demonstrated by application of price analysis techniques, such that:
a) There is reasonable doubt the quote would result in the lowest overall cost to the Government, even though it is the lowest priced quote; or
b) The quote is so grossly unbalanced; its acceptance would be tantamount to allowing an advanced payment.
2.1.5 Total Evaluated Price (TEP)
The TEP will be calculated as the sum of the total proposed prices for all separately priced line items (including sub line items). The total proposed price for each separately priced line item shall be calculated as the proposed unit price multiplied by the corresponding quantity.
The total proposed price for all line items will be added together as a part of the TEP calculation.
The TEP will be used for evaluation purposes only.
The TEP will be calculated as the sum of the vendor's proposed prices for the base period.
(End of provision)
| SUMMARY OF CHANGES |
| Evaluation Factors for Award |
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0001 |
| EffDate: 06 Jan 2025 |
| ReqNo: |
| ProjNo: |
| IssCode: FA8125 |
| AdmCode: |
| IssuedBy: FA8125 AFSC PZIMA |
3001 STAFF DR STE 2S76, CP 405 734 9107
TINKER AFB, OK 73145-3303
UNITED STATES
SHANA MANDLEY, Email: shana.mandley@us.af.mil Telephone: 405-739-4148 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA812525Q0023 |
| SolDate: 06 Jan 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: The purpose of this amendment is to add the 52.212-2 Addendum. All other terms and conditions remain in full force and effect. |
| ContNameTitle: |
| CoNameTitle: Sheridan Robison |
| ContDate: |
| CODate: 06 Jan 2025 |
File details come from the government source that posted it. Updated .